8403 S TRUXTON AVE 90045
Certificate Information: 8403 S TRUXTON AVE 90045
- Application / Permit
- 21016-10000-00170
- Plan Check / Job No.
- B20LA24351
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of an (E) detached 2-car garage into an ADU per State Law GCS 65852.2(e)(1)(A). Including new attached front porch.
- Permit Issued
- Issued on 9/7/2021
- Issuing Office
- Current Status
- CofO Issued on 3/10/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2021 | HELEN NGUYEN |
| Corrections Issued | 1/6/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/6/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 4/29/2021 | HELEN NGUYEN |
| Plan Check Approved | 5/21/2021 | HELEN NGUYEN |
| Issued | 9/7/2021 | APPLICANT |
| CofO in Progress | 3/9/2023 | BOBBY KEY |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
| CofO Issued | 3/10/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/10/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Specific Plan | Cleared | 3/23/2021 | EILEEN HUNT |
| Address approval | Cleared | 3/26/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/26/2021 | DINAH GARIN |
| Sewer availability | Cleared | 3/26/2021 | DINAH GARIN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Morales,, Carlos A; Lic. No.: C69972 | 38100 SAN MATEO AVE PALMDALE, CA 93551 |
| Engineer | Zhong,, Raymond Meng; Lic. No.: M27635 | 2416 W VALLEY BLVD ALHAMBRA, CA 91803 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/22/2021 | Corrections Issued | DAVID FEILER |
| PLUMBING-Rough | 10/22/2021 | Not Ready for Inspection | DAVID FEILER |
| BUILDING-Rough-Frame | 1/25/2022 | Not Ready for Inspection | BOBBY KEY |
| Footing/Foundation/Slab | 1/25/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 1/25/2022 | Partial Approval | BOBBY KEY |
| Excavation/Setback/Form/Re-Bar | 2/11/2022 | Approved | BOBBY KEY |
| Footing/Foundation/Slab | 2/11/2022 | Partial Approval | BOBBY KEY |
| Footing/Foundation/Slab | 2/15/2022 | Corrections Issued | BOBBY KEY |
| Footing/Foundation/Slab | 2/17/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 3/10/2022 | Partial Approval | BOBBY KEY |
| ELECTRICAL-Rough | 4/18/2022 | Approved | BOBBY KEY |
| Floor/Roof Diaphrgm/Shear Wall | 4/18/2022 | Partial Approval | BOBBY KEY |
| Gas Test | 4/18/2022 | Corrections Issued | BOBBY KEY |
| PLUMBING-Rough | 4/18/2022 | Approved | BOBBY KEY |
| Underground Mechanical | 4/18/2022 | Approved | BOBBY KEY |
| Deputy Wood Construction | 4/19/2022 | Conditional Approval | BOBBY KEY |
| Green Building Rough | 4/28/2022 | Approved | BOBBY KEY |
| Insulation | 4/28/2022 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 4/28/2022 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 5/4/2022 | Approved | BOBBY KEY |
| HVAC-Rough | 5/4/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 5/11/2022 | Approved | CLAYTON GRAHAM |
| Gas Test | 6/1/2022 | Approved | RICHARD STEINBACH |
| Final | 10/17/2022 | Corrections Issued | BOBBY KEY |
| ELECTRICAL-Final | 12/1/2022 | Corrections Issued | HERBERT GIRON |
| Final | 12/1/2022 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 12/1/2022 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Final | 12/1/2022 | Corrections Issued | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 12/1/2022 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 12/1/2022 | Corrections Issued | HERBERT GIRON |
| Final | 3/8/2023 | OK to Issue CofO | BOBBY KEY |
| Smoke Detectors | 3/8/2023 | Approved | BOBBY KEY |