7405 N COLLETT AVE 91406
Certificate Information: 7405 N COLLETT AVE 91406
- Application / Permit
- 21016-10000-00132
- Plan Check / Job No.
- B21LA00089
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. CONVERT (E) DETACHED CARPORT, RECREATION ROOM, AND STORAGE ROOM TO ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c)-(d). NEW PATIO COVER ADDITION. COMPLY WITH DEPARTMENT ORDER effective date 08/12/2019. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 4/28/2021
- Issuing Office
- Current Status
- Issued on 4/28/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2021 | KEVIN MORALES |
| Corrections Issued | 1/6/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 4/7/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 4/7/2021 | LARRY LEE |
| Plan Check Approved | 4/8/2021 | KEVIN MORALES |
| Issued | 4/28/2021 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 1/7/2021 | ABDULLAH SADOZAI |
| Eng Process Fee Ord 176,300 | Cleared | 1/7/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/7/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/7/2021 | JOHN TRIANTAFYLLOS |
| Construction near power lines | Cleared | 4/2/2021 | RIDWAN HARDY |
Contact Information
| Architect | Cohan,, Joseph; Lic. No.: C37739 | 1302 MANNING AVENUE LOS ANGELES, CA 90024 |
| Contractor | Owner-Builder | , |
Inspector Information
| MICHAEL CORTEZ, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
| WILLIAM WREN, (818) 374-1176 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/25/2021 | Approved | ARTHUR SARGSYAN |
| Sewer | 6/23/2021 | Not Ready for Inspection | JACK KARGODORIAN |
| Sewer | 6/29/2021 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 10/20/2021 | Not Ready for Inspection | RAUL OLAGI |
| Green Building Rough | 10/20/2021 | Not Ready for Inspection | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 10/20/2021 | SGSOV Not Ready | RAUL OLAGI |
| Underground Mechanical | 10/20/2021 | Corrections Issued | RAUL OLAGI |
| Gas Test | 10/27/2021 | Corrections Issued | ALAN MORELOS |
| Underground Mechanical | 11/1/2021 | Approved | RAUL OLAGI |
| BUILDING-Rough-Frame | 11/15/2021 | Not Ready for Inspection | RAUL OLAGI |
| ELECTRICAL-Rough | 6/3/2025 | Partial Approval | OGANES TARAKHCHYAN |
| HVAC-Rough | 6/3/2025 | Partial Approval | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/18/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2025 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Shower Pan | 10/17/2025 | Approved | GAREN HAYRAPETYAN |
| Floor/Roof Diaphrgm/Shear Wall | 10/29/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Insulation | 10/29/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 10/29/2025 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Interior/Exterior Lathing | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Wood Frame | 12/2/2025 | Approved | GAREN HAYRAPETYAN |
| Insulation | 2/12/2026 | Approved | MICHAEL CORTEZ |
| Drywall Nailing | 2/19/2026 | Approved | GAREN HAYRAPETYAN |
| Green Building Rough | 2/19/2026 | Approved | GAREN HAYRAPETYAN |