4034-4034 1/2 W 63RD ST 90043

Certificate Information: 4034-4034 1/2 W 63RD ST 90043

Application / Permit
21016-10000-00129
Plan Check / Job No.
B20LA24348
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
**eplan** CONVERSION OF LOWER LEVEL TO ACCESSORY DWELLING UNIT PER ORDINANCE (358 S.F. EXISTING HABITABLE SPACE + 689 S.F. NON-HABITABLE SPACE) OF (E) 1-STORY HOUSE WITH BASEMENT NO ALTERATIONS ARE INTENDED TO THE EXISTING BUILDING EXTERIOR OR BUILDING FOOTPRINT. COMPLY WITH DEPARTMENT ORDER effective date 12/05/2013. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE. All permits shall be for the same time period limitation. If additional assistance is needed, please call Inspector TIM FONG at (213)252-3959. CEIS Case Number is 487555.
Permit Issued
Issued on 5/25/2021
Issuing Office
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/5/2021 APPLICANT
Assigned to Plan Check Engineer 1/14/2021 MONICA RAMIREZ
Corrections Issued 1/19/2021 MONICA RAMIREZ
Quality Review Completed 2/2/2021 HERNAN ARREOLA
Applicant returned to address corrections 3/22/2021 MONICA RAMIREZ
Applicant returned to address corrections 4/19/2021 MONICA RAMIREZ
Applicant returned to address corrections 4/28/2021 MONICA RAMIREZ
Applicant returned to address corrections 5/18/2021 MONICA RAMIREZ
Plan Check Approved 5/20/2021 MONICA RAMIREZ
Issued 5/25/2021 APPLICANT
CofO in Progress 10/1/2021 FREDDIE RIVERA
No Progress 11/8/2021 FREDDIE RIVERA
CofO in Progress 11/18/2021 HORACE FULTZ
Permit Finaled 12/17/2021 DEROLD HAUFF
Permit Finaled 12/17/2021 DEROLD HAUFF
CofO Issued 12/17/2021 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/23/2021 THOMAS LANG
Sewer availability Cleared 2/23/2021 THOMAS LANG
Address approval Cleared 3/23/2021 THOMAS LANG

Contact Information

Architect Grant,, Thurman; Lic. No.: NA30285       ,
Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 6/9/2021 Approved FREDDIE RIVERA
ELECTRICAL-Rough 7/7/2021 Partial Approval ANSON MAGLASANG
Insulation 7/7/2021 Partial Approval ANSON MAGLASANG
Light Gage Steel Frame 7/7/2021 Partial Approval ANSON MAGLASANG
Drywall Nailing 7/20/2021 No Access for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 7/26/2021 Partial Approval FREDDIE RIVERA
Drywall Nailing 7/26/2021 Partial Approval FREDDIE RIVERA
ELECTRICAL-Rough 7/26/2021 Approved FREDDIE RIVERA
Green Building Final 7/26/2021 Approved FREDDIE RIVERA
Insulation 7/26/2021 Approved FREDDIE RIVERA
Drywall Nailing 8/9/2021 Approved FREDDIE RIVERA
PLUMBING-Rough 8/9/2021 Approved FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 9/2/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 9/14/2021 Not Ready for Inspection FREDDIE RIVERA
Final 9/14/2021 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 9/14/2021 Approved FREDDIE RIVERA
Green Building Rough 9/14/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/14/2021 SGSOV Not Ready FREDDIE RIVERA
Smoke Detectors 9/14/2021 Approved FREDDIE RIVERA
BUILDING-Rough-Frame 9/22/2021 Not Ready for Inspection FREDDIE RIVERA
Final 9/22/2021 Not Ready for Inspection FREDDIE RIVERA
Green Building Rough 9/22/2021 Not Ready for Inspection FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/22/2021 SGSOV Not Ready FREDDIE RIVERA
BUILDING-Rough-Frame 9/28/2021 Approved FREDDIE RIVERA
Final 9/28/2021 OK to Issue CofO FREDDIE RIVERA
Green Building Rough 9/28/2021 Approved FREDDIE RIVERA
SGSOV-Seismic Gas S/O Valve 9/28/2021 SGSOV Approved FREDDIE RIVERA
Final 9/30/2021 OK to Issue CofO FREDDIE RIVERA