5118 E ITHACA AVE 90032

Certificate Information: 5118 E ITHACA AVE 90032

Application / Permit
21016-10000-00128
Plan Check / Job No.
B20LA24347
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
E Plan INTERIOR REMODEL TO CONVERT DINING ROOM TO BEDROOM AND CONVERT EXISTING lower level to RECROOM
Permit Issued
Issued on 4/9/2021
Issuing Office
Current Status
CofO Issued on 8/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2021 APPLICANT
Assigned to Plan Check Engineer 1/28/2021 ARSALAN SHABESTARI
Corrections Issued 2/2/2021 ARSALAN SHABESTARI
Quality Review Completed 2/23/2021 HERNAN ARREOLA
Applicant returned to address corrections 3/14/2021 ARSALAN SHABESTARI
Plan Check Approved 4/7/2021 ARSALAN SHABESTARI
Issued 4/9/2021 APPLICANT
CofO in Progress 9/3/2022 AMY COLIN
CofO Issued 8/7/2023 DEROLD HAUFF
Permit Finaled 8/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Sewer availability Cleared 2/18/2021 CELINA MORENO
"D" conditions Cleared 3/24/2021 RICHARD REASER
"Q" conditions Cleared 3/24/2021 RICHARD REASER
Miscellaneous Cleared 3/24/2021 RICHARD REASER

Contact Information

Contractor Owner-Builder       ,
Engineer Medina,, Armando; Lic. No.: NA83911       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/6/2021 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 7/6/2021 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 7/6/2021 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 7/6/2021 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 7/19/2021 Corrections Issued OSVALDO PARAMO
Wood Frame 7/19/2021 Partial Approval OSVALDO PARAMO
PLUMBING-Rough 8/17/2021 Corrections Issued COREY HUPP
PLUMBING-Rough 8/18/2021 Not Ready for Inspection COREY HUPP
Insulation 8/20/2021 Approved JUSTIN CURTIS
PLUMBING-Rough 8/20/2021 Approved JUSTIN CURTIS
ELECTRICAL-Rough 8/23/2021 Corrections Issued COREY HUPP
ELECTRICAL-Rough 9/17/2021 Approved COREY HUPP
ELECTRICAL-Final 8/15/2022 Corrections Issued AMY COLIN
PLUMBING-Final 8/15/2022 Corrections Issued AMY COLIN
BUILDING-Rough-Frame 8/23/2022 Approved AMY COLIN
ELECTRICAL-Final 8/23/2022 Approved AMY COLIN
Final 8/23/2022 Partial Approval AMY COLIN
Green Building Final 8/23/2022 Approved AMY COLIN
Green Building Rough 8/23/2022 Approved AMY COLIN
PLUMBING-Final 8/23/2022 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 8/23/2022 SGSOV Approved AMY COLIN
Smoke Detectors 8/23/2022 Approved AMY COLIN
ELECTRICAL-Final 8/24/2022 Approved SCOTT FINNILA
Final 9/3/2022 OK to Issue CofO AMY COLIN