924 S HARVARD BLVD 90006

Certificate Information: 924 S HARVARD BLVD 90006

Application / Permit
21016-10000-00119
Plan Check / Job No.
B21LA00083
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF REAR YARD STORAGE INTO (N) DETTACHED ADU PER ORDINANCE 186,481; ALL WORK DONE PER WFPP
Permit Issued
Issued on 1/10/2022
Issuing Office
Current Status
CofO Issued on 9/6/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 SINA KHOSRAVI
Corrections Issued 1/14/2021 SINA KHOSRAVI
Applicant returned to address corrections 2/9/2021 SHANGQIN XIE
Plan Check Approved 12/15/2021 RICARDO RAMIREZ
Issued 1/10/2022 APPLICANT
Building Plans Picked Up 1/11/2022 APPLICANT
CofO in Progress 3/7/2024 ARTHUR NEGRETE
No Progress 3/7/2024 ARTHUR NEGRETE
CofO in Progress 3/7/2024 ARTHUR NEGRETE
Permit Finaled 9/6/2024 RUBEN SALAS
CofO Issued 9/6/2024 RUBEN SALAS
Permit Finaled 9/6/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 1/28/2021 CECILIO NAVARRO
Low Impact Development Cleared 8/26/2021 ANDRES COVARRUBIAS
Historic Resource Verification Cleared 10/8/2021 MICAELA TORRES-GIL
Redevelopment Project Area Cleared 10/22/2021 DAVID URITA
Eng Process Fee Ord 176,300 Cleared 10/26/2021 THAN WIN
Sewer availability Cleared 10/26/2021 THAN WIN
Public Works-Highway Ded. Cleared 2/16/2024 MANLEEN UBHI
Public Works-Open Permits Cleared 2/16/2024 MANLEEN UBHI
Public Works-Sewers Cleared 2/16/2024 MANLEEN UBHI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 5/9/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 5/9/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Pre-Inspection 6/3/2022 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 5/17/2023 Corrections Issued KATHRYN BUTTERWORTH
Wood Frame 5/17/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/14/2023 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 8/14/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 8/21/2023 Partial Approval KATHRYN BUTTERWORTH
Insulation 8/21/2023 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Rough 8/21/2023 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 10/19/2023 Corrections Issued KATHRYN BUTTERWORTH
ELECTRICAL-Rough 10/19/2023 Corrections Issued KATHRYN BUTTERWORTH
Footing/Foundation/Slab 10/19/2023 Approved KATHRYN BUTTERWORTH
HVAC-Rough 10/19/2023 Corrections Issued KATHRYN BUTTERWORTH
Insulation 10/19/2023 Corrections Issued KATHRYN BUTTERWORTH
Interior/Exterior Lathing 11/21/2023 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Final 12/27/2023 Corrections Issued BRENDAN MORELLI
ELECTRICAL-Final 1/23/2024 Approved RICHARD DOCKUS
PLUMBING-Final 1/23/2024 Approved RICHARD DOCKUS
Final 2/7/2024 Not Ready for Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Not Ready ARTHUR NEGRETE
Smoke Detectors 2/7/2024 Approved ARTHUR NEGRETE
Final 3/5/2024 Partial Inspection ARTHUR NEGRETE
SGSOV-Seismic Gas S/O Valve 3/5/2024 SGSOV Approved ARTHUR NEGRETE
Final 3/6/2024 OK to Issue CofO ARTHUR NEGRETE
HVAC-Final 3/6/2024 Approved ARTHUR NEGRETE
HVAC-Rough 3/6/2024 Approved ARTHUR NEGRETE