12654 W MOORPARK ST 91604
Certificate Information: 12654 W MOORPARK ST 91604
- Application / Permit
- 21016-10000-00115
- Plan Check / Job No.
- B21LA00080
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL (2) GRADE BEAMS AND USING (4) SPECIAL CANTILEVER COLUMN SYSTEMS.
- Permit Issued
- Issued on 4/27/2021
- Issuing Office
- Current Status
- CofC Issued on 8/4/2021
Permit Application Status History
| Submitted | 1/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | VARAND SARKISIAN |
| Corrections Issued | 1/19/2021 | VARAND SARKISIAN |
| Quality Review Completed | 1/20/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 2/24/2021 | VARAND SARKISIAN |
| Plan Check Approved | 3/4/2021 | VARAND SARKISIAN |
| Issued | 4/27/2021 | APPLICANT |
| OK for CofC | 8/4/2021 | JEFFREY DURAN |
| CofC Issued | 8/4/2021 | JEFFREY DURAN |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 4/20/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | Alpha Structural Inc; Lic. No.: 663409-B | 8334 FOOTHILL BLVD SUNLAND, CA 91040 |
| Engineer | Demers,, Joe Alan; Lic. No.: C71535 | 894 SANTA MARIA CIRCLE DUARTE, CA 91010 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/6/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Excavation/Setback/Form/Re-Bar | 5/27/2021 | Approved | JOE VELASQUEZ |
| Wood Frame | 5/27/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Wood Frame | 5/28/2021 | Partial Approval | JOE VELASQUEZ |
| Insulation | 6/2/2021 | Approved | JOE VELASQUEZ |
| Deputy Wood Construction | 6/16/2021 | No Access for Inspection | JOE VELASQUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2021 | Corrections Issued | JOE VELASQUEZ |
| Wood Frame | 6/24/2021 | Approved | JOE VELASQUEZ |
| Interior/Exterior Lathing | 7/2/2021 | Approved | JOE VELASQUEZ |
| Final | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/15/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 7/15/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 7/22/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/22/2021 | SGSOV Not Ready | JOE VELASQUEZ |
| Smoke Detectors | 7/22/2021 | Not Ready for Inspection | JOE VELASQUEZ |
| Final | 8/4/2021 | OK for CofC | JEFFREY DURAN |
| SGSOV-Seismic Gas S/O Valve | 8/4/2021 | SGSOV Approved | JEFFREY DURAN |
| Smoke Detectors | 8/4/2021 | Approved | JEFFREY DURAN |