10341-10343 N VENA AVE 91331
Certificate Information: 10341-10343 N VENA AVE 91331
- Application / Permit
- 21016-10000-00091
- Plan Check / Job No.
- B21LA00053
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) RECREATION ROOM ON 2ND FLOOR TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A). NEW FIRST FLOOR ADDITION AT REAR. COMPLY WITH DEPARTMENT ORDER effective date 11/03/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
- Permit Issued
- Issued on 3/1/2021
- Issuing Office
- Current Status
- CofO Issued on 7/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/5/2021 | KEVIN MORALES |
| Corrections Issued | 1/5/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 1/26/2021 | JOE VO |
| Plan Check Approved | 2/16/2021 | MONICA RAMIREZ |
| Issued | 3/1/2021 | APPLICANT |
| CofO in Progress | 7/7/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 7/22/2025 | RUBEN SALAS |
| CofO Issued | 7/22/2025 | RUBEN SALAS |
| Permit Finaled | 7/22/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Eng Process Fee Ord 176,300 | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Roof/Waste drainage to street | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
| Sewer availability | Cleared | 1/27/2021 | JOHN TRIANTAFYLLOS |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Papayans,, Michael Serge; Lic. No.: C44891 | 517 PASEO LUNADO PALOS VERDES ESTATES, CA 90274 |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/12/2022 | Partial Approval | JENNIFER RABUCHIN |
| METHANE-Barrier | 8/12/2022 | Approved | JENNIFER RABUCHIN |
| METHANE-Subgrade | 8/12/2022 | Approved | JENNIFER RABUCHIN |
| Insulation | 8/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| Wood Frame | 8/22/2022 | Partial Approval | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 9/7/2022 | Partial Approval | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2022 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 9/13/2022 | Conditional Approval | DAVID MATSON |
| Interior/Exterior Lathing | 9/14/2022 | Partial Approval | JENNIFER RABUCHIN |
| Insulation | 9/19/2022 | Partial Approval | JENNIFER RABUCHIN |
| Drywall Nailing | 9/23/2022 | Approved | MATTHEW NELSON |
| Green Building Rough | 9/23/2022 | Approved | MATTHEW NELSON |
| BUILDING-Rough-Frame | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 4/19/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 4/19/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Final | 4/19/2023 | Corrections Issued | JENNIFER RABUCHIN |
| MERV13>=Final | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Final | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| METHANE-Rough | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 4/19/2023 | Corrections Issued | JENNIFER RABUCHIN |
| SGSOV-Seismic Gas S/O Valve | 4/19/2023 | SGSOV Approved | JENNIFER RABUCHIN |
| Smoke Detectors | 4/19/2023 | Approved | JENNIFER RABUCHIN |
| Final | 11/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Green Building Final | 11/21/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Final | 2/12/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Green Building Final | 2/12/2025 | Partial Inspection | CHRISTOPHER ROJAS |
| Final | 3/24/2025 | No Access for Inspection | JENNIFER RABUCHIN |
| Green Building Final | 3/24/2025 | Approved | JENNIFER RABUCHIN |
| Final | 3/26/2025 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Final | 3/28/2025 | Corrections Issued | DAVID ANDERSON |
| Final | 4/11/2025 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Final | 7/3/2025 | Approved | JENNIFER RABUCHIN |
| Final | 7/3/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 7/3/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 7/3/2025 | Approved | JENNIFER RABUCHIN |