11251-11253 N CHIVERS AVE 91331

Certificate Information: 11251-11253 N CHIVERS AVE 91331

Application / Permit
21016-10000-00090
Plan Check / Job No.
B21LA00051
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Eplan. Ground floor addition to (E) SFD and conversion of (E) attached 2-car garage and new addition to a ADU per ordinance.
Permit Issued
Issued on 3/12/2021
Issuing Office
Current Status
CofO Issued on 7/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/16/2021 APPLICANT
Assigned to Plan Check Engineer 1/19/2021 HELEN NGUYEN
Corrections Issued 1/20/2021 HELEN NGUYEN
Applicant returned to address corrections 2/10/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 2/15/2021 KEVIN MORALES
Plan Check Approved 3/9/2021 CARLOS MONTES
No Progress 3/9/2021 CARLOS MONTES
Plan Check Approved 3/9/2021 CARLOS MONTES
Issued 3/12/2021 APPLICANT
CofO in Progress 2/18/2022 MICHEL ABAJAN
CofO Issued 7/12/2022 RONALD MYRICK
Permit Finaled 7/12/2022 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 2/2/2021 GABRIEL ROBLES
Roof/Waste drainage to street Cleared 2/2/2021 GABRIEL ROBLES
Eng Process Fee Ord 176,300 Cleared 2/4/2021 GABRIEL ROBLES
Sewer availability Cleared 2/4/2021 GABRIEL ROBLES

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MICHEL ABAJAN, (818) 374-9932 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/1/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 4/1/2021 Partial Approval MICHEL ABAJAN
BUILDING-Rough-Frame 5/7/2021 Approved MICHEL ABAJAN
ELECTRICAL-Rough 5/7/2021 Approved MICHEL ABAJAN
Green Building Rough 5/7/2021 Approved MICHEL ABAJAN
HVAC-Rough 5/7/2021 Approved MICHEL ABAJAN
PLUMBING-Rough 5/7/2021 Approved MICHEL ABAJAN
Insulation 5/21/2021 Approved JAVIER RAMOS JR
Interior/Exterior Lathing 5/21/2021 Partial Approval JAVIER RAMOS JR
Drywall Nailing 5/28/2021 Approved MICHEL ABAJAN
ELECTRICAL-Final 12/17/2021 Approved MICHEL ABAJAN
Final 12/17/2021 Corrections Issued MICHEL ABAJAN
Green Building Final 12/17/2021 Not Ready for Inspection MICHEL ABAJAN
HVAC-Final 12/17/2021 Approved MICHEL ABAJAN
PLUMBING-Final 12/17/2021 Approved MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 12/17/2021 SGSOV Not Ready MICHEL ABAJAN
Smoke Detectors 12/17/2021 Approved MICHEL ABAJAN
Final 1/31/2022 Not Ready for Inspection MICHEL ABAJAN
Green Building Final 1/31/2022 Not Ready for Inspection MICHEL ABAJAN
SGSOV-Seismic Gas S/O Valve 1/31/2022 SGSOV Approved MICHEL ABAJAN
Final 2/4/2022 Partial Approval MICHEL ABAJAN
Green Building Final 2/4/2022 Approved MICHEL ABAJAN
Final 2/18/2022 OK to Issue CofO MICHEL ABAJAN