4184 S HARVARD BLVD 90062
Certificate Information: 4184 S HARVARD BLVD 90062
- Application / Permit
- 21016-10000-00046
- Plan Check / Job No.
- B21LA00025
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert detached garage into ADU per state law.
- Permit Issued
- Issued on 11/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/13/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 1/14/2021 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 1/21/2021 | APPLICANT |
| Plan Check Approved | 11/14/2022 | RICARDO RAMIREZ |
| Issued | 11/21/2022 | APPLICANT |
| CofO in Progress | 8/25/2023 | SABAS ALONSO |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
| CofO Issued | 9/5/2023 | DEROLD HAUFF |
| Permit Finaled | 9/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hold | Cleared | 7/6/2021 | JASON SHEETS |
| Address approval | Cleared | 5/12/2022 | JEANIE LAM |
| Sewer availability | Cleared | 5/12/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2022 | JEANIE LAM |
| Construction near power lines | Cleared | 9/15/2022 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Floor/Roof Diaphrgm/Shear Wall | 12/28/2022 | Partial Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 1/17/2023 | Corrections Issued | SABAS ALONSO |
| Underground Mechanical | 1/17/2023 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 2/1/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/1/2023 | Partial Approval | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/10/2023 | Approved | RAUL BARAJAS |
| PLUMBING-Rough | 2/10/2023 | Partial Approval | RAUL BARAJAS |
| ELECTRICAL-Rough | 2/16/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 2/16/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 2/22/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 2/22/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 2/22/2023 | Approved | SABAS ALONSO |
| Insulation | 2/28/2023 | Conditional Approval | MICHAEL LEWIS |
| Interior/Exterior Lathing | 2/28/2023 | Approved | MICHAEL LEWIS |
| Drywall Nailing | 3/7/2023 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2023 | Approved | STUART CHAPMAN |
| Insulation | 3/7/2023 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 3/13/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Shower Pan | 3/13/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/12/2023 | Partial Approval | SABAS ALONSO |
| Final | 6/23/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 6/23/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 6/23/2023 | SGSOV Approved | SABAS ALONSO |
| Smoke Detectors | 6/23/2023 | Approved | SABAS ALONSO |
| Final | 7/18/2023 | Not Ready for Inspection | CHARLES BOGHOSKHAN |
| Final | 8/4/2023 | Corrections Issued | SABAS ALONSO |
| Final | 8/21/2023 | OK to Issue CofO | SABAS ALONSO |