4184 S HARVARD BLVD 90062

Certificate Information: 4184 S HARVARD BLVD 90062

Application / Permit
21016-10000-00046
Plan Check / Job No.
B21LA00025
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert detached garage into ADU per state law.
Permit Issued
Issued on 11/21/2022
Issuing Office
Metro
Current Status
CofO Issued on 9/5/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/7/2021 APPLICANT
Assigned to Plan Check Engineer 1/13/2021 FARSHAD ALIMOHAMADI
Corrections Issued 1/14/2021 FARSHAD ALIMOHAMADI
Building Plans Picked Up 1/21/2021 APPLICANT
Plan Check Approved 11/14/2022 RICARDO RAMIREZ
Issued 11/21/2022 APPLICANT
CofO in Progress 8/25/2023 SABAS ALONSO
Permit Finaled 9/5/2023 DEROLD HAUFF
CofO Issued 9/5/2023 DEROLD HAUFF
Permit Finaled 9/5/2023 DEROLD HAUFF

Permit Application Clearance Information

Hold Cleared 7/6/2021 JASON SHEETS
Address approval Cleared 5/12/2022 JEANIE LAM
Sewer availability Cleared 5/12/2022 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/13/2022 JEANIE LAM
Construction near power lines Cleared 9/15/2022 RIDWAN HARDY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 12/28/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 1/17/2023 Corrections Issued SABAS ALONSO
Underground Mechanical 1/17/2023 Partial Approval SABAS ALONSO
Excavation/Setback/Form/Re-Bar 2/1/2023 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/1/2023 Partial Approval ALIZAH MAYAGOITIA
Footing/Foundation/Slab 2/10/2023 Approved RAUL BARAJAS
PLUMBING-Rough 2/10/2023 Partial Approval RAUL BARAJAS
ELECTRICAL-Rough 2/16/2023 Approved SABAS ALONSO
PLUMBING-Rough 2/16/2023 Approved SABAS ALONSO
BUILDING-Rough-Frame 2/22/2023 Approved SABAS ALONSO
Green Building Rough 2/22/2023 Approved SABAS ALONSO
HVAC-Rough 2/22/2023 Approved SABAS ALONSO
Insulation 2/28/2023 Conditional Approval MICHAEL LEWIS
Interior/Exterior Lathing 2/28/2023 Approved MICHAEL LEWIS
Drywall Nailing 3/7/2023 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 3/7/2023 Approved STUART CHAPMAN
Insulation 3/7/2023 Approved STUART CHAPMAN
PLUMBING-Final 3/13/2023 Corrections Issued ALEJANDRO DE ARTOLA
Shower Pan 3/13/2023 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 5/12/2023 Partial Approval SABAS ALONSO
Final 6/23/2023 Corrections Issued SABAS ALONSO
Green Building Final 6/23/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 6/23/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 6/23/2023 Approved SABAS ALONSO
Final 7/18/2023 Not Ready for Inspection CHARLES BOGHOSKHAN
Final 8/4/2023 Corrections Issued SABAS ALONSO
Final 8/21/2023 OK to Issue CofO SABAS ALONSO