116 W 118TH PL 90061

Certificate Information: 116 W 118TH PL 90061

Application / Permit
21016-10000-00025
Plan Check / Job No.
B21LA00007
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERSION OF AN EXISTING DETACHED GARAGE INTO AN ACCESSORY DWELLING UNIT.
Permit Issued
Issued on 3/18/2021
Issuing Office
Current Status
CofO Issued on 9/4/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/4/2021 APPLICANT
Assigned to Plan Check Engineer 1/6/2021 FARSHAD ALIMOHAMADI
Corrections Issued 1/6/2021 FARSHAD ALIMOHAMADI
Plan Check Approved 2/18/2021 RICARDO RAMIREZ
Issued 3/18/2021 APPLICANT
Building Plans Picked Up 3/22/2021 APPLICANT
CofO in Progress 6/4/2021 EUGENE CASSIDY
Permit Finaled 9/4/2021 DEROLD HAUFF
CofO Issued 9/4/2021 DEROLD HAUFF
Permit Finaled 9/4/2021 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 2/9/2021 ROSA SILVA
Eng Process Fee Ord 176,300 Cleared 2/9/2021 ROSA SILVA
Sewer availability Cleared 2/9/2021 ROSA SILVA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOHN KLARIN, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI
ARTHUR NEGRETE, (310) 732-4558 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 4/1/2021 Approved EUGENE CASSIDY
ELECTRICAL-Rough 4/1/2021 Approved EUGENE CASSIDY
Green Building Rough 4/1/2021 Approved EUGENE CASSIDY
HVAC-Rough 4/1/2021 Approved EUGENE CASSIDY
MERV13>=Rough 4/1/2021 Approved EUGENE CASSIDY
PLUMBING-Rough 4/1/2021 Partial Approval EUGENE CASSIDY
Sewer 4/1/2021 Approved EUGENE CASSIDY
Shower Pan 4/1/2021 Not Ready for Inspection EUGENE CASSIDY
Wood Frame 4/1/2021 Approved EUGENE CASSIDY
Insulation 4/12/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Interior/Exterior Lathing 4/12/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Shower Pan 4/12/2021 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Insulation 4/19/2021 Partial Approval SABAS ALONSO
Interior/Exterior Lathing 4/19/2021 Partial Approval SABAS ALONSO
Shower Pan 4/19/2021 Approved SABAS ALONSO
Drywall Nailing 4/27/2021 Approved SABAS ALONSO
Insulation 4/27/2021 Approved SABAS ALONSO
Interior/Exterior Lathing 4/27/2021 Approved SABAS ALONSO
Final 5/25/2021 Corrections Issued EUGENE CASSIDY
Green Building Final 5/25/2021 Not Ready for Inspection EUGENE CASSIDY
MERV13>=Final 5/25/2021 Approved EUGENE CASSIDY
SGSOV-Seismic Gas S/O Valve 5/25/2021 SGSOV Approved EUGENE CASSIDY
Smoke Detectors 5/25/2021 Approved EUGENE CASSIDY
HVAC-Final 5/27/2021 Approved JOHN KLARIN
Pre-Inspection 5/27/2021 Corrections Issued JOHN KLARIN
Final 6/1/2021 Corrections Issued JOHN KLARIN
Pre-Inspection 6/1/2021 Partial Approval JOHN KLARIN
Final 6/4/2021 OK to Issue CofO EUGENE CASSIDY
Green Building Final 6/4/2021 Approved EUGENE CASSIDY