2501 N BANYAN DR 90049
Certificate Information: 2501 N BANYAN DR 90049
- Application / Permit
- 21014-30001-05418
- Plan Check / Job No.
- B23WL03076
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental Ref to PCIS#: 21014-30000-05418, to "Revise Area of Addition, Deck, and Interior Remodeal, and Include (N) Elevator"
- Permit Issued
- Issued on 1/4/2024
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 12/15/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2023 | DAVID CASTILLO |
| Corrections Issued | 12/29/2023 | DAVID CASTILLO |
| Quality Review Completed | 1/3/2024 | JASON JANGADA |
| Plan Check Approved | 1/3/2024 | DAVID CASTILLO |
| Issued | 1/4/2024 | APPLICANT |
| Building Plans Picked Up | 1/4/2024 | APPLICANT |
| Permit Finaled | 12/15/2025 | KEVIN SARGSYAN |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Architect | Mahmoodi,, Arshia; Lic. No.: C34875 | 6543 FRANKLIN AVENUE # 306 LOS ANGELES, CA 90028 |
| Contractor | Owner-Builder | , |
| Engineer | Nastarin,, Hooman; Lic. No.: C62199 | 554 S SAN VICNETE BLVD 202 LOS ANGELES, CA 90048 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/24/2024 | Corrections Issued | EVAN COOPER |
| PLUMBING-Rough | 2/9/2024 | Partial Approval | KEVIN SARGSYAN |
| FLOOD-Proofing Certificate | 3/15/2024 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/2/2024 | Partial Approval | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/16/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/17/2024 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/20/2024 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/21/2024 | Partial Approval | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 5/22/2024 | Approved | KEVIN SARGSYAN |
| PLUMBING-Rough | 6/3/2024 | Approved | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 6/20/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/10/2024 | Not Ready for Inspection | KEVIN SARGSYAN |
| Interior/Exterior Lathing | 9/19/2024 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/23/2024 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/27/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 10/25/2024 | Approved | MICHAEL ALLEN |
| Drywall Nailing | 11/22/2024 | Corrections Issued | KEVIN SARGSYAN |
| Drywall Nailing | 11/25/2024 | Approved | KEVIN SARGSYAN |
| Shower Pan | 4/25/2025 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 5/7/2025 | Approved | KEVIN SARGSYAN |
| PLUMBING-Final | 9/4/2025 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Final | 10/2/2025 | Approved | KEVIN SARGSYAN |