1281 S HOLMBY AVE 90024

Certificate Information: 1281 S HOLMBY AVE 90024

Application / Permit
21014-30001-04497
Plan Check / Job No.
B22WL01957
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Supplemental ref to pcis # 21014-30000-04497, to revise architectural and structural plans. Per engineering design.
Permit Issued
Issued on 7/1/2022
Issuing Office
Current Status
Permit Finaled on 12/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/15/2022 APPLICANT
Assigned to Plan Check Engineer 5/16/2022 ALFREDO JARA
Corrections Issued 5/16/2022 ALFREDO JARA
Plan Check Approved 6/22/2022 ALFREDO JARA
Issued 7/1/2022 APPLICANT
Building Plans Picked Up 7/1/2022 APPLICANT
Permit Finaled 12/16/2022 STEPHANIE SWANSON

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,
Engineer Sadjadi,, Abdulreza; Lic. No.: C51812 1223 WILSHIRE BLVD #169      SANTA MONICA, CA 90403

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/6/2022 Corrections Issued CHRISTOPHER WILSON
METHANE-Barrier 7/6/2022 Approved CHRISTOPHER WILSON
METHANE-Subgrade 7/6/2022 Approved CHRISTOPHER WILSON
BUILDING-Rough-Frame 7/15/2022 Partial Approval BRENDAN LOONEY
Green Building Rough 7/15/2022 Not Ready for Inspection BRENDAN LOONEY
METHANE-Rough 7/15/2022 Approved BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 8/30/2022 Partial Approval STEPHANIE SWANSON
Green Building Rough 8/30/2022 Not Ready for Inspection STEPHANIE SWANSON
Special/Order Compliance 8/30/2022 Approved ANDREW NAVE
ELECTRICAL-Rough 9/8/2022 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Rough 9/27/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Rough 9/30/2022 Corrections Issued STEPHANIE SWANSON