14308 S ORCHARD AVE 90247
Certificate Information: 14308 S ORCHARD AVE 90247
- Application / Permit
- 21014-30001-01547
- Plan Check / Job No.
- B22WL02446
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Supplemental Ref to PCIS#: 21014-30000-01547, to "Increase Size of Addition"
- Permit Issued
- Issued on 12/15/2022
- Issuing Office
- West Los Angeles
- Current Status
- Permit Finaled on 6/28/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 6/24/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 6/30/2022 | JASON JANGADA |
| Corrections Issued | 6/30/2022 | JASON JANGADA |
| Applicant returned to address corrections | 10/4/2022 | JASON JANGADA |
| Plan Check Approved | 11/4/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 11/16/2022 | APPLICANT |
| Issued | 12/15/2022 | APPLICANT |
| Permit Finaled | 6/28/2025 | DAVID FEILER |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 8/4/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 8/9/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 9/1/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Adefeso,, Wole Dayo; Lic. No.: C63361 | 1620 CENTINELA AVE 3048 INGLEWOOD, CA 90302 |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 1/27/2023 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 1/27/2023 | Partial Approval | JAMES CHAVEZ |
| METHANE-Barrier | 1/27/2023 | Approved | JAMES CHAVEZ |
| METHANE-Subgrade | 1/27/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2023 | Partial Inspection | JAMES CHAVEZ |
| Underground Mechanical | 2/10/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Approved | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/20/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 3/20/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| MERV13>=Rough | 3/20/2023 | Approved | JAMES CHAVEZ |
| METHANE-Rough | 3/20/2023 | Approved | JAMES CHAVEZ |
| Insulation | 4/13/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 5/2/2023 | Approved | JAMES CHAVEZ |
| Green Building Rough | 5/2/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 7/21/2023 | Approved | JAMES CHAVEZ |
| Final | 7/21/2023 | Corrections Issued | JAMES CHAVEZ |
| Footing/Foundation/Slab | 7/21/2023 | Approved | JAMES CHAVEZ |
| Green Building Final | 7/21/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| MERV13>=Final | 7/21/2023 | Approved | JAMES CHAVEZ |
| Smoke Detectors | 7/21/2023 | Approved | JAMES CHAVEZ |
| Final | 10/13/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Final | 10/13/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Final | 3/12/2025 | No Access for Inspection | BEN MOLSTAD |
| Green Building Final | 3/12/2025 | No Access for Inspection | BEN MOLSTAD |