6601 W 83RD ST 90045

Certificate Information: 6601 W 83RD ST 90045

Application / Permit
21014-30000-06505
Plan Check / Job No.
B21WL05831
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR REMODEL, BATH REMODEL, 2-NEW SLIDDING DOORS
Permit Issued
Issued on 4/6/2023
Issuing Office
San Pedro
Current Status
CofO Issued on 7/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/1/2022 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 KAVIAN REFAHI
Corrections Issued 1/31/2022 KAVIAN REFAHI
Quality Review Completed 2/8/2022 FELIX FIGUEROA
Applicant returned to address corrections 4/13/2022 KAVIAN REFAHI
Applicant returned to address corrections 7/8/2022 KAVIAN REFAHI
Plan Check Approved 9/30/2022 KAVIAN REFAHI
Building Plans Picked Up 4/4/2023 APPLICANT
Issued 4/6/2023 APPLICANT
CofO in Progress 7/11/2025 ANTHONY EGSON
Permit Finaled 7/17/2025 RICHARD STEINBACH
CofO Issued 7/17/2025 RICHARD STEINBACH
Permit Finaled 7/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor J D Boice Construction; Lic. No.: 927239-B 1516 CAMINO LOS ROBLES      FULLERTON, CA 92833
Engineer Assink,, Aart; Lic. No.: C39390 1611 EL PRADO AVE      TORRANCE, CA 90501

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Partial Approval BOBBY KEY
Interior/Exterior Lathing 12/4/2023 Partial Approval BOBBY KEY
ELECTRICAL-Rough 12/5/2023 Partial Approval BOBBY KEY
HVAC-Rough 12/5/2023 Partial Approval BOBBY KEY
PLUMBING-Rough 12/5/2023 Corrections Issued BOBBY KEY
PLUMBING-Rough 12/8/2023 Approved BOBBY KEY
Interior/Exterior Lathing 12/19/2023 Partial Approval TEMISTOCLES CAAL
Interior/Exterior Lathing 12/26/2023 Not Ready for Inspection BOBBY KEY
Shower Pan 12/26/2023 Not Ready for Inspection BOBBY KEY
Drywall Nailing 12/27/2023 Approved BOBBY KEY
Interior/Exterior Lathing 12/27/2023 Approved BOBBY KEY
Rough-Elec/Plmb/HVAC 12/27/2023 Approved BOBBY KEY
Shower Pan 12/27/2023 Approved BOBBY KEY
Wood Frame 12/27/2023 Approved BOBBY KEY
ELECTRICAL-Final 6/3/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 6/3/2025 Corrections Issued JESUS PINEDA
HVAC-Final 6/9/2025 Approved JESUS PINEDA
BUILDING-Rough-Frame 7/8/2025 Approved JESUS PINEDA
ELECTRICAL-Final 7/8/2025 Approved JESUS PINEDA
Final 7/8/2025 Corrections Issued JESUS PINEDA
PLUMBING-Final 7/8/2025 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 7/8/2025 SGSOV Approved JESUS PINEDA
Smoke Detectors 7/8/2025 Approved JESUS PINEDA
Final 7/10/2025 OK to Issue CofO ANTHONY EGSON
Service/Power Release 7/15/2025 Approved RUBEN RIVAS