8016 S DUNFIELD AVE 90045
Certificate Information: 8016 S DUNFIELD AVE 90045
- Application / Permit
- 21014-30000-06501
- Plan Check / Job No.
- B21WL05819
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel, Ground Floor and 2nd Story Addition with (N) 2-Car Garage to an (E) 1-Story S.F.D
- Permit Issued
- Issued on 11/28/2022
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 4/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/6/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 2/3/2022 | DAVID CASTILLO |
| Corrections Issued | 2/14/2022 | DAVID CASTILLO |
| Quality Review Completed | 3/7/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 10/7/2022 | DAVID CASTILLO |
| Applicant returned to address corrections | 10/24/2022 | DAVID CASTILLO |
| Plan Check Approved | 11/15/2022 | DAVID CASTILLO |
| Building Plans Picked Up | 11/15/2022 | APPLICANT |
| Issued | 11/28/2022 | APPLICANT |
| CofO in Progress | 4/5/2024 | TEMISTOCLES CAAL |
| Permit Finaled | 4/8/2024 | DANIEL ORRANTE |
| CofO Issued | 4/8/2024 | DANIEL ORRANTE |
| Permit Finaled | 4/8/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 4/1/2022 | KIRK LINKLATER |
| Specific Plan | Cleared | 5/19/2022 | FREDDY GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2022 | JENSON LEE |
| Sewer availability | Cleared | 5/26/2022 | JENSON LEE |
| Low Impact Development | Cleared | 10/14/2022 | DEBORA LEITE |
| Roof/Waste drainage to street | Cleared | 10/20/2022 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Builoff,, Sergei; Lic. No.: L8099 | 4004 SCHUYLKILL DR CALABASAS, CA 91302 |
Inspector Information
| MORRIS JACKSON, (310) 914-3885 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 12/23/2022 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 12/23/2022 | Corrections Issued | HERBERT GIRON |
| METHANE-Barrier | 12/23/2022 | Approved | HERBERT GIRON |
| METHANE-Subgrade | 12/23/2022 | Approved | HERBERT GIRON |
| Pre-Inspection | 12/23/2022 | Partial Inspection | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 12/28/2022 | Not Ready for Inspection | EVAN COOPER |
| Footing/Foundation/Slab | 12/28/2022 | Not Ready for Inspection | EVAN COOPER |
| METHANE-Rough | 12/28/2022 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 1/11/2023 | Approved | HERBERT GIRON |
| Footing/Foundation/Slab | 1/11/2023 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/2/2023 | Partial Approval | HERBERT GIRON |
| Insulation | 2/2/2023 | Partial Approval | HERBERT GIRON |
| PLUMBING-Rough | 2/2/2023 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Partial Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 3/29/2023 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Conditional Approval | HERBERT GIRON |
| Wood Frame | 3/31/2023 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 6/5/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Conditional Approval | JESUS RODRIGUEZ |
| Green Building Rough | 6/5/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| METHANE-Rough | 6/5/2023 | Approved | JESUS RODRIGUEZ |
| Wood Frame | 6/5/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 7/12/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 7/12/2023 | Corrections Issued | HERBERT GIRON |
| Special/Order Compliance | 7/12/2023 | Partial Inspection | BOBBY KEY |
| ELECTRICAL-Rough | 7/27/2023 | Corrections Issued | HERBERT GIRON |
| HVAC-Rough | 7/27/2023 | Not Ready for Inspection | HERBERT GIRON |
| PLUMBING-Rough | 7/27/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 7/31/2023 | Approved | RICHARD STEINBACH |
| HVAC-Rough | 7/31/2023 | Corrections Issued | RICHARD STEINBACH |
| Gas Test | 8/2/2023 | Partial Approval | RICHARD STEINBACH |
| HVAC-Rough | 8/2/2023 | Approved | RICHARD STEINBACH |
| PLUMBING-Rough | 8/2/2023 | Approved | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 8/4/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 8/4/2023 | Approved | HERBERT GIRON |
| Deputy Steel/Welding | 8/9/2023 | Conditional Approval | RICHARD STEINBACH |
| BUILDING-Rough-Frame | 8/10/2023 | Conditional Approval | HERBERT GIRON |
| Insulation | 8/10/2023 | Approved | HERBERT GIRON |
| Verify Sprinkler Sign Off | 8/10/2023 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/25/2023 | Partial Approval | TEMISTOCLES CAAL |
| Smoke Detectors | 8/25/2023 | Corrections Issued | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/8/2023 | Approved | TEMISTOCLES CAAL |
| Interior/Exterior Lathing | 9/11/2023 | No Access for Inspection | TEMISTOCLES CAAL |
| PLUMBING-Final | 12/22/2023 | Approved | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/12/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Final | 1/26/2024 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 1/26/2024 | Not Ready for Inspection | TEMISTOCLES CAAL |
| HVAC-Final | 1/30/2024 | Conditional Approval | TEMISTOCLES CAAL |
| BUILDING-Rough-Frame | 3/6/2024 | Approved | TEMISTOCLES CAAL |
| Drywall Nailing | 3/6/2024 | Approved | TEMISTOCLES CAAL |
| Final | 3/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Green Building Final | 3/6/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 3/6/2024 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Smoke Detectors | 3/6/2024 | Corrections Issued | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/2/2024 | SGSOV Not Ready | TEMISTOCLES CAAL |
| Final | 4/4/2024 | OK to Issue CofO | TEMISTOCLES CAAL |
| HVAC-Final | 4/4/2024 | Approved | TEMISTOCLES CAAL |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | TEMISTOCLES CAAL |
| Service/Power Release | 4/4/2024 | Approved | TEMISTOCLES CAAL |
| Smoke Detectors | 4/4/2024 | Approved | TEMISTOCLES CAAL |