445 E 90TH ST 90003
Certificate Information: 445 E 90TH ST 90003
- Application / Permit
- 21014-30000-06399
- Plan Check / Job No.
- B21WL05727
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (n) additional bedroom and bathroom to 1-story S.F.D. and interior remodeling creating a hallway per WFPP.
- Permit Issued
- Issued on 2/3/2022
- Issuing Office
- Current Status
- Issued on 2/3/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | KAVIAN REFAHI |
| Corrections Issued | 1/2/2022 | KAVIAN REFAHI |
| Plan Check Approved | 1/27/2022 | SAMUEL GONZALEZ |
| Issued | 2/3/2022 | APPLICANT |
| Building Plans Picked Up | 2/4/2022 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/14/2022 | CHRISTOPHER ROCHA |
| Roof/Waste drainage to street | Cleared | 1/14/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/14/2022 | CHRISTOPHER ROCHA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/27/2022 | Conditional Approval | RYAN SALAZAR |
| Excavation/Setback/Form/Re-Bar | 6/1/2022 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 6/1/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 6/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Sewer | 6/6/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Insulation | 6/15/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/21/2022 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Conditional Approval | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/29/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Green Building Rough | 6/29/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/11/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 7/11/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/19/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 7/26/2022 | Approved | ADAM ESCOTO |
| Wood Frame | 7/26/2022 | Approved | ADAM ESCOTO |
| Insulation | 8/5/2022 | Corrections Issued | LILIANA PORTILLO |
| Drywall Nailing | 8/19/2022 | Approved | LILIANA PORTILLO |
| Insulation | 8/19/2022 | Approved | LILIANA PORTILLO |
| Interior/Exterior Lathing | 8/30/2022 | Partial Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/6/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/26/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/26/2022 | Corrections Issued | LILIANA PORTILLO |
| Final | 10/26/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Final | 10/26/2022 | Corrections Issued | LILIANA PORTILLO |
| Green Building Rough | 10/26/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 10/26/2022 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Final | 10/26/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/26/2022 | SGSOV Approved | LILIANA PORTILLO |
| Smoke Detectors | 10/26/2022 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Final | 3/4/2024 | Partial Inspection | MICHAEL LEWIS |
| ELECTRICAL-Final | 2/6/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Final | 2/6/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Green Building Final | 2/6/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 2/6/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Final | 6/2/2025 | Not Ready for Inspection | JOHN QUINTANILLA |
| Green Building Final | 6/2/2025 | No Access for Inspection | JOHN QUINTANILLA |
| Smoke Detectors | 6/2/2025 | No Access for Inspection | JOHN QUINTANILLA |