12811 W INDIANAPOLIS ST 90066

Certificate Information: 12811 W INDIANAPOLIS ST 90066

Application / Permit
21014-30000-06363
Plan Check / Job No.
B21WL05685
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
1st (81 sf) and 2nd floor (349 sf) addition to (e) 2-story SFD (2,227 sf), add a roof deck
Permit Issued
Issued on 6/27/2022
Issuing Office
Current Status
CofO Issued on 3/9/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/23/2021 APPLICANT
Assigned to Plan Check Engineer 12/29/2021 REZA HAGHIGHAT
Corrections Issued 1/2/2022 REZA HAGHIGHAT
Quality Review Completed 1/10/2022 TARIK SAOUD
Plan Check Approved 4/11/2022 REZA HAGHIGHAT
Issued 6/27/2022 APPLICANT
Building Plans Picked Up 8/9/2022 APPLICANT
CofO in Progress 3/8/2024 RICHARD STEINBACH
CofO Issued 3/9/2024 DANIEL ORRANTE
Permit Finaled 3/9/2024 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 2/3/2022 DINAH GARIN
Sewer availability Cleared 2/3/2022 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 2/4/2022 DINAH GARIN
Grading Pre-Inspection Cleared 4/11/2022 REZA HAGHIGHAT

Contact Information

Contractor Erla Construction; Lic. No.: 1046950-B 2324 MICHIGAN AVE      SANTA MONICA, CA 90404
Engineer Choi,, David; Lic. No.: S4784 1327 LOMA AVENUE      LONG BEACH, CA 90804

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/27/2022 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 8/26/2022 No Access for Inspection JESUS RODRIGUEZ
Footing/Foundation/Slab 8/30/2022 Conditional Approval JESUS RODRIGUEZ
Wood Frame 10/17/2022 Corrections Issued HERBERT GIRON
PLUMBING-Rough 11/7/2022 Not Ready for Inspection JESUS RODRIGUEZ
PLUMBING-Rough 11/14/2022 Corrections Issued JESUS RODRIGUEZ
Wood Frame 11/14/2022 Corrections Issued JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 11/21/2022 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/7/2023 Partial Approval EVAN COOPER
ELECTRICAL-Rough 2/13/2023 Not Ready for Inspection EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Corrections Issued JESUS RODRIGUEZ
BUILDING-Rough-Frame 4/10/2023 Corrections Issued HERBERT GIRON
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Corrections Issued HERBERT GIRON
Green Building Rough 4/10/2023 Not Ready for Inspection HERBERT GIRON
Deputy Wood Construction 4/11/2023 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 4/13/2023 Partial Approval JESUS RODRIGUEZ
Deputy Drilled-In Anchors 4/20/2023 Conditional Approval JESUS RODRIGUEZ
ELECTRICAL-Rough 4/24/2023 Not Ready for Inspection EVAN COOPER
HVAC-Rough 4/24/2023 Not Ready for Inspection EVAN COOPER
ELECTRICAL-Rough 5/2/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 5/2/2023 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 5/2/2023 Approved JESUS RODRIGUEZ
PLUMBING-Rough 5/8/2023 Partial Approval JESUS RODRIGUEZ
Interior/Exterior Lathing 5/19/2023 Partial Approval JESUS RODRIGUEZ
Insulation 5/23/2023 Corrections Issued HERBERT GIRON
BUILDING-Rough-Frame 5/24/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Rough 5/24/2023 Approved JESUS RODRIGUEZ
Insulation 5/24/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 5/24/2023 Approved JESUS RODRIGUEZ
Insulation 5/25/2023 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 6/5/2023 Approved JESUS RODRIGUEZ
Green Building Rough 6/5/2023 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/5/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 6/14/2023 Approved EVAN COOPER
Shower Pan 6/27/2023 Approved ASHLEY THOMPSON
PLUMBING-Final 7/24/2023 Not Ready for Inspection JESUS RODRIGUEZ
Gas Test 9/20/2023 Not Ready for Inspection TEMISTOCLES CAAL
Gas Test 9/26/2023 Approved HERBERT GIRON
ELECTRICAL-Final 10/20/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 10/20/2023 Corrections Issued JESUS RODRIGUEZ
Service/Power Release 10/20/2023 Corrections Issued JESUS RODRIGUEZ
ELECTRICAL-Final 10/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Final 10/30/2023 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Final 10/30/2023 Approved JESUS RODRIGUEZ
Service/Power Release 10/30/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 11/3/2023 Approved TEMISTOCLES CAAL
Service/Power Release 11/13/2023 Approved JESUS RODRIGUEZ
Final 1/30/2024 Corrections Issued JESUS RODRIGUEZ
Green Building Final 1/30/2024 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 1/30/2024 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 1/30/2024 Approved JESUS RODRIGUEZ
Final 3/5/2024 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 3/5/2024 Approved JESUS RODRIGUEZ