10463 W HOLMAN AVE 90024
Certificate Information: 10463 W HOLMAN AVE 90024
- Application / Permit
- 21014-30000-06362
- Plan Check / Job No.
- B21WL05678
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Structural remodel and addition to an (e) 1-story sfd.
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 1/19/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/29/2021 | RICHARD GARCIA |
| Corrections Issued | 1/1/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 1/6/2022 | APPLICANT |
| Applicant returned to address corrections | 1/25/2022 | LUKE GONZALES |
| Plan Check Approved | 3/2/2022 | MARJAN SHENASI |
| Issued | 3/3/2022 | APPLICANT |
| CofO in Progress | 1/10/2023 | STEPHANIE SWANSON |
| Permit Finaled | 1/19/2023 | DANIEL ORRANTE |
| CofO Issued | 1/19/2023 | DANIEL ORRANTE |
| Permit Finaled | 1/19/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/11/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 1/11/2022 | DINAH GARIN |
| Sewer availability | Cleared | 1/11/2022 | DINAH GARIN |
| Specific Plan | Cleared | 1/12/2022 | VALERIA CEJA |
| GPI Written Notices | Cleared | 1/25/2022 | LUKE GONZALES |
| Grading Pre-Inspection | Cleared | 1/25/2022 | LUKE GONZALES |
Contact Information
| Architect | Myer,, Jamie Beekman; Lic. No.: C31042 | 1730 3/4 WESTWOOD BLVD LOS ANGELES, CA 90024 |
| Contractor | Owner-Builder | , |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/4/2022 | Approved | BRENDAN LOONEY |
| METHANE-Barrier | 4/4/2022 | Approved | BRENDAN LOONEY |
| METHANE-Subgrade | 4/4/2022 | Approved | BRENDAN LOONEY |
| Wood Frame | 4/8/2022 | Partial Approval | MICHAEL PELHAM |
| Deputy Drilled-In Anchors | 4/22/2022 | Conditional Approval | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2022 | Corrections Issued | CHRISTOPHER WILSON |
| Deputy Wood Construction | 5/4/2022 | Approved | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 5/5/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 7/21/2022 | Corrections Issued | PATRICK QUALEY |
| HVAC-Rough | 7/21/2022 | Corrections Issued | PATRICK QUALEY |
| PLUMBING-Rough | 7/26/2022 | Corrections Issued | PATRICK QUALEY |
| ELECTRICAL-Rough | 8/2/2022 | Approved | PATRICK QUALEY |
| HVAC-Rough | 8/2/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 8/2/2022 | Approved | PATRICK QUALEY |
| Wood Frame | 8/2/2022 | Approved | PATRICK QUALEY |
| Interior/Exterior Lathing | 8/16/2022 | Partial Approval | ANDREW NAVE |
| Insulation | 8/19/2022 | Approved | ANDREW NAVE |
| Drywall Nailing | 8/24/2022 | Approved | STEPHANIE SWANSON |
| Shower Pan | 9/7/2022 | Corrections Issued | MICHAEL PELHAM |
| Interior/Exterior Lathing | 9/14/2022 | Partial Approval | STEPHANIE SWANSON |
| Shower Pan | 9/14/2022 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 9/20/2022 | Approved | STEPHANIE SWANSON |
| Underground Mechanical | 10/7/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 10/28/2022 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 11/8/2022 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 11/8/2022 | Approved | STEPHANIE SWANSON |
| Smoke Detectors | 11/8/2022 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 12/16/2022 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 12/27/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 12/27/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| Special/Order Compliance | 12/27/2022 | Partial Approval | ASHLEY THOMPSON |
| BUILDING-Rough-Frame | 1/4/2023 | Approved | STEPHANIE SWANSON |
| Final | 1/4/2023 | Partial Approval | STEPHANIE SWANSON |
| Green Building Final | 1/4/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 1/4/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 1/4/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Final | 1/4/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 1/4/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 1/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 1/4/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Final | 1/10/2023 | OK to Issue CofO | STEPHANIE SWANSON |
| PLUMBING-Final | 1/10/2023 | Approved | STEPHANIE SWANSON |