8074-8076 N ALLOTT AVE 91402
Certificate Information: 8074-8076 N ALLOTT AVE 91402
- Application / Permit
- 21014-30000-06310
- Plan Check / Job No.
- B21WL05621
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Convert (E) garage to ADU, first floor addition, adding (N) 2nd floor to ADU PER LAMC 12.22 A.33(c) AND (e) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.
- Permit Issued
- Issued on 2/14/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 7/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | ALFREDO JARA |
| Corrections Issued | 12/26/2021 | ALFREDO JARA |
| Quality Review Completed | 1/3/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 4/18/2022 | ALFREDO JARA |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| Applicant returned to address corrections | 7/12/2022 | ALFREDO JARA |
| Plan Check Approved | 8/3/2022 | ALFREDO JARA |
| Issued | 2/14/2023 | APPLICANT |
| CofO in Progress | 6/20/2024 | RUBEN SALAS |
| Permit Finaled | 7/18/2024 | RUBEN SALAS |
| CofO Issued | 7/18/2024 | RUBEN SALAS |
| Permit Finaled | 7/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/10/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 2/24/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 2/24/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Sivushenka,, Mikita; Lic. No.: C87698 | 22121 CLARENDON ST APT 340 WOODLAND HILLS, CA 91367 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/13/2023 | Partial Approval | GREGG CUMMINGS |
| Deputy Drilled-In Anchors | 3/20/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 3/20/2023 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Excavation/Setback/Form/Re-Bar | 3/23/2023 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 3/23/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 4/12/2023 | Partial Approval | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Rough | 6/5/2023 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Green Building Rough | 6/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/5/2023 | Approved | GREGG CUMMINGS |
| Wood Frame | 6/5/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/14/2023 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 6/14/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 6/14/2023 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/26/2023 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 6/26/2023 | Approved | GREGG CUMMINGS |
| Insulation | 6/26/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 6/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Shower Pan | 6/26/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Drywall Nailing | 7/7/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/7/2023 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 7/7/2023 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 7/17/2023 | Approved | THOMAS FINNILA |
| Sewer | 9/14/2023 | Approved | CHRISTOPHER ROJAS |
| ELECTRICAL-Final | 1/31/2024 | Approved | GREGG CUMMINGS |
| Final | 1/31/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 1/31/2024 | Approved | GREGG CUMMINGS |
| HVAC-Final | 1/31/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 1/31/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 1/31/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 1/31/2024 | Approved | GREGG CUMMINGS |
| Final | 4/4/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| Service/Power Release | 4/4/2024 | Approved | GREGG CUMMINGS |
| Final | 6/20/2024 | OK to Issue CofO | RUBEN SALAS |