8074-8076 N ALLOTT AVE 91402

Certificate Information: 8074-8076 N ALLOTT AVE 91402

Application / Permit
21014-30000-06310
Plan Check / Job No.
B21WL05621
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Convert (E) garage to ADU, first floor addition, adding (N) 2nd floor to ADU PER LAMC 12.22 A.33(c) AND (e) The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.
Permit Issued
Issued on 2/14/2023
Issuing Office
Valley
Current Status
CofO Issued on 7/18/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 ALFREDO JARA
Corrections Issued 12/26/2021 ALFREDO JARA
Quality Review Completed 1/3/2022 TARIK SAOUD
Applicant returned to address corrections 4/18/2022 ALFREDO JARA
Building Plans Picked Up 4/22/2022 APPLICANT
Applicant returned to address corrections 7/12/2022 ALFREDO JARA
Plan Check Approved 8/3/2022 ALFREDO JARA
Issued 2/14/2023 APPLICANT
CofO in Progress 6/20/2024 RUBEN SALAS
Permit Finaled 7/18/2024 RUBEN SALAS
CofO Issued 7/18/2024 RUBEN SALAS
Permit Finaled 7/18/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/10/2022 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 2/24/2022 AMIR KASHFI
Sewer availability Cleared 2/24/2022 AMIR KASHFI
Roof/Waste drainage to street Cleared 4/20/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,
Engineer Sivushenka,, Mikita; Lic. No.: C87698 22121 CLARENDON ST APT 340      WOODLAND HILLS, CA 91367

Inspector Information

OGANES TARAKHCHYAN, (818) 374-1162 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/13/2023 Partial Approval GREGG CUMMINGS
Deputy Drilled-In Anchors 3/20/2023 Conditional Approval DAVID MATSON
Footing/Foundation/Slab 3/20/2023 Corrections Issued CHRISTOPHER DELLEFIELD
Excavation/Setback/Form/Re-Bar 3/23/2023 Approved GREGG CUMMINGS
Footing/Foundation/Slab 3/23/2023 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 4/12/2023 Partial Approval GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Corrections Issued GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 5/24/2023 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 6/5/2023 Not Ready for Inspection GREGG CUMMINGS
ELECTRICAL-Rough 6/5/2023 Approved GREGG CUMMINGS
Floor/Roof Diaphrgm/Shear Wall 6/5/2023 Not Ready for Inspection GREGG CUMMINGS
Green Building Rough 6/5/2023 Not Ready for Inspection GREGG CUMMINGS
PLUMBING-Rough 6/5/2023 Approved GREGG CUMMINGS
Wood Frame 6/5/2023 Not Ready for Inspection GREGG CUMMINGS
BUILDING-Rough-Frame 6/14/2023 Partial Approval GREGG CUMMINGS
Green Building Rough 6/14/2023 Approved GREGG CUMMINGS
HVAC-Rough 6/14/2023 Partial Approval GREGG CUMMINGS
BUILDING-Rough-Frame 6/26/2023 Approved GREGG CUMMINGS
HVAC-Rough 6/26/2023 Approved GREGG CUMMINGS
Insulation 6/26/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 6/26/2023 Not Ready for Inspection GREGG CUMMINGS
Shower Pan 6/26/2023 Not Ready for Inspection GREGG CUMMINGS
Drywall Nailing 7/7/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/7/2023 Partial Approval GREGG CUMMINGS
Shower Pan 7/7/2023 Approved GREGG CUMMINGS
Interior/Exterior Lathing 7/17/2023 Approved THOMAS FINNILA
Sewer 9/14/2023 Approved CHRISTOPHER ROJAS
ELECTRICAL-Final 1/31/2024 Approved GREGG CUMMINGS
Final 1/31/2024 Corrections Issued GREGG CUMMINGS
Green Building Final 1/31/2024 Approved GREGG CUMMINGS
HVAC-Final 1/31/2024 Approved GREGG CUMMINGS
PLUMBING-Final 1/31/2024 Approved GREGG CUMMINGS
SGSOV-Seismic Gas S/O Valve 1/31/2024 SGSOV Approved GREGG CUMMINGS
Smoke Detectors 1/31/2024 Approved GREGG CUMMINGS
Final 4/4/2024 Not Ready for Inspection GREGG CUMMINGS
Service/Power Release 4/4/2024 Approved GREGG CUMMINGS
Final 6/20/2024 OK to Issue CofO RUBEN SALAS