1224 S REDONDO BLVD 90019

Certificate Information: 1224 S REDONDO BLVD 90019

Application / Permit
21014-30000-06276
Plan Check / Job No.
B21WL05596
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
Adding a new covered balcony and sprial staircase to the second floor at the rear of the existing two story Duplex
Permit Issued
Issued on 5/9/2022
Issuing Office
Current Status
CofO Issued on 12/13/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 JASON JANGADA
Corrections Issued 12/25/2021 JASON JANGADA
Applicant returned to address corrections 2/17/2022 JASON JANGADA
Applicant returned to address corrections 4/9/2022 JASON JANGADA
Plan Check Approved 4/22/2022 JASON JANGADA
Building Plans Picked Up 4/25/2022 APPLICANT
Issued 5/9/2022 APPLICANT
CofO in Progress 12/7/2022 STUART CHAPMAN
Permit Finaled 12/13/2022 DEROLD HAUFF
CofO Issued 12/13/2022 DEROLD HAUFF
Permit Finaled 12/13/2022 DEROLD HAUFF

Permit Application Clearance Information

CPC Cleared 1/14/2022 MAXFIELD VERMY
Tenant Habitability Plan Cleared 2/22/2022 RICARDO BOHORQUEZ
HPOZ Cleared 4/5/2022 CHRISTINA PARK

Contact Information

Contractor Gabor Design Group Inc The; Lic. No.: 842370-B 4587 DON FELIPE DR      LOS ANGELES, CA 90008
Engineer Ilasin,, John Lacebal; Lic. No.: C67469 1011 OARFISH LN      OXNARD, CA 93035

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/28/2022 Conditional Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 7/1/2022 Approved STUART CHAPMAN
METHANE-Barrier 7/1/2022 Approved STUART CHAPMAN
METHANE-Subgrade 7/1/2022 Approved STUART CHAPMAN
Floor/Roof Diaphrgm/Shear Wall 8/16/2022 Approved STUART CHAPMAN
Interior/Exterior Lathing 8/25/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 9/23/2022 Corrections Issued JOSE AVILA
Final 9/23/2022 Corrections Issued JOSE AVILA
Green Building Final 9/23/2022 Approved JOSE AVILA
Green Building Rough 9/23/2022 Approved JOSE AVILA
METHANE-Final 9/23/2022 Approved JOSE AVILA
METHANE-Rough 9/23/2022 Approved JOSE AVILA
SGSOV-Seismic Gas S/O Valve 9/23/2022 SGSOV Not Ready JOSE AVILA
Smoke Detectors 9/23/2022 Corrections Issued JOSE AVILA
BUILDING-Rough-Frame 11/17/2022 Not Ready for Inspection STUART CHAPMAN
Final 11/17/2022 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 11/17/2022 SGSOV Not Ready STUART CHAPMAN
Smoke Detectors 11/17/2022 Not Ready for Inspection STUART CHAPMAN
BUILDING-Rough-Frame 11/30/2022 Approved BRENDAN MORELLI
Final 11/30/2022 Partial Approval BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 11/30/2022 SGSOV Approved BRENDAN MORELLI
Smoke Detectors 11/30/2022 Approved BRENDAN MORELLI
Final 12/7/2022 OK to Issue CofO STUART CHAPMAN