3524 S MOUNTAIN VIEW AVE 90066

Certificate Information: 3524 S MOUNTAIN VIEW AVE 90066

Application / Permit
21014-30000-06232
Plan Check / Job No.
B21WL05513
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2nd Floor Addition w/Trellis and Major Remodel of an (E) 2-Story S.F.D w/Attached Garage
Permit Issued
Issued on 2/3/2023
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/30/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 DAVID CASTILLO
Corrections Issued 1/13/2022 DAVID CASTILLO
Quality Review Completed 2/7/2022 CHIHARU SUZUKI
Building Plans Picked Up 4/19/2022 APPLICANT
Applicant returned to address corrections 4/22/2022 DAVID CASTILLO
Applicant returned to address corrections 7/5/2022 DAVID CASTILLO
Applicant returned to address corrections 12/21/2022 DAVID CASTILLO
Plan Check Approved 1/17/2023 DAVID CASTILLO
Issued 2/3/2023 APPLICANT
CofO in Progress 5/22/2024 JESUS PINEDA
Permit Finaled 5/30/2024 DANIEL ORRANTE
CofO Issued 5/30/2024 DANIEL ORRANTE
Permit Finaled 5/30/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 4/14/2022 CATHERINE ADROVER
Grading Pre-Inspection Cleared 7/5/2022 DAVID CASTILLO
Low Impact Development Cleared 8/8/2022 CHRIS VONG
Sewer availability Cleared 8/31/2022 ANTHONY MAINEZ
Roof/Waste drainage to street Cleared 12/12/2022 AHMED AMARRAGY

Contact Information

Contractor Refined Home Construction Inc; Lic. No.: 1001310-B 113 N SAN VICENTE BLVD      BEVERLY HILLS, CA 90211
Engineer Husain,, Shahzain; Lic. No.: C62744 1843 MONTGOMERY RD      THOUSAND OAKS, CA 91360
Engineer Quayum,, Mohammad; Lic. No.: C74111 1863 CHURCH ST      SIMI VALLEY, CA 93065

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/3/2023 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 4/3/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/17/2023 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/24/2023 Partial Approval JESUS RODRIGUEZ
Deputy Reinf. Concrete 4/25/2023 Conditional Approval RICHARD STEINBACH
Footing/Foundation/Slab 4/25/2023 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/25/2023 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 5/31/2023 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 5/31/2023 Not Ready for Inspection JOHNNY MIRANDA
PLUMBING-Rough 5/31/2023 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 6/2/2023 Approved JOHNNY MIRANDA
HVAC-Rough 6/2/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 6/2/2023 Not Ready for Inspection JOHNNY MIRANDA
Gas Test 7/5/2023 Approved JESUS PINEDA
Green Building Rough 7/5/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 7/5/2023 Partial Approval JESUS PINEDA
PLUMBING-Rough 7/5/2023 Approved JESUS PINEDA
Shower Pan 7/5/2023 Approved JESUS PINEDA
Interior/Exterior Lathing 7/10/2023 Approved JESUS PINEDA
Shower Pan 7/10/2023 Approved JESUS PINEDA
BUILDING-Rough-Frame 7/13/2023 Corrections Issued DAVID FEILER
Insulation 7/13/2023 Not Ready for Inspection DAVID FEILER
BUILDING-Rough-Frame 7/21/2023 Approved JESUS PINEDA
Green Building Rough 7/21/2023 Approved JESUS PINEDA
Insulation 7/21/2023 Approved JESUS PINEDA
Verify Sprinkler Sign Off 7/21/2023 Approved JESUS PINEDA
Drywall Nailing 8/1/2023 Approved JESUS PINEDA
Sewer 12/18/2023 Approved JESUS PINEDA
Gas Test 1/19/2024 Approved JESUS PINEDA
ELECTRICAL-Final 2/7/2024 Corrections Issued JESUS PINEDA
PLUMBING-Final 2/7/2024 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 2/7/2024 SGSOV Approved JESUS PINEDA
Smoke Detectors 2/7/2024 Approved JESUS PINEDA
HVAC-Final 2/9/2024 Approved TEMISTOCLES CAAL
ELECTRICAL-Final 2/22/2024 Approved TEMISTOCLES CAAL
Service/Power Release 2/23/2024 Approved JESUS PINEDA
Final 4/15/2024 Not Ready for Inspection JESUS PINEDA
Footing/Foundation/Slab 4/15/2024 Approved JESUS PINEDA
Green Building Final 4/15/2024 Approved JESUS PINEDA
Structural Steel Frame 4/15/2024 Approved JESUS PINEDA
Final 5/22/2024 OK to Issue CofO JESUS PINEDA