13916 W LA MAIDA ST 91423
Certificate Information: 13916 W LA MAIDA ST 91423
- Application / Permit
- 21014-30000-06169
- Plan Check / Job No.
- B21WL05473
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- new addition to S.F.D.(435 sf). Per WFPP
- Permit Issued
- Issued on 5/12/2022
- Issuing Office
- Current Status
- CofO Issued on 11/29/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2021 | ALFREDO JARA |
| Corrections Issued | 12/20/2021 | ALFREDO JARA |
| Building Plans Picked Up | 1/19/2022 | APPLICANT |
| Applicant returned to address corrections | 4/20/2022 | JASON JANGADA |
| Plan Check Approved | 5/3/2022 | EDWIN ESPIN |
| Issued | 5/12/2022 | APPLICANT |
| CofO in Progress | 11/15/2023 | PATRICK LIEBREGT |
| Permit Finaled | 11/29/2023 | DANIEL SANCHEZ |
| CofO Issued | 11/29/2023 | DANIEL SANCHEZ |
| Permit Finaled | 11/29/2023 | DANIEL SANCHEZ |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 4/8/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOEL ORDAZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| PTOLEMY HILL, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVAKIAN, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| EDMOND DECKERT, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| TIMOTHY KEY, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
| ROBERT CHAVEZ, (213) 252-3049 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/18/2022 | Corrections Issued | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 6/8/2022 | Corrections Issued | PIERRE VEGA |
| Footing/Foundation/Slab | 6/8/2022 | Not Ready for Inspection | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 6/21/2022 | Partial Approval | PIERRE VEGA |
| Footing/Foundation/Slab | 6/21/2022 | Corrections Issued | PIERRE VEGA |
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Partial Approval | PIERRE VEGA |
| Footing/Foundation/Slab | 6/29/2022 | Partial Approval | PIERRE VEGA |
| PLUMBING-Rough | 7/21/2022 | Corrections Issued | PIERRE VEGA |
| Underground Mechanical | 7/21/2022 | Not Ready for Inspection | COREY HUPP |
| Footing/Foundation/Slab | 7/26/2022 | Not Ready for Inspection | PIERRE VEGA |
| Underground Mechanical | 7/26/2022 | Not Ready for Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 7/28/2022 | Partial Approval | ROBERT MINASSIANS |
| Green Building Rough | 7/28/2022 | Not Ready for Inspection | ROBERT MINASSIANS |
| MERV13>=Rough | 7/28/2022 | Not Ready for Inspection | ROBERT MINASSIANS |
| PLUMBING-Rough | 7/28/2022 | Partial Approval | ROBERT MINASSIANS |
| Underground Mechanical | 7/28/2022 | Partial Approval | ROBERT MINASSIANS |
| Insulation | 8/1/2022 | Not Ready for Inspection | PIERRE VEGA |
| Wood Frame | 8/1/2022 | Partial Approval | PIERRE VEGA |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2022 | Approved | PIERRE VEGA |
| Special/Order Compliance | 8/3/2022 | Approved | ROBERT MINASSIANS |
| BUILDING-Rough-Frame | 9/22/2022 | Corrections Issued | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 9/22/2022 | Approved | ROBERT MINASSIANS |
| HVAC-Rough | 9/22/2022 | Corrections Issued | ROBERT MINASSIANS |
| PLUMBING-Rough | 9/22/2022 | Approved | ROBERT MINASSIANS |
| Special/Order Compliance | 9/22/2022 | Partial Inspection | PIERRE VEGA |
| BUILDING-Rough-Frame | 12/8/2022 | Conditional Approval | ROBERT MINASSIANS |
| ELECTRICAL-Rough | 12/8/2022 | Approved | ROBERT MINASSIANS |
| Floor/Roof Diaphrgm/Shear Wall | 12/8/2022 | Approved | ROBERT MINASSIANS |
| HVAC-Rough | 12/8/2022 | Approved | ROBERT MINASSIANS |
| MERV13>=Rough | 12/8/2022 | Approved | ROBERT MINASSIANS |
| PLUMBING-Rough | 12/8/2022 | Approved | ROBERT MINASSIANS |
| Insulation | 3/9/2023 | Approved | PATRICK LIEBREGT |
| Drywall Nailing | 7/10/2023 | Approved | JOEL ORDAZ |
| Green Building Rough | 7/10/2023 | Approved | JOEL ORDAZ |
| Shower Pan | 7/21/2023 | Approved | JOEL ORDAZ |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | ARAM AVAKIAN |
| Final | 11/14/2023 | Conditional Approval | ARAM AVAKIAN |
| Footing/Foundation/Slab | 11/14/2023 | Approved | ARAM AVAKIAN |
| Green Building Final | 11/14/2023 | Approved | ARAM AVAKIAN |
| MERV13>=Final | 11/14/2023 | Approved | ARAM AVAKIAN |
| SGSOV-Seismic Gas S/O Valve | 11/14/2023 | SGSOV Approved | ARAM AVAKIAN |
| Smoke Detectors | 11/14/2023 | Approved | ARAM AVAKIAN |