5844 W 77TH PL 90045
Certificate Information: 5844 W 77TH PL 90045
- Application / Permit
- 21014-30000-06164
- Plan Check / Job No.
- B21WL05466
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- One-story, ground floor addition to (E) Single Family Dwelling and attached garage to create irregular-shaped trellis with BBQ area with island under the trellis. "COMPLY WITH DEPARTMENT ORDER effective date 11/02/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- CofO Issued on 5/26/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/13/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/14/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 12/16/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/24/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 3/7/2022 | RAHEL BEYENE |
| Plan Check Approved | 3/15/2022 | KHUONG TRUONG |
| Issued | 3/15/2022 | APPLICANT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| CofO in Progress | 5/9/2022 | JOHN MATTILLO |
| Permit Finaled | 5/26/2022 | BRUCE TODD |
| CofO Issued | 5/26/2022 | BRUCE TODD |
| Permit Finaled | 5/26/2022 | BRUCE TODD |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/8/2022 | STEVEN JIN |
| Roof/Waste drainage to street | Cleared | 1/8/2022 | STEVEN JIN |
| GPI Written Notices | Cleared | 2/23/2022 | KHUONG TRUONG |
| Grading Pre-Inspection | Cleared | 2/23/2022 | KHUONG TRUONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Mohammadi,, Saeid; Lic. No.: C82330 | 17412 VENTUTRA BLVD 21 ENCINO, CA 91316 |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/21/2022 | Approved | MARIAN PODPORA |
| Pre-Inspection | 4/5/2022 | Approved | MARIAN PODPORA |
| Excavation/Setback/Form/Re-Bar | 4/6/2022 | Partial Approval | MARIAN PODPORA |
| ELECTRICAL-Rough | 4/18/2022 | Corrections Issued | JOHN MATTILLO |
| Footing/Foundation/Slab | 4/18/2022 | Approved | JOHN MATTILLO |
| PLUMBING-Final | 4/18/2022 | Approved | JOHN MATTILLO |
| Wood Frame | 4/18/2022 | Conditional Approval | JOHN MATTILLO |
| BUILDING-Rough-Frame | 4/20/2022 | Approved | JOHN MATTILLO |
| ELECTRICAL-Final | 4/20/2022 | Approved | JOHN MATTILLO |
| Final | 4/20/2022 | Conditional Approval | JOHN MATTILLO |
| Green Building Final | 4/20/2022 | Approved | JOHN MATTILLO |
| Green Building Rough | 4/20/2022 | Approved | JOHN MATTILLO |
| Smoke Detectors | 4/20/2022 | Approved | JOHN MATTILLO |