1477 S LIVONIA AVE 90035
Certificate Information: 1477 S LIVONIA AVE 90035
- Application / Permit
- 21014-30000-06126
- Plan Check / Job No.
- B21WL05412
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and altertation to (E) Single family dwelling. Fully equipped w/NFPA 13D fire sprinklers
- Permit Issued
- Issued on 9/21/2022
- Issuing Office
- Current Status
- CofO Issued on 6/24/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | ALFREDO JARA |
| Corrections Issued | 12/21/2021 | ALFREDO JARA |
| Quality Review Completed | 12/29/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 7/14/2022 | ALFREDO JARA |
| Applicant returned to address corrections | 8/24/2022 | ALFREDO JARA |
| Plan Check Approved | 8/25/2022 | ALFREDO JARA |
| No Progress | 8/26/2022 | ALFREDO JARA |
| Building Plans Picked Up | 8/26/2022 | APPLICANT |
| Plan Check Approved | 9/13/2022 | ALFREDO JARA |
| Issued | 9/21/2022 | APPLICANT |
| CofO in Progress | 6/17/2024 | MEL KHACHATOURIAN |
| Permit Finaled | 6/24/2024 | DANIEL ORRANTE |
| CofO Issued | 6/24/2024 | DANIEL ORRANTE |
| Permit Finaled | 6/24/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/14/2022 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 6/16/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 6/21/2022 | JEANIE LAM |
| Sewer availability | Cleared | 6/21/2022 | JEANIE LAM |
| GPI Written Notices | Cleared | 8/25/2022 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 8/25/2022 | ALFREDO JARA |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Ponderosa Pines Gen Contractors; Lic. No.: 450947-B | 9616 RIESHEL STREET PICO RIVERA, CA 90660 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/8/2022 | Corrections Issued | EVAN COOPER |
| Footing/Foundation/Slab | 12/28/2022 | Conditional Approval | JEREMY TODD |
| METHANE-Barrier | 12/28/2022 | Not Ready for Inspection | JEREMY TODD |
| METHANE-Subgrade | 12/28/2022 | Not Ready for Inspection | JEREMY TODD |
| Deputy Reinf. Concrete | 12/29/2022 | Conditional Approval | JEREMY TODD |
| METHANE-Barrier | 1/9/2023 | Approved | JEREMY TODD |
| METHANE-Subgrade | 1/9/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Approved | JEREMY TODD |
| Sewer | 1/18/2023 | Not Ready for Inspection | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2023 | Approved | JEREMY TODD |
| Sewer | 1/27/2023 | Approved | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 2/6/2023 | Conditional Approval | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 4/3/2023 | Approved | JEREMY TODD |
| ELECTRICAL-Rough | 7/31/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 7/31/2023 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/31/2023 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 9/12/2023 | Approved | MEL KHACHATOURIAN |
| Insulation | 9/12/2023 | Approved | MEL KHACHATOURIAN |
| Interior/Exterior Lathing | 9/12/2023 | Approved | MEL KHACHATOURIAN |
| Shower Pan | 9/12/2023 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Drywall Nailing | 9/22/2023 | Approved | MEL KHACHATOURIAN |
| Green Building Rough | 9/22/2023 | Approved | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 4/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 4/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| Final | 4/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| Footing/Foundation/Slab | 4/15/2024 | Approved | MEL KHACHATOURIAN |
| Gas Test | 4/15/2024 | Approved | MEL KHACHATOURIAN |
| Green Building Final | 4/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| HVAC-Final | 4/15/2024 | Partial Approval | MEL KHACHATOURIAN |
| METHANE-Final | 4/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| METHANE-Rough | 4/15/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 4/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| SGSOV-Seismic Gas S/O Valve | 4/15/2024 | SGSOV Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 4/15/2024 | Not Ready for Inspection | MEL KHACHATOURIAN |
| BUILDING-Rough-Frame | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| Final | 6/6/2024 | Corrections Issued | MEL KHACHATOURIAN |
| Green Building Final | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Final | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| METHANE-Rough | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| Smoke Detectors | 6/6/2024 | Approved | MEL KHACHATOURIAN |
| ELECTRICAL-Final | 6/14/2024 | Approved | MEL KHACHATOURIAN |
| Final | 6/14/2024 | OK to Issue CofO | MEL KHACHATOURIAN |
| HVAC-Final | 6/14/2024 | Approved | MEL KHACHATOURIAN |
| PLUMBING-Final | 6/14/2024 | Approved | MEL KHACHATOURIAN |
| Service/Power Release | 6/18/2024 | Approved | MEL KHACHATOURIAN |