10906 N MT GLEASON AVE 91042
Certificate Information: 10906 N MT GLEASON AVE 91042
- Application / Permit
- 21014-30000-06107
- Plan Check / Job No.
- B21WL05374
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- two story addition/remodel to (e) S.F.D.
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Valley
- Current Status
- Issued on 3/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/6/2022 | FELIPE HERNANDEZ |
| Corrections Issued | 1/10/2022 | FELIPE HERNANDEZ |
| Quality Review Completed | 2/10/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 11/15/2022 | YASHAR EMAMI |
| Applicant returned to address corrections | 12/5/2022 | YASHAR EMAMI |
| Plan Check Approved | 1/26/2023 | YASHAR EMAMI |
| Building Plans Picked Up | 1/31/2023 | APPLICANT |
| Issued | 3/28/2023 | APPLICANT |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 3/24/2022 | SERGIO VALENZUELA |
| Permit | Cleared | 5/10/2022 | DAGOVERTO GUERRERO |
| Roof/Waste drainage to street | Cleared | 5/10/2022 | DAGOVERTO GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 5/11/2022 | DAGOVERTO GUERRERO |
| Watercourse | Cleared | 5/12/2022 | DAGOVERTO GUERRERO |
| Trees in Parkway | Cleared | 6/3/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 11/2/2022 | LUIS LUVANO |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| NICHOLAS TROWBRIDGE, (818) 374-1174 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/1/2023 | Corrections Issued | DAVID ANDERSON |
| Footing/Foundation/Slab | 9/1/2023 | Not Ready for Inspection | DAVID ANDERSON |
| Pre-Inspection | 9/1/2023 | Approved | DAVID ANDERSON |
| Deputy Drilled-In Anchors | 9/25/2023 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 10/3/2023 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/12/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 2/12/2024 | Not Ready for Inspection | WILLIAM WREN |
| BUILDING-Rough-Frame | 2/27/2024 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 2/27/2024 | Not Ready for Inspection | WILLIAM WREN |
| Deputy Drilled-In Anchors | 6/13/2024 | Conditional Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/21/2024 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 6/21/2024 | Not Ready for Inspection | WILLIAM WREN |
| Insulation | 6/21/2024 | Partial Approval | WILLIAM WREN |
| PLUMBING-Rough | 6/21/2024 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 10/21/2024 | Not Ready for Inspection | WILLIAM WREN |
| Green Building Rough | 10/21/2024 | Not Ready for Inspection | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2024 | Partial Approval | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 3/7/2025 | Corrections Issued | WILLIAM WREN |
| Green Building Rough | 3/7/2025 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 3/7/2025 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 4/7/2025 | Approved | WILLIAM WREN |
| HVAC-Rough | 10/15/2025 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 10/15/2025 | Partial Approval | WILLIAM WREN |
| ELECTRICAL-Rough | 3/16/2026 | Corrections Issued | NICHOLAS TROWBRIDGE |
| BUILDING-Rough-Frame | 3/24/2026 | Approved | NICHOLAS TROWBRIDGE |
| ELECTRICAL-Rough | 3/24/2026 | Approved | NICHOLAS TROWBRIDGE |