1121 E VAN BUREN AVE 90291
Certificate Information: 1121 E VAN BUREN AVE 90291
- Application / Permit
- 21014-30000-05964
- Plan Check / Job No.
- B21WL05258
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Bathroom and bicycle storage addition to (E) 1-story S.F.D.
- Permit Issued
- Issued on 8/6/2024
- Issuing Office
- West Los Angeles
- Current Status
- Issued on 8/6/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 1/5/2022 | FELIPE HERNANDEZ |
| Quality Review Completed | 1/31/2022 | CHIHARU SUZUKI |
| Building Plans Picked Up | 2/9/2022 | APPLICANT |
| Applicant returned to address corrections | 10/26/2023 | HOOMAN HAJIZADEH |
| Plan Check Approved | 6/13/2024 | HOOMAN HAJIZADEH |
| Issued | 8/6/2024 | APPLICANT |
Permit Application Clearance Information
| Permit | Cleared | 2/22/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 2/22/2022 | JOSE HERNANDEZ |
| ZI | Cleared | 3/2/2022 | PABLO ESTRADA |
| Trees in Parkway | Cleared | 4/6/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 12/6/2022 | ANTHONY VARGAS |
| Specific Plan | Cleared | 3/23/2023 | PEDRO AYALA |
| Eng Process Fee Ord 176,300 | Cleared | 3/28/2023 | AHMED AMARRAGY |
| Roof/Waste drainage to street | Cleared | 3/28/2023 | AHMED AMARRAGY |
| Coastal Zone | Cleared | 5/31/2024 | JAZMIN ROQUE |
| Specific Plan | Cleared | 5/31/2024 | JAZMIN ROQUE |
| ZI | Cleared | 5/31/2024 | JAZMIN ROQUE |
Contact Information
| Architect | Glen-Schieneman,, Magdalena J; Lic. No.: C28205 | 4445 STEWART AVENUE LOS ANGELES, CA 90066 |
| Contractor | Ssa Construction; Lic. No.: 1072146-B | 840 W 76TH ST LOS ANGELES, CA 90044 |
| Engineer | Lycklama,, James Heinz; Lic. No.: L7525 | 32218 N BIG OAK LN CASTAIC, CA 91384 |
| Engineer | Moon,, Samuel Sukjoon; Lic. No.: C49445 | 4020 MONTAIGNE WY PALOS VERDES PENINSULA, CA 90274 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/26/2024 | Partial Inspection | JESUS PINEDA |
| Special/Order Compliance | 9/26/2024 | Corrections Issued | JESUS PINEDA |
| Deputy Drilled-In Anchors | 2/24/2025 | Conditional Approval | JESUS PINEDA |
| Deputy Drilled-In Anchors | 3/5/2025 | Conditional Approval | JESUS PINEDA |
| ELECTRICAL-Rough | 3/26/2025 | Partial Approval | MICHAEL ALLEN |
| Footing/Foundation/Slab | 3/26/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 4/8/2025 | Approved | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2025 | Partial Approval | MICHAEL ALLEN |
| Deputy Wood Construction | 4/29/2025 | Partial Approval | MICHAEL ALLEN |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2025 | Approved | MICHAEL ALLEN |
| HVAC-Rough | 5/28/2025 | Approved | MICHAEL ALLEN |
| PLUMBING-Rough | 5/28/2025 | Approved | MICHAEL ALLEN |
| ELECTRICAL-Rough | 5/30/2025 | Approved | MICHAEL ALLEN |
| Special/Order Compliance | 5/30/2025 | Corrections Issued | MICHAEL ALLEN |
| Insulation | 7/21/2025 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Insulation | 7/29/2025 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 7/29/2025 | Approved | JESUS RODRIGUEZ |
| Service/Power Release | 7/29/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/22/2025 | Corrections Issued | BOBBY KEY |
| Green Building Rough | 9/22/2025 | Approved | BOBBY KEY |
| Interior/Exterior Lathing | 9/22/2025 | Partial Approval | BOBBY KEY |
| BUILDING-Rough-Frame | 10/17/2025 | Approved | WILBER ROSALES |
| Drywall Nailing | 11/3/2025 | Approved | WILBER ROSALES |
| Shower Pan | 1/29/2026 | Corrections Issued | DAKOTA LOW |
| Shower Pan | 2/2/2026 | Approved | DAKOTA LOW |
| Interior/Exterior Lathing | 2/17/2026 | Approved | DAKOTA LOW |