934 N ORLANDO AVE 90069
Certificate Information: 934 N ORLANDO AVE 90069
- Application / Permit
- 21014-30000-05961
- Plan Check / Job No.
- B21WL05255
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story Addition (623 sf) and remodel to (e) single story SFD (1,892 sf)
- Permit Issued
- Issued on 3/24/2023
- Issuing Office
- Current Status
- CofO Issued on 5/29/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/22/2021 | REZA HAGHIGHAT |
| Corrections Issued | 1/3/2022 | REZA HAGHIGHAT |
| Quality Review Completed | 1/10/2022 | TARIK SAOUD |
| Applicant returned to address corrections | 8/7/2022 | REZA HAGHIGHAT |
| Building Plans Picked Up | 9/19/2022 | APPLICANT |
| Plan Check Approved | 3/23/2023 | REZA HAGHIGHAT |
| Issued | 3/24/2023 | APPLICANT |
| CofO in Progress | 5/23/2024 | AMIR NAZARIAN |
| CofO Issued | 5/29/2024 | DEROLD HAUFF |
| Permit Finaled | 5/29/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Low Impact Development | Cleared | 6/20/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 7/9/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 7/18/2022 | STEVE MELGAR |
Contact Information
| Contractor | Rodo Development Inc; Lic. No.: 1100805-B | 5260 ROYER AVE WOODLAND, CA 91367 |
| Engineer | Erdelyi,, Peter Tibor; Lic. No.: C26962 | 2999 OVERLAND AVE STE 103 LOS ANGELES, CA 90064 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/13/2023 | Approved | MICHAEL LEWIS |
| PLUMBING-Rough | 5/17/2023 | Corrections Issued | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 5/23/2023 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 5/23/2023 | Partial Approval | LILIANA PORTILLO |
| Sewer | 5/23/2023 | Approved | LILIANA PORTILLO |
| Footing/Foundation/Slab | 5/30/2023 | Corrections Issued | LILIANA PORTILLO |
| Deputy Drilled-In Anchors | 5/31/2023 | Partial Approval | JEFFREY MEAD |
| Footing/Foundation/Slab | 6/7/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 6/22/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2023 | Partial Approval | LILIANA PORTILLO |
| Deputy Wood Construction | 6/28/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 6/28/2023 | Partial Approval | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/31/2023 | Corrections Issued | LILIANA PORTILLO |
| HVAC-Rough | 7/31/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 7/31/2023 | Corrections Issued | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 8/16/2023 | Corrections Issued | LILIANA PORTILLO |
| ELECTRICAL-Rough | 8/16/2023 | Approved | LILIANA PORTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/16/2023 | Approved | LILIANA PORTILLO |
| PLUMBING-Rough | 8/16/2023 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 9/1/2023 | Partial Approval | LILIANA PORTILLO |
| Insulation | 9/1/2023 | Conditional Approval | LILIANA PORTILLO |
| Interior/Exterior Lathing | 9/12/2023 | Approved | LILIANA PORTILLO |
| Shower Pan | 9/12/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 9/13/2023 | Approved | LILIANA PORTILLO |
| Green Building Rough | 9/13/2023 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 12/28/2023 | Not Ready for Inspection | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/3/2024 | Corrections Issued | BRENDAN MORELLI |
| Service/Power Release | 1/3/2024 | Approved | BRENDAN MORELLI |
| BUILDING-Rough-Frame | 3/28/2024 | Partial Inspection | AMIR NAZARIAN |
| ELECTRICAL-Final | 3/28/2024 | Approved | AMIR NAZARIAN |
| Final | 3/28/2024 | Corrections Issued | AMIR NAZARIAN |
| Green Building Final | 3/28/2024 | Approved | AMIR NAZARIAN |
| HVAC-Final | 3/28/2024 | No Access for Inspection | AMIR NAZARIAN |
| PLUMBING-Final | 3/28/2024 | Approved | AMIR NAZARIAN |
| SGSOV-Seismic Gas S/O Valve | 3/28/2024 | SGSOV Approved | AMIR NAZARIAN |
| Smoke Detectors | 3/28/2024 | Approved | AMIR NAZARIAN |
| BUILDING-Rough-Frame | 4/17/2024 | Approved | AMIR NAZARIAN |
| Final | 4/17/2024 | Corrections Issued | AMIR NAZARIAN |
| Final | 5/9/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Final | 5/14/2024 | Conditional Approval | AMIR NAZARIAN |
| Final | 5/21/2024 | OK to Issue CofO | AMIR NAZARIAN |