3115-3117 S GLENDON AVE 90034

Certificate Information: 3115-3117 S GLENDON AVE 90034

Application / Permit
21014-30000-05842
Plan Check / Job No.
B21WL05145
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Junior Accessory Dwelling Unit
Work Description
Addition to a single family home and conversion of the garage into a JADU.
Permit Issued
Issued on 8/5/2022
Issuing Office
West Los Angeles
Current Status
CofO Issued on 5/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/19/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 RICHARD GARCIA
Corrections Issued 11/28/2021 RICHARD GARCIA
Applicant returned to address corrections 1/15/2022 RICHARD GARCIA
Plan Check Approved 2/22/2022 RICHARD GARCIA
Building Plans Picked Up 2/24/2022 APPLICANT
Issued 8/5/2022 APPLICANT
CofO in Progress 5/16/2024 JESUS PINEDA
Permit Finaled 5/22/2024 DANIEL ORRANTE
CofO Issued 5/22/2024 DANIEL ORRANTE
Permit Finaled 5/22/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 12/11/2021 JOSE HERNANDEZ
Sewer availability Cleared 12/11/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 12/13/2021 JOSE HERNANDEZ
Roof/Waste drainage to street Cleared 12/13/2021 JOSE HERNANDEZ
Specific Plan Cleared 12/14/2021 RUBEN VASQUEZ
ZI Cleared 12/14/2021 RUBEN VASQUEZ
ZI Cleared 12/14/2021 RUBEN VASQUEZ
Specific Plan Cleared 12/21/2021 VALERIA CEJA
Grading Pre-Inspection Cleared 1/25/2022 RICHARD GARCIA

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor True North Designs; Lic. No.: 541817-B 12430 MITCHELL AVENUE      LOS ANGELES, CA 90066

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Grading Pre-Inspection 9/9/2022 Partial Approval JOHNNY MIRANDA
Pre-Inspection 9/9/2022 Partial Approval JOHNNY MIRANDA
Deputy Drilled-In Anchors 9/28/2022 Conditional Approval MICHAEL PELHAM
Footing/Foundation/Slab 9/29/2022 Corrections Issued JOHNNY MIRANDA
Footing/Foundation/Slab 10/3/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 10/12/2022 Partial Approval JOHNNY MIRANDA
Wood Frame 10/12/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Partial Approval CLAYTON GRAHAM
ELECTRICAL-Rough 11/8/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Partial Approval JOHNNY MIRANDA
PLUMBING-Rough 11/8/2022 Partial Approval JOHNNY MIRANDA
Underground Mechanical 11/8/2022 Not Ready for Inspection JOHNNY MIRANDA
Wood Frame 11/8/2022 Not Ready for Inspection JOHNNY MIRANDA
Deputy Wood Construction 11/9/2022 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 11/10/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/16/2022 Partial Approval JOHNNY MIRANDA
Interior/Exterior Lathing 11/16/2022 Partial Approval JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 11/18/2022 Partial Approval JOHNNY MIRANDA
BUILDING-Rough-Frame 2/9/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 2/9/2023 Corrections Issued HERBERT GIRON
Green Building Rough 2/9/2023 Not Ready for Inspection HERBERT GIRON
HVAC-Rough 2/9/2023 Corrections Issued HERBERT GIRON
MERV13>=Rough 2/9/2023 Not Ready for Inspection HERBERT GIRON
PLUMBING-Rough 2/9/2023 Approved HERBERT GIRON
BUILDING-Rough-Frame 2/17/2023 Approved JOHNNY MIRANDA
ELECTRICAL-Rough 2/17/2023 Approved JOHNNY MIRANDA
Green Building Rough 2/17/2023 Approved JOHNNY MIRANDA
HVAC-Rough 2/17/2023 Approved JOHNNY MIRANDA
MERV13>=Rough 2/17/2023 Approved JOHNNY MIRANDA
PLUMBING-Rough 2/17/2023 Approved JOHNNY MIRANDA
Insulation 2/23/2023 Approved JOHNNY MIRANDA
Drywall Nailing 3/2/2023 Approved JOHNNY MIRANDA
Shower Pan 4/11/2023 Corrections Issued DAVID FEILER
Shower Pan 4/14/2023 Not Ready for Inspection JOHNNY MIRANDA
Interior/Exterior Lathing 4/18/2023 Approved JESUS RODRIGUEZ
Shower Pan 4/18/2023 Approved JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 9/14/2023 Approved BEN MOLSTAD
Final 12/22/2023 Corrections Issued JESUS PINEDA
Footing/Foundation/Slab 12/22/2023 Approved JESUS PINEDA
Green Building Final 12/22/2023 Approved JESUS PINEDA
MERV13>=Final 12/22/2023 Approved JESUS PINEDA
SGSOV-Seismic Gas S/O Valve 12/22/2023 SGSOV Approved JESUS PINEDA
Smoke Detectors 12/22/2023 Approved JESUS PINEDA
Final 5/16/2024 OK to Issue CofO JESUS PINEDA