3432 S DENISON AVE 90731
Certificate Information: 3432 S DENISON AVE 90731
- Application / Permit
- 21014-30000-05810
- Plan Check / Job No.
- B21WL05105
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Add new master bedroom & bath. Add to (e) kitchen & (e) bedroom. Relocate existing laundry and add new rear deck. Total addition 501 SF
- Permit Issued
- Issued on 1/11/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 3/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | RICHARD GARCIA |
| Corrections Issued | 11/28/2021 | RICHARD GARCIA |
| Building Plans Picked Up | 12/3/2021 | APPLICANT |
| Applicant returned to address corrections | 11/3/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 11/18/2022 | RICHARD GARCIA |
| Plan Check Approved | 1/11/2023 | JOHNPAUL ISIP |
| Issued | 1/11/2023 | APPLICANT |
| CofO in Progress | 2/27/2025 | JOSEPH MCGARRY |
| Permit Finaled | 3/3/2025 | ANSON MAGLASANG |
| CofO Issued | 3/3/2025 | ANSON MAGLASANG |
| Permit Finaled | 3/3/2025 | ANSON MAGLASANG |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/28/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 4/29/2022 | JOSE HERNANDEZ |
| Low Impact Development | Cleared | 10/25/2022 | ROGELIO CORTES |
| Coastal Zone | Cleared | 11/18/2022 | RYAN LY |
| GPI Written Notices | Cleared | 11/18/2022 | RICHARD GARCIA |
| Grading Pre-Inspection | Cleared | 11/18/2022 | RICHARD GARCIA |
| Roof/Waste drainage to street | Cleared | 12/20/2022 | ERIK BEASLEY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Hale,, Ronald Richard; Lic. No.: C17056 | 1869 PALACIOS DR SAN PEDRO, CA 90732 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/22/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 4/14/2023 | Partial Approval | JOHN KLARIN |
| BUILDING-Rough-Frame | 5/11/2023 | Partial Approval | JOHN KLARIN |
| Green Building Rough | 5/11/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 5/11/2023 | Partial Approval | JOHN KLARIN |
| Pre-Inspection | 5/11/2023 | Approved | JOHN KLARIN |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Partial Approval | JAMES CHAVEZ |
| Green Building Rough | 5/17/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Insulation | 5/17/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Pre-Inspection | 5/17/2023 | Partial Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/31/2023 | Approved | JOHN KLARIN |
| Pre-Inspection | 5/31/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 6/22/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 6/22/2023 | Not Required | JOHN KLARIN |
| BUILDING-Rough-Frame | 6/23/2023 | Not Ready for Inspection | JOHN KLARIN |
| ELECTRICAL-Rough | 6/23/2023 | Approved | JOHN KLARIN |
| Footing/Foundation/Slab | 6/23/2023 | Approved | JOHN KLARIN |
| Green Building Rough | 6/23/2023 | Approved | JOHN KLARIN |
| HVAC-Rough | 6/23/2023 | Corrections Issued | JOHN KLARIN |
| PLUMBING-Rough | 6/23/2023 | Approved | JOHN KLARIN |
| ELECTRICAL-Rough | 6/27/2023 | Approved | JOHN KLARIN |
| HVAC-Rough | 6/27/2023 | Approved | JOHN KLARIN |
| PLUMBING-Rough | 6/27/2023 | Approved | JOHN KLARIN |
| Insulation | 7/5/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Insulation | 7/10/2023 | Approved | JAMES CHAVEZ |
| Drywall Nailing | 7/26/2023 | Approved | JOHN KLARIN |
| Shower Pan | 8/3/2023 | Approved | JOHN KLARIN |
| Interior/Exterior Lathing | 8/9/2023 | Approved | JOHN KLARIN |
| BUILDING-Rough-Frame | 1/24/2025 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 1/24/2025 | Corrections Issued | JOSEPH MCGARRY |
| Green Building Final | 1/24/2025 | Approved | JOSEPH MCGARRY |
| SGSOV-Seismic Gas S/O Valve | 1/24/2025 | SGSOV Approved | JOSEPH MCGARRY |
| Smoke Detectors | 1/24/2025 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/31/2025 | Approved | EUGENE CASSIDY |
| Final | 1/31/2025 | Corrections Issued | EUGENE CASSIDY |
| Final | 2/26/2025 | OK to Issue CofO | JOSEPH MCGARRY |