11712 W EXPOSITION BLVD 90064
Certificate Information: 11712 W EXPOSITION BLVD 90064
- Application / Permit
- 21014-30000-05794
- Plan Check / Job No.
- B21WL05081
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Convert (E) 160 s.f. detached garage to ADU at rear of the lot per LAMC 12.22A33(c) & (d) and add 95 s.f. to the side of the ADU.
- Permit Issued
- Issued on 5/31/2022
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/24/2021 | JAHANSHAH POURHASSAN |
| Corrections Issued | 12/6/2021 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 1/4/2022 | JAHANSHAH POURHASSAN |
| Applicant returned to address corrections | 2/8/2022 | EDWIN ESPIN |
| Plan Check Approved | 3/3/2022 | EDWIN ESPIN |
| Issued | 5/31/2022 | APPLICANT |
| Building Plans Picked Up | 6/7/2022 | APPLICANT |
| CofO in Progress | 11/14/2023 | KENNETH NAGLE |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
| CofO Issued | 11/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 12/11/2021 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 12/11/2021 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 12/13/2021 | JOSE HERNANDEZ |
| Specific Plan | Cleared | 12/14/2021 | DYLAN SITTIG |
Contact Information
| Contractor | Yu Construction; Lic. No.: 1054615-B | 11627 RIO HONDO PKWAY EL MONTE, CA 91732 |
| Engineer | Chen,, Junfei; Lic. No.: C85841 | 726 FAMILY TREE IRVINE, CA 92618 |
Inspector Information
| ANTHONY EGSON, (310) 914-3893 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/24/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Sewer | 6/30/2022 | Corrections Issued | OGANES TARAKHCHYAN |
| Sewer | 7/7/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Pre-Inspection | 7/12/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/25/2022 | Partial Inspection | JOHN KIDWELL |
| Deputy Drilled-In Anchors | 7/26/2022 | Conditional Approval | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 7/28/2022 | Corrections Issued | RICHARD STEINBACH |
| Excavation/Setback/Form/Re-Bar | 8/1/2022 | Corrections Issued | JOHN KIDWELL |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Approved | JOHN KIDWELL |
| ELECTRICAL-Rough | 9/30/2022 | No Access for Inspection | JOHN KIDWELL |
| PLUMBING-Rough | 9/30/2022 | No Access for Inspection | JOHN KIDWELL |
| Wood Frame | 9/30/2022 | No Access for Inspection | JOHN KIDWELL |
| ELECTRICAL-Rough | 10/4/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| PLUMBING-Rough | 10/4/2022 | Not Ready for Inspection | ASHLEY THOMPSON |
| Pre-Inspection | 10/4/2022 | Approved | ASHLEY THOMPSON |
| Wood Frame | 10/4/2022 | Corrections Issued | ASHLEY THOMPSON |
| Wood Frame | 10/5/2022 | No Access for Inspection | EVAN COOPER |
| Wood Frame | 10/6/2022 | Corrections Issued | ANDREW NAVE |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Rough | 11/1/2022 | Corrections Issued | CLAYTON GRAHAM |
| HVAC-Rough | 11/1/2022 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 11/1/2022 | Corrections Issued | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 11/4/2022 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Rough | 11/4/2022 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Rough | 11/4/2022 | Corrections Issued | ASHLEY THOMPSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/7/2023 | Corrections Issued | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 2/8/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 2/27/2023 | Corrections Issued | CLAYTON GRAHAM |
| PLUMBING-Rough | 2/27/2023 | Approved | CLAYTON GRAHAM |
| ELECTRICAL-Rough | 3/2/2023 | Approved | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/2/2023 | Partial Approval | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/23/2023 | No Access for Inspection | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Corrections Issued | CLAYTON GRAHAM |
| Interior/Exterior Lathing | 3/28/2023 | Corrections Issued | CLAYTON GRAHAM |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Not Ready for Inspection | JEREMY TODD |
| Floor/Roof Diaphrgm/Shear Wall | 4/13/2023 | Not Ready for Inspection | JESUS PINEDA |
| BUILDING-Rough-Frame | 4/18/2023 | Corrections Issued | CLAYTON GRAHAM |
| Green Building Rough | 4/18/2023 | Approved | CLAYTON GRAHAM |
| HVAC-Rough | 4/18/2023 | Approved | CLAYTON GRAHAM |
| Insulation | 4/26/2023 | Approved | JESUS PINEDA |
| Drywall Nailing | 5/15/2023 | Corrections Issued | HERBERT GIRON |
| Drywall Nailing | 5/23/2023 | Approved | JOHNNY MIRANDA |
| Shower Pan | 7/11/2023 | Corrections Issued | JEREMY TODD |
| Shower Pan | 7/13/2023 | Approved | JEREMY TODD |
| BUILDING-Rough-Frame | 9/19/2023 | Not Ready for Inspection | KENNETH NAGLE |
| Final | 9/19/2023 | Corrections Issued | KENNETH NAGLE |
| Footing/Foundation/Slab | 9/19/2023 | Approved | KENNETH NAGLE |
| Green Building Final | 9/19/2023 | Not Ready for Inspection | KENNETH NAGLE |
| SGSOV-Seismic Gas S/O Valve | 9/19/2023 | SGSOV Not Ready | KENNETH NAGLE |
| Smoke Detectors | 9/19/2023 | Corrections Issued | KENNETH NAGLE |
| Final | 10/6/2023 | Not Ready for Inspection | CLAYTON GRAHAM |
| Green Building Final | 10/6/2023 | Approved | CLAYTON GRAHAM |
| PLUMBING-Final | 10/6/2023 | Approved | CLAYTON GRAHAM |
| SGSOV-Seismic Gas S/O Valve | 10/6/2023 | SGSOV Not Ready | CLAYTON GRAHAM |
| Smoke Detectors | 10/6/2023 | Approved | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 10/17/2023 | Corrections Issued | BEN MOLSTAD |
| Final | 10/17/2023 | Corrections Issued | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 10/17/2023 | SGSOV Approved | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/3/2023 | Not Ready for Inspection | BEN MOLSTAD |
| ELECTRICAL-Final | 11/3/2023 | Corrections Issued | BEN MOLSTAD |
| Final | 11/3/2023 | Not Ready for Inspection | BEN MOLSTAD |
| HVAC-Final | 11/3/2023 | Corrections Issued | BEN MOLSTAD |
| PLUMBING-Final | 11/3/2023 | Corrections Issued | BEN MOLSTAD |
| BUILDING-Rough-Frame | 11/9/2023 | Approved | KENNETH NAGLE |
| ELECTRICAL-Final | 11/9/2023 | Approved | KENNETH NAGLE |
| Final | 11/9/2023 | Conditional Approval | KENNETH NAGLE |
| HVAC-Final | 11/9/2023 | Approved | KENNETH NAGLE |
| PLUMBING-Final | 11/9/2023 | Approved | KENNETH NAGLE |