5007 N MURIETTA AVE 91423
Certificate Information: 5007 N MURIETTA AVE 91423
- Application / Permit
- 21014-30000-05793
- Plan Check / Job No.
- B21WL05079
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 1-story addition (1,115 sf) to (e) single story SFD (1,097 sf) and remodel
- Permit Issued
- Issued on 7/11/2022
- Issuing Office
- Current Status
- CofO Issued on 1/31/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/9/2021 | REZA HAGHIGHAT |
| Corrections Issued | 12/13/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 12/22/2021 | TARIK SAOUD |
| Plan Check Approved | 7/8/2022 | REZA HAGHIGHAT |
| Issued | 7/11/2022 | APPLICANT |
| Building Plans Picked Up | 7/20/2022 | APPLICANT |
| CofO in Progress | 12/13/2023 | MISAEL ESPARZA |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
| CofO Issued | 1/31/2024 | RUBEN SALAS |
| Permit Finaled | 1/31/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/23/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/23/2022 | CARLOS AGUILERA |
| ZI | Cleared | 2/23/2022 | RICHARD REASER |
| Low Impact Development | Cleared | 3/15/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 3/21/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Copper Construction Llc; Lic. No.: 1060557-B | 605 S MILLIKEN AVENUE UNIT D ONTARIO, CA 91761 |
| Engineer | Chen,, Junfei; Lic. No.: C85841 | 726 FAMILY TREE IRVINE, CA 92618 |
Inspector Information
| MISAEL ESPARZA, (818) 374-1169 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/2/2022 | Corrections Issued | MISAEL ESPARZA |
| Footing/Foundation/Slab | 9/7/2022 | Approved | MISAEL ESPARZA |
| PLUMBING-Rough | 10/13/2022 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/27/2022 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Approved | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/8/2023 | Corrections Issued | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 3/28/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/1/2023 | Corrections Issued | MISAEL ESPARZA |
| PLUMBING-Rough | 5/1/2023 | Approved | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/8/2023 | Corrections Issued | MISAEL ESPARZA |
| ELECTRICAL-Rough | 5/8/2023 | Approved | MISAEL ESPARZA |
| Green Building Rough | 5/8/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| HVAC-Rough | 5/8/2023 | Corrections Issued | MISAEL ESPARZA |
| BUILDING-Rough-Frame | 5/15/2023 | Conditional Approval | ROBERT GOLD |
| Deputy Wood Construction | 5/15/2023 | Conditional Approval | MICHAEL SMITH |
| Green Building Rough | 5/15/2023 | Partial Inspection | ROBERT GOLD |
| HVAC-Rough | 5/15/2023 | Approved | ROBERT GOLD |
| Structural Steel Frame | 5/15/2023 | Not Ready for Inspection | ROBERT GOLD |
| Deputy Wood Construction | 5/16/2023 | Conditional Approval | MICHAEL SMITH |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Corrections Issued | JOHN COLEMAN |
| Underground Mechanical | 5/26/2023 | Partial Approval | JOHN COLEMAN |
| BUILDING-Rough-Frame | 7/13/2023 | Approved | JUAN VALENZUELA |
| Green Building Rough | 7/13/2023 | Approved | JUAN VALENZUELA |
| Insulation | 7/13/2023 | Conditional Approval | JUAN VALENZUELA |
| Verify Sprinkler Sign Off | 7/13/2023 | Approved | JUAN VALENZUELA |
| Drywall Nailing | 7/25/2023 | Approved | MISAEL ESPARZA |
| Interior/Exterior Lathing | 7/25/2023 | Approved | MISAEL ESPARZA |
| Shower Pan | 8/10/2023 | Corrections Issued | MISAEL ESPARZA |
| Shower Pan | 8/14/2023 | Approved | MISAEL ESPARZA |
| ELECTRICAL-Final | 10/4/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Service/Power Release | 10/4/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 10/17/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 10/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| SGSOV-Seismic Gas S/O Valve | 10/17/2023 | SGSOV Approved | MISAEL ESPARZA |
| Service/Power Release | 10/17/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Smoke Detectors | 10/17/2023 | Approved | MISAEL ESPARZA |
| Final | 12/5/2023 | Corrections Issued | MISAEL ESPARZA |
| Green Building Final | 12/5/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Final | 12/11/2023 | OK to Issue CofO | MISAEL ESPARZA |
| Green Building Final | 12/11/2023 | Approved | MISAEL ESPARZA |
| Service/Power Release | 12/11/2023 | Approved | MISAEL ESPARZA |