23233 W LADRILLO ST 91367
Certificate Information: 23233 W LADRILLO ST 91367
- Application / Permit
- 21014-30000-05771
- Plan Check / Job No.
- B21WL05037
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADDITON AND REMODEL (E) SFD. PER ENGINEERING DESIGN.
- Permit Issued
- Issued on 12/21/2021
- Issuing Office
- Current Status
- CofO Issued on 8/31/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | RICHARD GARCIA |
| Corrections Issued | 11/23/2021 | RICHARD GARCIA |
| Plan Check Approved | 12/14/2021 | ALFREDO JARA |
| Building Plans Picked Up | 12/15/2021 | APPLICANT |
| Issued | 12/21/2021 | APPLICANT |
| CofO in Progress | 5/26/2022 | TROY SANDERS |
| Permit Finaled | 8/31/2022 | JOHN JANSON |
| CofO Issued | 8/31/2022 | JOHN JANSON |
| Permit Finaled | 8/31/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 11/29/2021 | CARLOS AGUILERA |
| Sewer availability | Cleared | 11/29/2021 | CARLOS AGUILERA |
| Grading Pre-Inspection | Cleared | 12/1/2021 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | George,, George Amgad; Lic. No.: C91528 | 5 BROWNFIELD LN POMONA, CA 91766 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 12/27/2021 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/7/2022 | Partial Approval | TROY SANDERS |
| ELECTRICAL-Rough | 1/21/2022 | Approved | TROY SANDERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/21/2022 | Approved | TROY SANDERS |
| HVAC-Rough | 1/21/2022 | Approved | TROY SANDERS |
| PLUMBING-Rough | 1/21/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 2/7/2022 | Approved | TROY SANDERS |
| Insulation | 2/7/2022 | Approved | TROY SANDERS |
| Interior/Exterior Lathing | 2/7/2022 | Partial Approval | TROY SANDERS |
| Shower Pan | 2/7/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 5/13/2022 | Approved | TROY SANDERS |
| Final | 5/13/2022 | Not Ready for Inspection | TROY SANDERS |
| Green Building Final | 5/13/2022 | Approved | TROY SANDERS |
| Green Building Rough | 5/13/2022 | Approved | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 5/13/2022 | SGSOV Approved | TROY SANDERS |
| Smoke Detectors | 5/13/2022 | Approved | TROY SANDERS |
| Final | 5/25/2022 | OK to Issue CofO | TROY SANDERS |