Application / Permit
21014-30000-05771
Plan Check / Job No.
B21WL05037
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITON AND REMODEL (E) SFD. PER ENGINEERING DESIGN.
Permit Issued
Issued on 12/21/2021
Issuing Office
Current Status
CofO Issued on 8/31/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 RICHARD GARCIA
Corrections Issued 11/23/2021 RICHARD GARCIA
Plan Check Approved 12/14/2021 ALFREDO JARA
Building Plans Picked Up 12/15/2021 APPLICANT
Issued 12/21/2021 APPLICANT
CofO in Progress 5/26/2022 TROY SANDERS
Permit Finaled 8/31/2022 JOHN JANSON
CofO Issued 8/31/2022 JOHN JANSON
Permit Finaled 8/31/2022 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 11/29/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 11/29/2021 CARLOS AGUILERA
Sewer availability Cleared 11/29/2021 CARLOS AGUILERA
Grading Pre-Inspection Cleared 12/1/2021 BRIAN MILLER

Contact Information

Contractor Owner-Builder       ,
Engineer George,, George Amgad; Lic. No.: C91528 5 BROWNFIELD LN      POMONA, CA 91766

Inspector Information

GEVORK IPCHYAN, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI
TROY SANDERS, (818) 774-4308 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 12/27/2021 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/7/2022 Partial Approval TROY SANDERS
ELECTRICAL-Rough 1/21/2022 Approved TROY SANDERS
Floor/Roof Diaphrgm/Shear Wall 1/21/2022 Approved TROY SANDERS
HVAC-Rough 1/21/2022 Approved TROY SANDERS
PLUMBING-Rough 1/21/2022 Approved TROY SANDERS
Drywall Nailing 2/7/2022 Approved TROY SANDERS
Insulation 2/7/2022 Approved TROY SANDERS
Interior/Exterior Lathing 2/7/2022 Partial Approval TROY SANDERS
Shower Pan 2/7/2022 Approved TROY SANDERS
BUILDING-Rough-Frame 5/13/2022 Approved TROY SANDERS
Final 5/13/2022 Not Ready for Inspection TROY SANDERS
Green Building Final 5/13/2022 Approved TROY SANDERS
Green Building Rough 5/13/2022 Approved TROY SANDERS
SGSOV-Seismic Gas S/O Valve 5/13/2022 SGSOV Approved TROY SANDERS
Smoke Detectors 5/13/2022 Approved TROY SANDERS
Final 5/25/2022 OK to Issue CofO TROY SANDERS