757 S HOLMBY AVE 90024
Certificate Information: 757 S HOLMBY AVE 90024
- Application / Permit
- 21014-30000-05761
- Plan Check / Job No.
- B21WL05027
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel and 1st Floor Addition to an (E) 2-Story S.F.D *** 1 of 3 ***
- Permit Issued
- Issued on 3/23/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 12/17/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2021 | DAVID CASTILLO |
| Corrections Issued | 11/30/2021 | DAVID CASTILLO |
| Quality Review Completed | 12/7/2021 | TARIK SAOUD |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| Plan Check Approved | 2/16/2022 | DAVID CASTILLO |
| Issued | 3/23/2023 | APPLICANT |
| CofO in Progress | 12/11/2024 | STEPHANIE SWANSON |
| Permit Finaled | 12/17/2024 | RICHARD STEINBACH |
| CofO Issued | 12/17/2024 | RICHARD STEINBACH |
| Permit Finaled | 12/17/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/22/2022 | STEVEN JIN |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2022 | STEVEN JIN |
| Sewer availability | Cleared | 1/28/2022 | STEVEN JIN |
| Grading Pre-Inspection | Cleared | 2/16/2022 | DAVID CASTILLO |
Contact Information
| Architect | Lindfors,, Douglas A; Lic. No.: C27129 | 991 RICHARDSON AVENUE SIMI VALLEY, CA 93065 |
| Contractor | Dixon Construction Inc; Lic. No.: 706524-B | 3169 MOUNTAIN VIEW AVE LOS ANGELES, CA 90066 |
| Engineer | Niver,, Kenneth Earl; Lic. No.: S2554 | 10845 LINDBROOK DR STE 203 W LOS ANGELES, CA 90024 |
| Engineer | Yamashita,, Mark Alan; Lic. No.: L7155 | 6718 BIANCA AVE LAKE BALBOA, CA 91406 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/6/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/7/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 6/8/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/14/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Wood Construction | 8/9/2023 | Conditional Approval | MICHAEL PELHAM |
| Floor/Roof Diaphrgm/Shear Wall | 8/10/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/10/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/10/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/12/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/12/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 10/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/8/2023 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Rough | 11/8/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 11/14/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 11/14/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 11/14/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 11/20/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 11/20/2023 | Partial Approval | STEPHANIE SWANSON |
| Insulation | 11/30/2023 | Approved | BRENDAN LOONEY |
| Deputy Wood Construction | 12/1/2023 | Conditional Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/4/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 12/6/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 12/11/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 12/18/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 12/18/2023 | Conditional Approval | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 12/26/2023 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 4/8/2024 | Partial Approval | CHRISTOPHER WILSON |
| Gas Test | 4/10/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 5/22/2024 | Approved | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 5/22/2024 | SGSOV Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 10/2/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 10/2/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 10/2/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 10/2/2024 | Corrections Issued | STEPHANIE SWANSON |
| Smoke Detectors | 10/2/2024 | Approved | STEPHANIE SWANSON |
| Final | 11/8/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 12/11/2024 | Approved | STEPHANIE SWANSON |
| Final | 12/11/2024 | OK to Issue CofO | STEPHANIE SWANSON |
| HVAC-Final | 12/11/2024 | Approved | STEPHANIE SWANSON |