6672 W WHITLEY TER 90068

Certificate Information: 6672 W WHITLEY TER 90068

Application / Permit
21014-30000-05551
Plan Check / Job No.
B21WL04872
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Conversion of and addition to an (e) two-story detached accessory structure to create an ADU, *** 1 of 3 ***
Permit Issued
Issued on 7/18/2022
Issuing Office
Current Status
CofO Issued on 8/13/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/10/2021 RICHARD GARCIA
Corrections Issued 11/13/2021 RICHARD GARCIA
Quality Review Completed 11/22/2021 TARIK SAOUD
Applicant returned to address corrections 2/17/2022 RICHARD GARCIA
Plan Check Approved 3/16/2022 RICHARD GARCIA
Issued 7/18/2022 APPLICANT
Building Plans Picked Up 7/20/2022 APPLICANT
CofO in Progress 8/8/2024 ROY SPAULDING
Permit Finaled 8/13/2024 RONALD MYRICK
CofO Issued 8/13/2024 RONALD MYRICK
Permit Finaled 8/13/2024 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 12/9/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 12/9/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 12/9/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 12/9/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 12/9/2021 CELINA MORENO
BHO/Hillside ordinance Cleared 12/9/2021 CELINA MORENO
Roof/Waste drainage to street Cleared 12/9/2021 CELINA MORENO
Sewer availability Cleared 12/9/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/10/2021 CELINA MORENO
HPOZ Cleared 12/30/2021 DEEPEAKA DHALIWAL
ZI Cleared 12/30/2021 DEEPEAKA DHALIWAL
Hydrant and Access approval Cleared 1/5/2022 ROBERT DUFF
GPI Written Notices Cleared 2/17/2022 RICHARD GARCIA
Grading Pre-Inspection Cleared 2/17/2022 RICHARD GARCIA

Contact Information

Contractor Abraham Building & Consulting Inc; Lic. No.: 1046696-B 356 E AVENIDA DE LOS ARBOLES   B33    THOUSAND OAKS, CA 91360
Engineer Garcia,, Ricardo Ray; Lic. No.: C66957 27702 QUINCY ST      CASTAIC, CA 91384

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Special/Order Compliance 1/11/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/3/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/24/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/8/2023 No Access for Inspection RUBEN SALAS
Pre-Inspection 5/12/2023 Corrections Issued JOAQUIN GREENOUGH
Pre-Inspection 5/12/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/2/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/8/2023 Conditional Approval JOAQUIN GREENOUGH
Sewer 6/8/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 6/13/2023 Partial Approval JOAQUIN GREENOUGH
Sewer 6/13/2023 Corrections Issued JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 6/26/2023 Conditional Approval JOAQUIN GREENOUGH
Excavation/Setback/Form/Re-Bar 6/27/2023 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 6/27/2023 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 7/24/2023 Corrections Issued STUART CHAPMAN
Piling/Pier/Caisson 7/24/2023 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 7/28/2023 Not Ready for Inspection STUART CHAPMAN
Piling/Pier/Caisson 7/28/2023 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 7/31/2023 Partial Approval STUART CHAPMAN
Piling/Pier/Caisson 7/31/2023 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 8/1/2023 Partial Approval STUART CHAPMAN
Deputy Reinf. Concrete 8/2/2023 Conditional Approval JOAQUIN GREENOUGH
Deputy Drilled-In Anchors 8/14/2023 Conditional Approval JOAQUIN GREENOUGH
Deputy Shotcrete 8/24/2023 Conditional Approval JOAQUIN GREENOUGH
Sewer 8/31/2023 Approved JOAQUIN GREENOUGH
Footing/Foundation/Slab 9/7/2023 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/14/2023 Corrections Issued JOAQUIN GREENOUGH
ELECTRICAL-Rough 12/14/2023 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Conditional Approval JOAQUIN GREENOUGH
Green Building Rough 12/14/2023 Not Ready for Inspection JOAQUIN GREENOUGH
HVAC-Rough 12/14/2023 Not Ready for Inspection JOAQUIN GREENOUGH
MERV13>=Rough 12/14/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Rough 12/14/2023 Approved JOAQUIN GREENOUGH
HVAC-Rough 1/4/2024 Approved BRIAN SULLIVAN
Pre-Inspection 1/4/2024 Corrections Issued BRIAN SULLIVAN
Interior/Exterior Lathing 1/17/2024 Approved ROY SPAULDING
BUILDING-Rough-Frame 2/13/2024 Corrections Issued BRIAN SULLIVAN
Green Building Rough 2/13/2024 Approved BRIAN SULLIVAN
MERV13>=Rough 2/13/2024 Approved BRIAN SULLIVAN
Insulation 2/20/2024 Approved ROY SPAULDING
Drywall Nailing 2/26/2024 Approved ROY SPAULDING
Interior/Exterior Lathing 3/5/2024 Approved BRIAN SULLIVAN
Shower Pan 3/5/2024 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 6/3/2024 Approved ROY SPAULDING
ELECTRICAL-Final 6/3/2024 Approved ROY SPAULDING
Final 6/3/2024 Conditional Approval ROY SPAULDING
Green Building Final 6/3/2024 Approved ROY SPAULDING
HVAC-Final 6/3/2024 Approved ROY SPAULDING
MERV13>=Final 6/3/2024 Approved ROY SPAULDING
PLUMBING-Final 6/3/2024 Approved ROY SPAULDING
SGSOV-Seismic Gas S/O Valve 6/3/2024 SGSOV Approved ROY SPAULDING
Smoke Detectors 6/3/2024 Approved ROY SPAULDING
Final 8/7/2024 OK to Issue CofO ROY SPAULDING