5110 S 6TH AVE 90043

Certificate Information: 5110 S 6TH AVE 90043

Application / Permit
21014-30000-05543
Plan Check / Job No.
B21WL04869
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition to the rear (E) 1-story SFD PER ENGR OF RECORD
Permit Issued
Issued on 3/14/2023
Issuing Office
Metro
Current Status
CofO Issued on 4/14/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/5/2021 APPLICANT
Assigned to Plan Check Engineer 11/8/2021 JAHANSHAH POURHASSAN
Corrections Issued 11/9/2021 JAHANSHAH POURHASSAN
Plan Check Approved 10/12/2022 GEORGE ALVAREZ
Plan Check Approved 2/28/2023 RICARDO RAMIREZ
Issued 3/14/2023 APPLICANT
CofO in Progress 4/14/2025 LUIS CASTRO
CofO Issued 4/14/2025 DEROLD HAUFF
Permit Finaled 4/14/2025 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 10/7/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/11/2022 STEVE MELGAR

Contact Information

Contractor Bolden Ralph Eugene Construction; Lic. No.: 540324-B 1110 E PHILADELPHIA STREET   UNIT 1106    ONTARIO, CA 91761
Engineer Hamilton,, John O; Lic. No.: C53284 P O BOX 866      HAWTHORNE, CA 90251

Inspector Information

LUIS CASTRO, (213) 202-3436 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/20/2023 Approved ANTHONY EGSON
Footing/Foundation/Slab 3/23/2023 Corrections Issued ANTHONY EGSON
Footing/Foundation/Slab 3/28/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 4/10/2023 Corrections Issued MICHAEL LEWIS
Deputy Wood Construction 4/18/2023 Approved ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 11/27/2023 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 11/27/2023 Not Ready for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Partial Approval ANTHONY EGSON
Green Building Rough 11/27/2023 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 12/5/2023 Not Ready for Inspection ANTHONY EGSON
ELECTRICAL-Rough 12/5/2023 Partial Approval ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/5/2023 Corrections Issued ANTHONY EGSON
Green Building Rough 12/5/2023 Not Ready for Inspection ANTHONY EGSON
Deputy Wood Construction 12/6/2023 Conditional Approval BRENDAN MORELLI
Deputy Wood Construction 12/11/2023 Conditional Approval BRENDAN MORELLI
ELECTRICAL-Final 12/12/2023 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/12/2023 No Access for Inspection ANTHONY EGSON
PLUMBING-Final 12/12/2023 No Access for Inspection ANTHONY EGSON
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Partial Approval ANTHONY EGSON
Rough-Elec/Plmb/HVAC 12/14/2023 Not Ready for Inspection ANTHONY EGSON
BUILDING-Rough-Frame 12/28/2023 Approved ANTHONY EGSON
Green Building Rough 12/28/2023 Approved ANTHONY EGSON
Insulation 12/28/2023 Approved ANTHONY EGSON
Interior/Exterior Lathing 12/28/2023 Approved ANTHONY EGSON
Rough-Elec/Plmb/HVAC 12/28/2023 Approved ANTHONY EGSON
Drywall Nailing 1/3/2024 Approved JOSH MEISTER
ELECTRICAL-Final 6/20/2024 Approved ANTHONY EGSON
Final 6/20/2024 Corrections Issued ANTHONY EGSON
Green Building Final 6/20/2024 Not Ready for Inspection ANTHONY EGSON
HVAC-Final 6/20/2024 Approved ANTHONY EGSON
PLUMBING-Final 6/20/2024 Approved ANTHONY EGSON
SGSOV-Seismic Gas S/O Valve 6/20/2024 SGSOV Approved ANTHONY EGSON
Smoke Detectors 6/20/2024 Corrections Issued ANTHONY EGSON
Final 4/10/2025 Partial Approval LUIS CASTRO
Green Building Final 4/10/2025 Approved LUIS CASTRO
Smoke Detectors 4/10/2025 Approved LUIS CASTRO
Final 4/14/2025 OK to Issue CofO LUIS CASTRO