1417 S CRESTVIEW CT 90024
Certificate Information: 1417 S CRESTVIEW CT 90024
- Application / Permit
- 21014-30000-05509
- Plan Check / Job No.
- B21WL04846
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New 2-story ADU ( per state law).
- Permit Issued
- Issued on 4/13/2023
- Issuing Office
- West Los Angeles
- Current Status
- CofO Issued on 11/25/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2021 | HOOMAN HAJIZADEH |
| Corrections Issued | 12/2/2021 | HOOMAN HAJIZADEH |
| Quality Review Completed | 12/13/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 6/3/2022 | HOOMAN HAJIZADEH |
| Applicant returned to address corrections | 10/21/2022 | HOOMAN HAJIZADEH |
| Building Plans Picked Up | 11/16/2022 | APPLICANT |
| Plan Check Approved | 2/10/2023 | HOOMAN HAJIZADEH |
| No Progress | 3/30/2023 | HOOMAN HAJIZADEH |
| Plan Check Approved | 3/30/2023 | HOOMAN HAJIZADEH |
| Issued | 4/13/2023 | APPLICANT |
| CofO in Progress | 11/22/2024 | STEPHANIE SWANSON |
| Permit Finaled | 11/25/2024 | RICHARD STEINBACH |
| CofO Issued | 11/25/2024 | RICHARD STEINBACH |
| Permit Finaled | 11/25/2024 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 3/5/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2022 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 3/17/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 3/17/2022 | JOSE HERNANDEZ |
| Specific Plan | Cleared | 3/21/2022 | EDUARDO HERMOSO |
| Construction within easement | Cleared | 4/8/2022 | RIDWAN HARDY |
| GPI Written Notices | Cleared | 6/3/2022 | HOOMAN HAJIZADEH |
| Grading Pre-Inspection | Cleared | 6/3/2022 | HOOMAN HAJIZADEH |
Contact Information
| Architect | Heeb,, Derek M; Lic. No.: C32338 | 406 BROADWAY 222C SANTA MONICA, CA 90401 |
| Contractor | M Y Construction Inc; Lic. No.: 1036168-B | 10116 HILLGROVE DRIVE BEVERLY HILLS, CA 90210 |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
| Engineer | Tsou,, Jason Chia-Hsiang; Lic. No.: M22486 | 1355 WAVERLY CT UPLAND, CA 91786 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| Sewer | 4/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/14/2023 | Partial Approval | STEPHANIE SWANSON |
| Sewer | 7/14/2023 | Approved | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 8/30/2023 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Subgrade | 8/30/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Rough | 8/30/2023 | Corrections Issued | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 9/6/2023 | Corrections Issued | CARLOS MATAMOROS |
| PLUMBING-Rough | 9/6/2023 | Partial Approval | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 9/11/2023 | Corrections Issued | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 9/11/2023 | Not Ready for Inspection | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 9/21/2023 | Approved | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 9/21/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 9/21/2023 | No Access for Inspection | STEPHANIE SWANSON |
| METHANE-Barrier | 9/21/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 9/21/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 9/21/2023 | Corrections Issued | STEPHANIE SWANSON |
| Deputy Methane Barrier | 9/22/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 10/17/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/17/2023 | Partial Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 10/17/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 10/30/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 10/30/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/30/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 10/30/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| METHANE-Rough | 10/30/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Underground Mechanical | 10/30/2023 | Corrections Issued | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 10/30/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Methane Barrier | 11/13/2023 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 11/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| METHANE-Final | 11/28/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 11/28/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 1/3/2024 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 1/3/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Special/Order Compliance | 1/3/2024 | Partial Inspection | BEN MOLSTAD |
| BUILDING-Rough-Frame | 1/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 1/18/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 1/18/2024 | Approved | STEPHANIE SWANSON |
| Shower Pan | 1/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 1/31/2024 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 1/31/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 1/31/2024 | Corrections Issued | STEPHANIE SWANSON |
| Shower Pan | 1/31/2024 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 1/31/2024 | Approved | STEPHANIE SWANSON |
| Insulation | 2/27/2024 | Approved | CHRISTOPHER WILSON |
| Interior/Exterior Lathing | 2/27/2024 | Approved | CHRISTOPHER WILSON |
| Drywall Nailing | 3/5/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 3/5/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 9/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 9/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 9/17/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 9/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 9/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 9/17/2024 | SGSOV Not Ready | STEPHANIE SWANSON |
| Service/Power Release | 9/17/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Smoke Detectors | 9/17/2024 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 10/15/2024 | Approved | STEPHANIE SWANSON |
| Final | 10/15/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 10/15/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 10/15/2024 | Partial Approval | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 10/15/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Service/Power Release | 10/15/2024 | Not Ready for Inspection | STEPHANIE SWANSON |
| Final | 11/21/2024 | OK to Issue CofO | STEPHANIE SWANSON |
| Gas Test | 11/21/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 11/21/2024 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 11/21/2024 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 11/21/2024 | Approved | STEPHANIE SWANSON |