3863 S DEGNAN BLVD 90008
Certificate Information: 3863 S DEGNAN BLVD 90008
- Application / Permit
- 21014-30000-05502
- Plan Check / Job No.
- B21WL04842
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Addition and remodel (E) Single family dwelling. Per engineering design.
- Permit Issued
- Issued on 1/3/2022
- Issuing Office
- Current Status
- CofO Issued on 10/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/5/2021 | ALFREDO JARA |
| Corrections Issued | 11/8/2021 | ALFREDO JARA |
| Plan Check Approved | 11/17/2021 | ALFREDO JARA |
| Building Plans Picked Up | 11/17/2021 | APPLICANT |
| Issued | 1/3/2022 | APPLICANT |
| CofO in Progress | 9/19/2022 | ANTHONY EGSON |
| CofO Issued | 10/17/2022 | DEROLD HAUFF |
| Permit Finaled | 10/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 11/15/2021 | CINDY QI |
| Sewer availability | Cleared | 11/15/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/16/2021 | CINDY QI |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Minchez Construction Inc; Lic. No.: 1022183-B | 11211 OSBORNE STREET LAKE VIEW TERRACE, CA 91342 |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 1/6/2022 | Approved | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 1/19/2022 | Conditional Approval | ADAM ESCOTO |
| Floor/Roof Diaphrgm/Shear Wall | 1/20/2022 | Approved | ANTHONY EGSON |
| Pre-Inspection | 1/20/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/25/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 4/5/2022 | Corrections Issued | ANTHONY EGSON |
| Deputy Drilled-In Anchors | 4/6/2022 | No Access for Inspection | ANTHONY EGSON |
| Deputy Wood Construction | 4/6/2022 | No Access for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 4/28/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 4/28/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Rough | 4/28/2022 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 5/2/2022 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 5/2/2022 | Approved | ANTHONY EGSON |
| Green Building Rough | 5/2/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/6/2022 | Approved | ANTHONY EGSON |
| Insulation | 5/10/2022 | Approved | ANTHONY EGSON |
| Drywall Nailing | 5/25/2022 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 5/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Shower Pan | 5/25/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Interior/Exterior Lathing | 6/17/2022 | Approved | ANTHONY EGSON |
| Shower Pan | 6/17/2022 | Approved | ANTHONY EGSON |
| HVAC-Rough | 8/23/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 8/23/2022 | SGSOV Not Ready | ANTHONY EGSON |
| ELECTRICAL-Final | 8/29/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Gas Test | 8/29/2022 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Final | 8/29/2022 | Not Ready for Inspection | ANTHONY EGSON |
| PLUMBING-Final | 8/29/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 9/8/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 9/8/2022 | Corrections Issued | ANTHONY EGSON |
| Gas Test | 9/8/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Final | 9/8/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 9/8/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 9/8/2022 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 9/8/2022 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 9/8/2022 | Approved | ANTHONY EGSON |
| ELECTRICAL-Final | 9/13/2022 | Approved | ANTHONY EGSON |
| Final | 9/13/2022 | Corrections Issued | ANTHONY EGSON |
| HVAC-Final | 9/13/2022 | Approved | ANTHONY EGSON |
| PLUMBING-Final | 9/13/2022 | Approved | ANTHONY EGSON |
| Service/Power Release | 9/13/2022 | Approved | ANTHONY EGSON |
| Final | 9/16/2022 | OK to Issue CofO | ANTHONY EGSON |