12319 W 18TH HELENA DR 90049

Certificate Information: 12319 W 18TH HELENA DR 90049

Application / Permit
21014-30000-05473
Plan Check / Job No.
B21WL04814
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition *** 1 of 3 ***
Permit Issued
Issued on 6/7/2022
Issuing Office
Current Status
CofO Issued on 3/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/10/2021 FELIPE HERNANDEZ
Corrections Issued 11/16/2021 FELIPE HERNANDEZ
Quality Review Completed 11/24/2021 TARIK SAOUD
Applicant returned to address corrections 3/23/2022 FELIPE HERNANDEZ
Plan Check Approved 5/31/2022 FELIPE HERNANDEZ
Issued 6/7/2022 APPLICANT
Building Plans Picked Up 8/4/2022 APPLICANT
CofO in Progress 3/18/2024 ARAM AVEDISIAN
Permit Finaled 3/20/2024 DANIEL ORRANTE
CofO Issued 3/20/2024 DANIEL ORRANTE
Permit Finaled 3/20/2024 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 11/24/2021 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 11/30/2021 ANTHONY MAINEZ
Sewer availability Cleared 11/30/2021 ANTHONY MAINEZ
Trees in Parkway Cleared 12/28/2021 ADALBERTO VERA
Low Impact Development Cleared 3/4/2022 ROGELIO CORTES
Hydrant and Access approval Cleared 5/3/2022 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 5/13/2022 DINAH GARIN
GPI Written Notices Cleared 5/31/2022 FELIPE HERNANDEZ
Grading Pre-Inspection Cleared 5/31/2022 FELIPE HERNANDEZ

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor Pillar Building Group Llc; Lic. No.: 1017041-B 8109 ORION AVE      VAN NUYS, CA 91406
Engineer Le,, Thang Huu; Lic. No.: S4978 507 MAGELLAN RD      ARCADIA, CA 91007

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/18/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 11/21/2022 Partial Approval JUAN VALENZUELA
Footing/Foundation/Slab 12/8/2022 Not Ready for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 12/14/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 1/20/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Drilled-In Anchors 1/25/2023 Conditional Approval DAVID FEILER
Excavation/Setback/Form/Re-Bar 1/26/2023 Partial Approval STEPHANIE SWANSON
Footing/Foundation/Slab 1/26/2023 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/13/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 3/14/2023 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Partial Approval STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Corrections Issued OGANES TARAKHCHYAN
PLUMBING-Rough 3/24/2023 Approved OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 4/11/2023 Approved CHRISTOPHER WILSON
Shower Pan 4/14/2023 Approved JESUS PINEDA
ELECTRICAL-Rough 4/21/2023 Corrections Issued BRENDAN LOONEY
HVAC-Rough 4/24/2023 Partial Approval OGANES TARAKHCHYAN
Special/Order Compliance 4/24/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Rough 4/27/2023 Approved OGANES TARAKHCHYAN
Insulation 5/4/2023 Partial Inspection OGANES TARAKHCHYAN
Interior/Exterior Lathing 5/4/2023 Partial Approval OGANES TARAKHCHYAN
Green Building Rough 5/12/2023 Not Ready for Inspection OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/15/2023 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 5/17/2023 Approved CARLOS MATAMOROS
Green Building Rough 5/17/2023 Approved CARLOS MATAMOROS
Interior/Exterior Lathing 5/17/2023 Approved CARLOS MATAMOROS
Insulation 5/23/2023 Approved JESUS RODRIGUEZ
Drywall Nailing 6/1/2023 Approved OGANES TARAKHCHYAN
Gas Test 9/14/2023 Partial Approval OGANES TARAKHCHYAN
Gas Test 10/2/2023 Partial Approval OGANES TARAKHCHYAN
ELECTRICAL-Final 11/14/2023 Corrections Issued KENNETH NAGLE
Service/Power Release 11/14/2023 Approved KENNETH NAGLE
Gas Test 11/20/2023 Approved ARAM AVEDISIAN
HVAC-Final 11/20/2023 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 11/20/2023 SGSOV Approved ARAM AVEDISIAN
ELECTRICAL-Final 12/13/2023 Approved ARAM AVEDISIAN
Final 12/13/2023 Corrections Issued ARAM AVEDISIAN
Footing/Foundation/Slab 12/13/2023 Approved ARAM AVEDISIAN
Green Building Final 12/13/2023 Approved ARAM AVEDISIAN
PLUMBING-Final 12/13/2023 Approved ARAM AVEDISIAN
Smoke Detectors 12/13/2023 Approved ARAM AVEDISIAN
Final 3/18/2024 OK to Issue CofO ARAM AVEDISIAN