3389 S MANNING CT 90064

Certificate Information: 3389 S MANNING CT 90064

Application / Permit
21014-30000-05443
Plan Check / Job No.
B21WL04789
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition and remodel (E) SFD. Per engineering design.
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
CofO Issued on 2/1/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/29/2021 APPLICANT
Assigned to Plan Check Engineer 11/5/2021 KAVIAN REFAHI
Corrections Issued 11/7/2021 KAVIAN REFAHI
Plan Check Approved 1/31/2022 ALFREDO JARA
Issued 2/14/2022 APPLICANT
Building Plans Picked Up 2/17/2022 APPLICANT
CofO in Progress 1/26/2023 ASHLEY THOMPSON
Permit Finaled 2/1/2023 DANIEL ORRANTE
CofO Issued 2/1/2023 DANIEL ORRANTE
Permit Finaled 2/1/2023 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/21/2021 TRACY TATE
Roof/Waste drainage to street Cleared 12/21/2021 TRACY TATE
Sewer availability Cleared 12/21/2021 TRACY TATE
Grading Pre-Inspection Cleared 1/31/2022 KAVIAN REFAHI

Contact Information

Contractor Owner-Builder       ,
Engineer Garcia,, Eddy Alexander; Lic. No.: S6159 17958 LULL ST      RESEDA, CA 91335

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/23/2022 Approved JOHNNY MIRANDA
Footing/Foundation/Slab 3/10/2022 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 3/30/2022 Partial Approval KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 4/1/2022 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/13/2022 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 4/14/2022 Approved MICHAEL PELHAM
BUILDING-Rough-Frame 5/2/2022 Not Ready for Inspection KEVIN SARGSYAN
ELECTRICAL-Rough 5/2/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/2/2022 Partial Approval KEVIN SARGSYAN
Green Building Rough 5/2/2022 Not Ready for Inspection KEVIN SARGSYAN
MERV13>=Rough 5/2/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 5/2/2022 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 5/9/2022 Partial Approval EVAN COOPER
ELECTRICAL-Rough 5/9/2022 Partial Approval EVAN COOPER
Green Building Rough 5/9/2022 Partial Approval EVAN COOPER
HVAC-Rough 5/9/2022 Partial Approval EVAN COOPER
Interior/Exterior Lathing 5/9/2022 Partial Approval EVAN COOPER
MERV13>=Rough 5/9/2022 Partial Approval EVAN COOPER
PLUMBING-Rough 5/9/2022 Partial Approval EVAN COOPER
Shower Pan 5/9/2022 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 6/21/2022 No Result Entered RONALD WEBER
Footing/Foundation/Slab 6/23/2022 Partial Approval KEVIN SARGSYAN
PLUMBING-Rough 6/23/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 7/1/2022 Approved KEVIN SARGSYAN
PLUMBING-Rough 8/25/2022 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/19/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 10/19/2022 Approved OGANES TARAKHCHYAN
MERV13>=Rough 10/19/2022 Approved OGANES TARAKHCHYAN
Insulation 10/21/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 10/26/2022 Approved CLAYTON GRAHAM
Interior/Exterior Lathing 10/26/2022 Partial Approval CLAYTON GRAHAM
Interior/Exterior Lathing 10/28/2022 Not Ready for Inspection OGANES TARAKHCHYAN
Final 1/17/2023 Corrections Issued ASHLEY THOMPSON
Green Building Final 1/17/2023 Corrections Issued ASHLEY THOMPSON
MERV13>=Final 1/17/2023 Approved ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 1/17/2023 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 1/17/2023 Not Ready for Inspection ASHLEY THOMPSON
Final 1/25/2023 Conditional Approval ASHLEY THOMPSON
Green Building Final 1/25/2023 Approved ASHLEY THOMPSON
Smoke Detectors 1/25/2023 Approved ASHLEY THOMPSON