2411 N LA CONDESA DR 90049
Certificate Information: 2411 N LA CONDESA DR 90049
- Application / Permit
- 21014-30000-05427
- Plan Check / Job No.
- B21WL04779
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Replace existing second floor deck due to dry rot.
- Permit Issued
- Issued on 6/6/2022
- Issuing Office
- Current Status
- Permit Finaled on 2/9/2023
Permit Application Status History
| Submitted | 10/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | RICHARD GARCIA |
| Corrections Issued | 11/10/2021 | RICHARD GARCIA |
| Quality Review Completed | 11/22/2021 | TARIK SAOUD |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| Plan Check Approved | 12/22/2021 | RICHARD GARCIA |
| Issued | 6/6/2022 | APPLICANT |
| Permit Finaled | 2/8/2023 | KEVIN SARGSYAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2021 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 12/3/2021 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 12/22/2021 | RICHARD GARCIA |
Contact Information
| Contractor | Rohan Dean Construction; Lic. No.: 698469-B | 1310 NORTH FREDERIC STREET BURBANK, CA 91505 |
| Engineer | Martinez,, Michael Anthony; Lic. No.: S3825 | 902 15TH PLACE HERMOSA BEACH, CA 90254 |
Inspector Information
| KEVIN SARGSYAN, (310) 914-3889 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/13/2022 | Corrections Issued | JUAN VALENZUELA |
| Pre-Inspection | 6/13/2022 | Partial Inspection | JUAN VALENZUELA |
| Piling/Pier/Caisson | 6/15/2022 | Partial Approval | JUAN VALENZUELA |
| Deputy Reinf. Concrete | 6/17/2022 | Approved | MICHAEL PELHAM |
| Excavation/Setback/Form/Re-Bar | 6/22/2022 | Approved | JUAN VALENZUELA |
| Footing/Foundation/Slab | 6/22/2022 | Approved | JUAN VALENZUELA |
| Deputy Steel/Welding | 8/19/2022 | Conditional Approval | JUAN VALENZUELA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Partial Approval | KEVIN SARGSYAN |
| Special/Order Compliance | 10/31/2022 | Corrections Issued | KEVIN SARGSYAN |
| ELECTRICAL-Rough | 11/8/2022 | Corrections Issued | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 11/15/2022 | Approved | JUAN VALENZUELA |
| ELECTRICAL-Rough | 11/15/2022 | Approved | JUAN VALENZUELA |
| Green Building Rough | 11/15/2022 | Not Ready for Inspection | JUAN VALENZUELA |
| Interior/Exterior Lathing | 11/23/2022 | Approved | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 2/8/2023 | Approved | KEVIN SARGSYAN |
| Final | 2/8/2023 | Permit Finaled | KEVIN SARGSYAN |
| Green Building Final | 2/8/2023 | Approved | KEVIN SARGSYAN |
| Green Building Rough | 2/8/2023 | Approved | KEVIN SARGSYAN |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | KEVIN SARGSYAN |
| Smoke Detectors | 2/8/2023 | Approved | KEVIN SARGSYAN |