Deputy Grading
|
5/25/2022
|
Conditional Approval
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
6/13/2022
|
Corrections Issued
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
6/13/2022
|
Partial Inspection
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
6/21/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
6/21/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
7/12/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Reinforced Concrete Frame
|
7/12/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Deputy Grading
|
7/22/2022
|
Conditional Approval
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
8/2/2022
|
Partial Inspection
|
ANDREW NAVE
|
|
Footing/Foundation/Slab
|
8/2/2022
|
Partial Inspection
|
ANDREW NAVE
|
|
Excavation/Setback/Form/Re-Bar
|
8/16/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
8/16/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Deputy Grading
|
8/22/2022
|
Conditional Approval
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
8/26/2022
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
8/26/2022
|
Not Ready for Inspection
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
8/31/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Footing/Foundation/Slab
|
9/9/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
9/23/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Piling/Pier/Caisson
|
9/23/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
10/14/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Piling/Pier/Caisson
|
10/14/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
Piling/Pier/Caisson
|
10/20/2022
|
Partial Approval
|
JUAN VALENZUELA
|
|
PLUMBING-Rough
|
10/31/2022
|
Partial Inspection
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
12/5/2022
|
Corrections Issued
|
CHRISTOPHER WILSON
|
|
Footing/Foundation/Slab
|
12/5/2022
|
Not Ready for Inspection
|
CHRISTOPHER WILSON
|
|
Excavation/Setback/Form/Re-Bar
|
12/7/2022
|
Partial Approval
|
CHRISTOPHER WILSON
|
|
Deputy Steel/Welding
|
12/29/2022
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Reinf. Concrete
|
12/30/2022
|
Conditional Approval
|
JUAN VALENZUELA
|
|
Excavation/Setback/Form/Re-Bar
|
1/5/2023
|
Conditional Approval
|
BRENDAN LOONEY
|
|
FLOOD-Proofing Certificate
|
1/5/2023
|
Approved
|
BRENDAN LOONEY
|
|
Green Building Rough
|
1/5/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Structural Steel Frame
|
1/5/2023
|
Partial Approval
|
BRENDAN LOONEY
|
|
Verify Sprinkler Sign Off
|
1/5/2023
|
Not Ready for Inspection
|
BRENDAN LOONEY
|
|
Excavation/Setback/Form/Re-Bar
|
1/30/2023
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
PLUMBING-Rough
|
1/30/2023
|
Corrections Issued
|
STEPHANIE SWANSON
|
|
Deputy Steel/Welding
|
2/1/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Steel/Welding
|
2/2/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Excavation/Setback/Form/Re-Bar
|
2/7/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
PLUMBING-Rough
|
2/7/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
2/21/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Deputy Wood Construction
|
3/3/2023
|
Conditional Approval
|
MICHAEL PELHAM
|
|
Deputy Steel/Welding
|
3/6/2023
|
Conditional Approval
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
3/6/2023
|
Approved
|
KEVIN SARGSYAN
|
|
Structural Steel Frame
|
3/6/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
4/6/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
4/20/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
4/20/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
5/4/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
5/15/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Shower Pan
|
5/15/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
PLUMBING-Rough
|
5/25/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Deputy Wood Construction
|
5/31/2023
|
Conditional Approval
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
6/1/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
6/1/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
HVAC-Rough
|
6/1/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Interior/Exterior Lathing
|
6/1/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
PLUMBING-Rough
|
6/1/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
BUILDING-Rough-Frame
|
6/7/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Rough
|
6/7/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Verify Sprinkler Sign Off
|
6/7/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Rough
|
6/12/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Excavation/Setback/Form/Re-Bar
|
6/12/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Deputy Wood Construction
|
6/14/2023
|
No Access for Inspection
|
KENNETH NAGLE
|
|
ELECTRICAL-Rough
|
6/29/2023
|
Corrections Issued
|
HERBERT GIRON
|
|
Excavation/Setback/Form/Re-Bar
|
6/29/2023
|
Partial Approval
|
HERBERT GIRON
|
|
Insulation
|
6/29/2023
|
Partial Approval
|
HERBERT GIRON
|
|
Deputy Wood Construction
|
7/6/2023
|
Conditional Approval
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Rough
|
7/6/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Rough
|
7/12/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
HVAC-Rough
|
7/12/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
BUILDING-Rough-Frame
|
7/13/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Green Building Rough
|
7/13/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Verify Sprinkler Sign Off
|
7/13/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Deputy Wood Construction
|
7/17/2023
|
Conditional Approval
|
KEVIN SARGSYAN
|
|
Gas Test
|
7/18/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Underground Mechanical
|
7/18/2023
|
Approved
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/20/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
7/28/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Insulation
|
7/28/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
Deputy Wood Construction
|
8/31/2023
|
Approved
|
KEVIN SARGSYAN
|
|
Wood Frame
|
8/31/2023
|
Partial Inspection
|
KEVIN SARGSYAN
|
|
BUILDING-Rough-Frame
|
9/18/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Green Building Rough
|
9/18/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
PLUMBING-Rough
|
9/18/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Verify Sprinkler Sign Off
|
9/18/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
PLUMBING-Rough
|
9/26/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Wood Frame
|
9/26/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Insulation
|
9/29/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
PLUMBING-Rough
|
9/29/2023
|
Approved
|
KEVIN SARGSYAN
|
|
Floor/Roof Diaphrgm/Shear Wall
|
10/16/2023
|
Approved
|
KEVIN SARGSYAN
|
|
BUILDING-Rough-Frame
|
10/30/2023
|
Partial Approval
|
ARAM AVEDISIAN
|
|
Green Building Rough
|
10/30/2023
|
Not Ready for Inspection
|
ARAM AVEDISIAN
|
|
Insulation
|
10/30/2023
|
Partial Approval
|
ARAM AVEDISIAN
|
|
Verify Sprinkler Sign Off
|
10/30/2023
|
Partial Approval
|
ARAM AVEDISIAN
|
|
Interior/Exterior Lathing
|
10/31/2023
|
Not Ready for Inspection
|
ARAM AVEDISIAN
|
|
BUILDING-Rough-Frame
|
11/3/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Green Building Rough
|
11/3/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
Interior/Exterior Lathing
|
11/3/2023
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
PLUMBING-Rough
|
11/3/2023
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Verify Sprinkler Sign Off
|
11/3/2023
|
Approved
|
KEVIN SARGSYAN
|
|
BUILDING-Rough-Frame
|
11/15/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Rough
|
11/15/2023
|
Approved
|
KEVIN SARGSYAN
|
|
Green Building Rough
|
11/15/2023
|
Approved
|
KEVIN SARGSYAN
|
|
HVAC-Rough
|
11/15/2023
|
Approved
|
KEVIN SARGSYAN
|
|
Interior/Exterior Lathing
|
11/15/2023
|
Partial Approval
|
KEVIN SARGSYAN
|
|
PLUMBING-Rough
|
11/15/2023
|
Approved
|
KEVIN SARGSYAN
|
|
Insulation
|
11/20/2023
|
Approved
|
KEVIN SARGSYAN
|
|
Drywall Nailing
|
12/15/2023
|
Partial Approval
|
STEPHANIE SWANSON
|
|
Drywall Nailing
|
1/10/2024
|
Approved
|
KEVIN SARGSYAN
|
|
Interior/Exterior Lathing
|
2/16/2024
|
Approved
|
KEVIN SARGSYAN
|
|
Gas Test
|
8/28/2024
|
Approved
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Final
|
9/4/2024
|
Not Ready for Inspection
|
KEVIN SARGSYAN
|
|
PLUMBING-Final
|
9/4/2024
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Smoke Detectors
|
9/4/2024
|
Approved
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Final
|
9/6/2024
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
PLUMBING-Final
|
9/6/2024
|
Approved
|
KEVIN SARGSYAN
|
|
ELECTRICAL-Final
|
9/9/2024
|
Approved
|
KEVIN SARGSYAN
|
|
HVAC-Final
|
9/9/2024
|
Approved
|
KEVIN SARGSYAN
|
|
BUILDING-Rough-Frame
|
9/24/2024
|
Approved
|
KEVIN SARGSYAN
|
|
Final
|
9/24/2024
|
Corrections Issued
|
KEVIN SARGSYAN
|
|
Footing/Foundation/Slab
|
9/24/2024
|
Approved
|
KEVIN SARGSYAN
|
|
Green Building Final
|
9/24/2024
|
Approved
|
KEVIN SARGSYAN
|
|
SGSOV-Seismic Gas S/O Valve
|
9/24/2024
|
SGSOV Approved
|
KEVIN SARGSYAN
|
|
Structural Steel Frame
|
9/24/2024
|
Approved
|
KEVIN SARGSYAN
|
|
Final
|
9/26/2024
|
OK to Issue CofO
|
JESUS RODRIGUEZ
|