824 E MARCO PL 90291
Certificate Information: 824 E MARCO PL 90291
- Application / Permit
- 21014-30000-05300
- Plan Check / Job No.
- B21WL04663
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story addition (1,744 sf) to (e) single story SFD (848), add an att. 2-car garage (402 sf)
- Permit Issued
- Issued on 5/27/2022
- Issuing Office
- Current Status
- CofO Issued on 11/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | REZA HAGHIGHAT |
| Corrections Issued | 11/8/2021 | REZA HAGHIGHAT |
| Quality Review Completed | 11/17/2021 | TARIK SAOUD |
| Plan Check Approved | 5/4/2022 | REZA HAGHIGHAT |
| Issued | 5/27/2022 | APPLICANT |
| Building Plans Picked Up | 6/2/2022 | APPLICANT |
| CofO in Progress | 11/14/2023 | HERBERT GIRON |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
| CofO Issued | 11/14/2023 | DANIEL ORRANTE |
| Permit Finaled | 11/14/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 3/22/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 4/11/2022 | TRACY TATE |
| Eng Process Fee Ord 176,300 | Cleared | 4/12/2022 | TRACY TATE |
| Sewer availability | Cleared | 4/12/2022 | TRACY TATE |
| Coastal Zone | Cleared | 4/13/2022 | RICHARD REASER |
| Specific Plan | Cleared | 4/13/2022 | RICHARD REASER |
| ZA Case | Cleared | 4/13/2022 | RICHARD REASER |
| ZA Case | Cleared | 4/13/2022 | RICHARD REASER |
| ZA Case | Cleared | 4/13/2022 | RICHARD REASER |
| ZI | Cleared | 4/13/2022 | RICHARD REASER |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/19/2022 | Partial Inspection | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 7/27/2022 | Partial Approval | DAVID FEILER |
| Footing/Foundation/Slab | 8/10/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/31/2022 | Partial Approval | DAVID FEILER |
| Insulation | 8/31/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 8/31/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 9/2/2022 | Partial Approval | DAVID FEILER |
| Insulation | 9/2/2022 | Not Ready for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Partial Approval | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 10/21/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 12/7/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 1/9/2023 | Approved | EVAN COOPER |
| BUILDING-Rough-Frame | 2/14/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Deputy Wood Construction | 2/14/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/14/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 2/14/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 2/14/2023 | Conditional Approval | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 3/24/2023 | Approved | EVAN COOPER |
| Green Building Rough | 3/24/2023 | Approved | EVAN COOPER |
| Insulation | 3/24/2023 | Corrections Issued | EVAN COOPER |
| Shower Pan | 3/24/2023 | Approved | EVAN COOPER |
| Verify Sprinkler Sign Off | 3/24/2023 | Approved | EVAN COOPER |
| Insulation | 3/30/2023 | Approved | RICHARD STEINBACH |
| Drywall Nailing | 4/7/2023 | Approved | JEREMY TODD |
| Interior/Exterior Lathing | 4/7/2023 | Approved | JEREMY TODD |
| Footing/Foundation/Slab | 5/26/2023 | Approved | HERBERT GIRON |
| Gas Test | 9/14/2023 | Approved | TEMISTOCLES CAAL |
| HVAC-Final | 10/3/2023 | Approved | HERBERT GIRON |
| PLUMBING-Final | 10/10/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 10/11/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Rough | 10/24/2023 | Approved | HERBERT GIRON |
| Final | 11/1/2023 | Corrections Issued | HERBERT GIRON |
| Green Building Final | 11/1/2023 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 11/1/2023 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 11/1/2023 | Approved | HERBERT GIRON |
| Final | 11/3/2023 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 11/13/2023 | Approved | HERBERT GIRON |
| Final | 11/13/2023 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 11/13/2023 | Approved | HERBERT GIRON |