824 E MARCO PL 90291

Certificate Information: 824 E MARCO PL 90291

Application / Permit
21014-30000-05300
Plan Check / Job No.
B21WL04663
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story addition (1,744 sf) to (e) single story SFD (848), add an att. 2-car garage (402 sf)
Permit Issued
Issued on 5/27/2022
Issuing Office
Current Status
CofO Issued on 11/14/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/22/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 REZA HAGHIGHAT
Corrections Issued 11/8/2021 REZA HAGHIGHAT
Quality Review Completed 11/17/2021 TARIK SAOUD
Plan Check Approved 5/4/2022 REZA HAGHIGHAT
Issued 5/27/2022 APPLICANT
Building Plans Picked Up 6/2/2022 APPLICANT
CofO in Progress 11/14/2023 HERBERT GIRON
Permit Finaled 11/14/2023 DANIEL ORRANTE
CofO Issued 11/14/2023 DANIEL ORRANTE
Permit Finaled 11/14/2023 DANIEL ORRANTE

Permit Application Clearance Information

Low Impact Development Cleared 3/22/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 4/11/2022 TRACY TATE
Eng Process Fee Ord 176,300 Cleared 4/12/2022 TRACY TATE
Sewer availability Cleared 4/12/2022 TRACY TATE
Coastal Zone Cleared 4/13/2022 RICHARD REASER
Specific Plan Cleared 4/13/2022 RICHARD REASER
ZA Case Cleared 4/13/2022 RICHARD REASER
ZA Case Cleared 4/13/2022 RICHARD REASER
ZA Case Cleared 4/13/2022 RICHARD REASER
ZI Cleared 4/13/2022 RICHARD REASER

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/19/2022 Partial Inspection DAVID FEILER
Excavation/Setback/Form/Re-Bar 7/27/2022 Partial Approval DAVID FEILER
Footing/Foundation/Slab 8/10/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 8/31/2022 Partial Approval DAVID FEILER
Insulation 8/31/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 8/31/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 9/2/2022 Partial Approval DAVID FEILER
Insulation 9/2/2022 Not Ready for Inspection DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/4/2022 Partial Approval DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 10/21/2022 Partial Approval DAVID FEILER
PLUMBING-Rough 12/7/2022 Approved EVAN COOPER
ELECTRICAL-Rough 1/9/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 2/14/2023 Corrections Issued JESUS RODRIGUEZ
Deputy Wood Construction 2/14/2023 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 2/14/2023 Approved JESUS RODRIGUEZ
Green Building Rough 2/14/2023 Not Ready for Inspection JESUS RODRIGUEZ
HVAC-Rough 2/14/2023 Conditional Approval JESUS RODRIGUEZ
BUILDING-Rough-Frame 3/24/2023 Approved EVAN COOPER
Green Building Rough 3/24/2023 Approved EVAN COOPER
Insulation 3/24/2023 Corrections Issued EVAN COOPER
Shower Pan 3/24/2023 Approved EVAN COOPER
Verify Sprinkler Sign Off 3/24/2023 Approved EVAN COOPER
Insulation 3/30/2023 Approved RICHARD STEINBACH
Drywall Nailing 4/7/2023 Approved JEREMY TODD
Interior/Exterior Lathing 4/7/2023 Approved JEREMY TODD
Footing/Foundation/Slab 5/26/2023 Approved HERBERT GIRON
Gas Test 9/14/2023 Approved TEMISTOCLES CAAL
HVAC-Final 10/3/2023 Approved HERBERT GIRON
PLUMBING-Final 10/10/2023 Approved EVAN COOPER
ELECTRICAL-Final 10/11/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Rough 10/24/2023 Approved HERBERT GIRON
Final 11/1/2023 Corrections Issued HERBERT GIRON
Green Building Final 11/1/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/1/2023 SGSOV Approved HERBERT GIRON
Smoke Detectors 11/1/2023 Approved HERBERT GIRON
Final 11/3/2023 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 11/13/2023 Approved HERBERT GIRON
Final 11/13/2023 OK to Issue CofO HERBERT GIRON
Service/Power Release 11/13/2023 Approved HERBERT GIRON