11828 W STANWOOD DR 90066

Certificate Information: 11828 W STANWOOD DR 90066

Application / Permit
21014-30000-05282
Plan Check / Job No.
B21WL04641
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
2-story ADU addition (1158 sf) to (e) det. 2-car garage (361 sf) per LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/7/2022
Issuing Office
Current Status
CofO Issued on 1/4/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/21/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 REZA HAGHIGHAT
Corrections Issued 11/2/2021 REZA HAGHIGHAT
Quality Review Completed 11/15/2021 TARIK SAOUD
Applicant returned to address corrections 2/23/2022 REZA HAGHIGHAT
Building Plans Picked Up 2/25/2022 APPLICANT
Plan Check Approved 3/7/2022 REZA HAGHIGHAT
Issued 3/7/2022 APPLICANT
CofO in Progress 12/28/2022 JOHNNY MIRANDA
Permit Finaled 1/4/2023 DANIEL ORRANTE
CofO Issued 1/4/2023 DANIEL ORRANTE
Permit Finaled 1/4/2023 DANIEL ORRANTE

Permit Application Clearance Information

Hold Cleared 11/1/2021 JASON SHEETS
Construction near power lines Cleared 12/3/2021 RIDWAN HARDY
Specific Plan Cleared 12/9/2021 EDUARDO HERMOSO
Low Impact Development Cleared 12/22/2021 TA ANH
Address approval Cleared 12/28/2021 SAUL GARCIA
Roof/Waste drainage to street Cleared 12/28/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 12/29/2021 SAUL GARCIA
Sewer availability Cleared 12/29/2021 SAUL GARCIA
Hydrant and Access approval Cleared 1/20/2022 KURT CORRAL
GPI Written Notices Cleared 2/23/2022 REZA HAGHIGHAT
Grading Pre-Inspection Cleared 2/23/2022 REZA HAGHIGHAT

Contact Information

Contractor Owner-Builder       ,
Engineer Berkoz,, Ertunga; Lic. No.: S2504 4665 ELLENITA AVE      TARZANA, CA 91356

Inspector Information

KIRK SANDERS, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI
ARAM AVEDISIAN, (310) 914-3896 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/5/2022 Corrections Issued JOHNNY MIRANDA
PLUMBING-Rough 4/7/2022 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 4/15/2022 Partial Approval JOHNNY MIRANDA
Footing/Foundation/Slab 4/22/2022 Not Ready for Inspection JOHNNY MIRANDA
Excavation/Setback/Form/Re-Bar 4/25/2022 Approved JOHNNY MIRANDA
Floor/Roof Diaphrgm/Shear Wall 7/6/2022 Partial Approval JOHNNY MIRANDA
Green Building Rough 7/6/2022 Not Ready for Inspection JOHNNY MIRANDA
ELECTRICAL-Rough 8/18/2022 Corrections Issued JOHNNY MIRANDA
BUILDING-Rough-Frame 8/23/2022 Partial Approval JOHNNY MIRANDA
ELECTRICAL-Rough 8/23/2022 Approved JOHNNY MIRANDA
Green Building Rough 8/23/2022 Not Ready for Inspection JOHNNY MIRANDA
HVAC-Rough 8/23/2022 Approved JOHNNY MIRANDA
PLUMBING-Rough 8/23/2022 Approved JOHNNY MIRANDA
BUILDING-Rough-Frame 8/30/2022 Approved JOHNNY MIRANDA
Green Building Rough 8/30/2022 Approved JOHNNY MIRANDA
Insulation 8/30/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 8/30/2022 Partial Approval JOHNNY MIRANDA
Shower Pan 8/30/2022 Approved JOHNNY MIRANDA
Drywall Nailing 9/6/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 9/6/2022 Not Ready for Inspection JOHNNY MIRANDA
Gas Test 9/14/2022 Approved JOHNNY MIRANDA
Interior/Exterior Lathing 9/14/2022 Approved JOHNNY MIRANDA
ELECTRICAL-Final 11/29/2022 Approved JESUS RODRIGUEZ
Final 11/29/2022 Corrections Issued JESUS RODRIGUEZ
Footing/Foundation/Slab 11/29/2022 Approved JESUS RODRIGUEZ
Green Building Final 11/29/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 11/29/2022 Approved JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/29/2022 SGSOV Not Ready JESUS RODRIGUEZ
Service/Power Release 11/29/2022 Corrections Issued JESUS RODRIGUEZ
Sewer 11/29/2022 Approved JESUS RODRIGUEZ
Smoke Detectors 11/29/2022 Approved JESUS RODRIGUEZ
HVAC-Final 11/30/2022 Not Ready for Inspection ASHLEY THOMPSON
Final 12/22/2022 Corrections Issued JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Not Ready JOHNNY MIRANDA
Final 12/27/2022 OK to Issue CofO JOHNNY MIRANDA
HVAC-Final 12/27/2022 Approved JOHNNY MIRANDA
SGSOV-Seismic Gas S/O Valve 12/27/2022 SGSOV Approved JOHNNY MIRANDA