10728 W LE CONTE AVE 90024
Certificate Information: 10728 W LE CONTE AVE 90024
- Application / Permit
- 21014-30000-05221
- Plan Check / Job No.
- B21WL04576
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION & CONVERSION OF (E) GARAGE INTO AN ADU.
- Permit Issued
- Issued on 6/22/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/30/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/22/2021 | RICHARD GARCIA |
| Corrections Issued | 10/24/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 12/28/2021 | RICHARD GARCIA |
| Applicant returned to address corrections | 2/12/2022 | RICHARD GARCIA |
| Applicant returned to address corrections | 3/27/2022 | JASON JANGADA |
| Applicant returned to address corrections | 5/27/2022 | RICHARD GARCIA |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| Plan Check Approved | 6/3/2022 | RICHARD GARCIA |
| Issued | 6/22/2022 | APPLICANT |
| Permit Finaled | 7/30/2024 | DANIEL ORRANTE |
| CofO Issued | 7/30/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/30/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 11/10/2021 | VASIL MIHALEV |
| Eng Process Fee Ord 176,300 | Cleared | 3/8/2022 | JENSON LEE |
| Address approval | Cleared | 3/21/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 3/21/2022 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 3/21/2022 | ANTHONY MAINEZ |
| Specific Plan | Cleared | 3/21/2022 | FREDDY GARCIA |
| Specific Plan | Cleared | 3/21/2022 | FREDDY GARCIA |
Contact Information
| Contractor | Ludamark Construction Inc; Lic. No.: 1039132-B | 10630 MOUNTAIR AVE TUJUNGA, CA 91042 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/18/2023 | Partial Approval | BRENDAN LOONEY |
| Special/Order Compliance | 5/18/2023 | Corrections Issued | BRENDAN LOONEY |
| Deputy Drilled-In Anchors | 5/19/2023 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 5/23/2023 | Approved | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 7/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 7/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/12/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 7/20/2023 | Partial Approval | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 7/20/2023 | Conditional Approval | STEPHANIE SWANSON |
| HVAC-Final | 7/20/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 7/20/2023 | Conditional Approval | STEPHANIE SWANSON |
| PLUMBING-Rough | 7/20/2023 | Approved | STEPHANIE SWANSON |
| Insulation | 7/28/2023 | Approved | STEPHANIE SWANSON |
| Insulation | 7/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 7/28/2023 | Partial Approval | STEPHANIE SWANSON |
| Deputy Drilled-In Anchors | 8/11/2023 | Conditional Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 8/28/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 8/28/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 8/28/2023 | Approved | STEPHANIE SWANSON |
| Green Building Rough | 8/28/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 9/11/2023 | Approved | MICHAEL PELHAM |
| Interior/Exterior Lathing | 9/19/2023 | Partial Approval | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 5/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| Final | 5/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 5/17/2024 | Approved | STEPHANIE SWANSON |
| HVAC-Final | 5/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 5/17/2024 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 5/17/2024 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 5/17/2024 | Approved | STEPHANIE SWANSON |
| Final | 7/18/2024 | Corrections Issued | STEPHANIE SWANSON |
| ELECTRICAL-Final | 7/25/2024 | Approved | STEPHANIE SWANSON |
| Final | 7/25/2024 | Partial Approval | STEPHANIE SWANSON |
| HVAC-Final | 7/25/2024 | Approved | STEPHANIE SWANSON |
| Final | 7/29/2024 | Conditional Approval | STEPHANIE SWANSON |