1065 E AMOROSO PL 90291
Certificate Information: 1065 E AMOROSO PL 90291
- Application / Permit
- 21014-30000-05207
- Plan Check / Job No.
- B21WL04563
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Major remodel, 2nd story and 2 car garage addition to (E) 1 story SFD.
- Permit Issued
- Issued on 3/15/2022
- Issuing Office
- Current Status
- CofO Issued on 5/24/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | VLADIMIR ARUTYUNYAN |
| Corrections Issued | 11/29/2021 | VLADIMIR ARUTYUNYAN |
| Quality Review Completed | 11/30/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 1/31/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/15/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 2/18/2022 | CHIHARU SUZUKI |
| Applicant returned to address corrections | 3/3/2022 | CHIHARU SUZUKI |
| Plan Check Approved | 3/15/2022 | CHIHARU SUZUKI |
| Issued | 3/15/2022 | APPLICANT |
| Building Plans Picked Up | 3/18/2022 | APPLICANT |
| CofO in Progress | 5/19/2023 | EVAN COOPER |
| Permit Finaled | 5/24/2023 | DANIEL ORRANTE |
| CofO Issued | 5/24/2023 | DANIEL ORRANTE |
| Permit Finaled | 5/24/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Low Impact Development | Cleared | 12/12/2021 | MICHAEL SCADUTO |
| Permit | Cleared | 12/13/2021 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | JOSE HERNANDEZ |
| Roof/Waste drainage to street | Cleared | 12/22/2021 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 12/22/2021 | JOSE HERNANDEZ |
| Trees in Parkway | Cleared | 12/29/2021 | ADALBERTO VERA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | Zepeda General Building; Lic. No.: 1028796-B | 9525 HUNT AVE SOUTH GATE, CA 90280 |
| Engineer | Namdar,, Mansour Tom; Lic. No.: S2976 | 16867 SEVERO PLACE ENCINO, CA 91436 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/6/2022 | Partial Approval | DAVID FEILER |
| Excavation/Setback/Form/Re-Bar | 4/22/2022 | Approved | DAVID FEILER |
| Footing/Foundation/Slab | 4/22/2022 | Approved | DAVID FEILER |
| Deputy Wood Construction | 5/5/2022 | No Access for Inspection | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 5/6/2022 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 8/25/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 8/25/2022 | Partial Approval | DAVID FEILER |
| PLUMBING-Rough | 8/25/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 8/26/2022 | Approved | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Approved | DAVID FEILER |
| Special/Order Compliance | 8/30/2022 | Partial Inspection | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 9/8/2022 | Approved | DAVID FEILER |
| Green Building Rough | 9/8/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 9/8/2022 | Corrections Issued | DAVID FEILER |
| Verify Sprinkler Sign Off | 9/8/2022 | Approved | DAVID FEILER |
| Insulation | 9/13/2022 | Corrections Issued | DAVID FEILER |
| Interior/Exterior Lathing | 9/13/2022 | Not Ready for Inspection | DAVID FEILER |
| Insulation | 9/15/2022 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 9/21/2022 | Approved | JESUS RODRIGUEZ |
| Shower Pan | 10/14/2022 | Partial Inspection | DAVID FEILER |
| Shower Pan | 10/18/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 10/31/2022 | Approved | DAVID FEILER |
| Gas Test | 1/3/2023 | Approved | EVAN COOPER |
| ELECTRICAL-Final | 5/8/2023 | Approved | EVAN COOPER |
| PLUMBING-Final | 5/8/2023 | Corrections Issued | EVAN COOPER |
| HVAC-Final | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 5/11/2023 | Approved | JESUS RODRIGUEZ |
| Final | 5/17/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 5/17/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 5/17/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 5/17/2023 | Approved | EVAN COOPER |
| Final | 5/18/2023 | OK to Issue CofO | EVAN COOPER |
| Service/Power Release | 5/18/2023 | Approved | EVAN COOPER |