2917 S BEVERLY DR 90034

Certificate Information: 2917 S BEVERLY DR 90034

Application / Permit
21014-30000-05206
Plan Check / Job No.
B21WL04561
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
2-story house addition and alteration. Fully equipped w/fire sprinklres NFPA 13D
Permit Issued
Issued on 3/2/2022
Issuing Office
Current Status
CofO Issued on 3/21/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 ALFREDO JARA
Corrections Issued 11/1/2021 ALFREDO JARA
Quality Review Completed 11/15/2021 TARIK SAOUD
Plan Check Approved 2/23/2022 ALFREDO JARA
Issued 3/2/2022 APPLICANT
Building Plans Picked Up 3/4/2022 APPLICANT
CofO in Progress 3/20/2023 ASHLEY THOMPSON
Permit Finaled 3/21/2023 DANIEL ORRANTE
CofO Issued 3/21/2023 DANIEL ORRANTE
Permit Finaled 3/21/2023 DANIEL ORRANTE

Permit Application Clearance Information

Permit Cleared 11/5/2021 DINAH GARIN
Eng Process Fee Ord 176,300 Cleared 11/9/2021 DINAH GARIN
Sewer availability Cleared 11/9/2021 DINAH GARIN
ZA Case Cleared 1/10/2022 RYAN LY
Low Impact Development Cleared 1/18/2022 MARCO SANCHEZ
Roof/Waste drainage to street Cleared 1/20/2022 DINAH GARIN
Trees in Parkway Cleared 1/27/2022 ADALBERTO VERA
GPI Written Notices Cleared 2/23/2022 ALFREDO JARA
Grading Pre-Inspection Cleared 2/23/2022 ALFREDO JARA

Contact Information

Architect Walters,, Jonathan A; Lic. No.: C33220 4634 LAURELGROVE AVENUE      STUDIO CITY, CA 91604
Contractor T J C Home Builders Llc; Lic. No.: 1025507-B 26880 ALISO VIEJO PKWY STE 100      ALISO VIEJO, CA 92656
Engineer De, Leon, Cynthia Aguilar; Lic. No.: C31604 8061 SAN MATEO CIR      BUENA PARK, CA 90620
Engineer Nguyen,, Huan Ngoc; Lic. No.: C64238 13831 TYPEE WAY      IRVINE, CA 92620

Inspector Information

ASHLEY THOMPSON, (310) 914-3897 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/25/2022 Partial Inspection KEVIN SARGSYAN
PLUMBING-Rough 5/2/2022 Partial Approval KEVIN SARGSYAN
Sewer 5/2/2022 Approved KEVIN SARGSYAN
Footing/Foundation/Slab 5/11/2022 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 5/18/2022 Partial Approval KEVIN SARGSYAN
Footing/Foundation/Slab 5/27/2022 Partial Approval KEVIN SARGSYAN
Underground Mechanical 6/9/2022 Partial Approval KEVIN SARGSYAN
Underground Mechanical 6/15/2022 Corrections Issued KEVIN SARGSYAN
Underground Mechanical 6/20/2022 Corrections Issued DAVID FEILER
Floor/Roof Diaphrgm/Shear Wall 6/28/2022 Corrections Issued KEVIN SARGSYAN
Underground Mechanical 6/28/2022 Approved KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Partial Approval KEVIN SARGSYAN
Deputy Wood Construction 8/4/2022 No Access for Inspection KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 8/5/2022 No Access for Inspection OGANES TARAKHCHYAN
Floor/Roof Diaphrgm/Shear Wall 8/8/2022 Not Ready for Inspection OGANES TARAKHCHYAN
PLUMBING-Rough 8/29/2022 Approved EVAN COOPER
Special/Order Compliance 8/29/2022 Partial Inspection CLAYTON GRAHAM
HVAC-Rough 9/7/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/12/2022 Corrections Issued JOHN KIDWELL
Shower Pan 9/15/2022 Approved JOHN KIDWELL
Special/Order Compliance 9/19/2022 Corrections Issued MICHAEL PELHAM
Deputy Wood Construction 9/20/2022 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Rough 9/21/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 9/21/2022 Partial Approval OGANES TARAKHCHYAN
BUILDING-Rough-Frame 10/14/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 10/14/2022 Approved OGANES TARAKHCHYAN
Insulation 10/31/2022 Approved OGANES TARAKHCHYAN
Drywall Nailing 11/9/2022 Approved OGANES TARAKHCHYAN
Interior/Exterior Lathing 11/9/2022 Partial Approval OGANES TARAKHCHYAN
Deputy Wood Construction 12/12/2022 Conditional Approval MICHAEL PELHAM
ELECTRICAL-Final 2/3/2023 Corrections Issued ASHLEY THOMPSON
Final 2/3/2023 Corrections Issued ASHLEY THOMPSON
Footing/Foundation/Slab 2/3/2023 Approved ASHLEY THOMPSON
Green Building Final 2/3/2023 Not Ready for Inspection ASHLEY THOMPSON
HVAC-Final 2/3/2023 Corrections Issued ASHLEY THOMPSON
PLUMBING-Final 2/3/2023 Corrections Issued ASHLEY THOMPSON
SGSOV-Seismic Gas S/O Valve 2/3/2023 SGSOV Approved ASHLEY THOMPSON
Smoke Detectors 2/3/2023 Approved ASHLEY THOMPSON
ELECTRICAL-Final 3/1/2023 Corrections Issued ASHLEY THOMPSON
Green Building Final 3/1/2023 Corrections Issued ASHLEY THOMPSON
HVAC-Final 3/1/2023 Approved ASHLEY THOMPSON
PLUMBING-Final 3/1/2023 Not Ready for Inspection ASHLEY THOMPSON
ELECTRICAL-Final 3/7/2023 Approved STEPHANIE SWANSON
Final 3/7/2023 Corrections Issued STEPHANIE SWANSON
Green Building Final 3/7/2023 Approved STEPHANIE SWANSON
PLUMBING-Final 3/7/2023 Approved STEPHANIE SWANSON
Final 3/10/2023 Partial Approval ASHLEY THOMPSON
Gas Test 3/10/2023 Approved ASHLEY THOMPSON
Final 3/20/2023 Conditional Approval ASHLEY THOMPSON
Service/Power Release 3/20/2023 Approved ASHLEY THOMPSON