2917 S BEVERLY DR 90034
Certificate Information: 2917 S BEVERLY DR 90034
- Application / Permit
- 21014-30000-05206
- Plan Check / Job No.
- B21WL04561
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 2-story house addition and alteration. Fully equipped w/fire sprinklres NFPA 13D
- Permit Issued
- Issued on 3/2/2022
- Issuing Office
- Current Status
- CofO Issued on 3/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | ALFREDO JARA |
| Corrections Issued | 11/1/2021 | ALFREDO JARA |
| Quality Review Completed | 11/15/2021 | TARIK SAOUD |
| Plan Check Approved | 2/23/2022 | ALFREDO JARA |
| Issued | 3/2/2022 | APPLICANT |
| Building Plans Picked Up | 3/4/2022 | APPLICANT |
| CofO in Progress | 3/20/2023 | ASHLEY THOMPSON |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
| CofO Issued | 3/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 3/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Permit | Cleared | 11/5/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | DINAH GARIN |
| Sewer availability | Cleared | 11/9/2021 | DINAH GARIN |
| ZA Case | Cleared | 1/10/2022 | RYAN LY |
| Low Impact Development | Cleared | 1/18/2022 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 1/20/2022 | DINAH GARIN |
| Trees in Parkway | Cleared | 1/27/2022 | ADALBERTO VERA |
| GPI Written Notices | Cleared | 2/23/2022 | ALFREDO JARA |
| Grading Pre-Inspection | Cleared | 2/23/2022 | ALFREDO JARA |
Contact Information
| Architect | Walters,, Jonathan A; Lic. No.: C33220 | 4634 LAURELGROVE AVENUE STUDIO CITY, CA 91604 |
| Contractor | T J C Home Builders Llc; Lic. No.: 1025507-B | 26880 ALISO VIEJO PKWY STE 100 ALISO VIEJO, CA 92656 |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Nguyen,, Huan Ngoc; Lic. No.: C64238 | 13831 TYPEE WAY IRVINE, CA 92620 |
Inspector Information
| ASHLEY THOMPSON, (310) 914-3897 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/25/2022 | Partial Inspection | KEVIN SARGSYAN |
| PLUMBING-Rough | 5/2/2022 | Partial Approval | KEVIN SARGSYAN |
| Sewer | 5/2/2022 | Approved | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/11/2022 | Corrections Issued | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/18/2022 | Partial Approval | KEVIN SARGSYAN |
| Footing/Foundation/Slab | 5/27/2022 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 6/9/2022 | Partial Approval | KEVIN SARGSYAN |
| Underground Mechanical | 6/15/2022 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 6/20/2022 | Corrections Issued | DAVID FEILER |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Corrections Issued | KEVIN SARGSYAN |
| Underground Mechanical | 6/28/2022 | Approved | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Partial Approval | KEVIN SARGSYAN |
| Deputy Wood Construction | 8/4/2022 | No Access for Inspection | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 8/5/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2022 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 8/29/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 8/29/2022 | Partial Inspection | CLAYTON GRAHAM |
| HVAC-Rough | 9/7/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/12/2022 | Corrections Issued | JOHN KIDWELL |
| Shower Pan | 9/15/2022 | Approved | JOHN KIDWELL |
| Special/Order Compliance | 9/19/2022 | Corrections Issued | MICHAEL PELHAM |
| Deputy Wood Construction | 9/20/2022 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Rough | 9/21/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 9/21/2022 | Partial Approval | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 10/14/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 10/14/2022 | Approved | OGANES TARAKHCHYAN |
| Insulation | 10/31/2022 | Approved | OGANES TARAKHCHYAN |
| Drywall Nailing | 11/9/2022 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 11/9/2022 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 12/12/2022 | Conditional Approval | MICHAEL PELHAM |
| ELECTRICAL-Final | 2/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| Final | 2/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| Footing/Foundation/Slab | 2/3/2023 | Approved | ASHLEY THOMPSON |
| Green Building Final | 2/3/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| HVAC-Final | 2/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| PLUMBING-Final | 2/3/2023 | Corrections Issued | ASHLEY THOMPSON |
| SGSOV-Seismic Gas S/O Valve | 2/3/2023 | SGSOV Approved | ASHLEY THOMPSON |
| Smoke Detectors | 2/3/2023 | Approved | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/1/2023 | Corrections Issued | ASHLEY THOMPSON |
| Green Building Final | 3/1/2023 | Corrections Issued | ASHLEY THOMPSON |
| HVAC-Final | 3/1/2023 | Approved | ASHLEY THOMPSON |
| PLUMBING-Final | 3/1/2023 | Not Ready for Inspection | ASHLEY THOMPSON |
| ELECTRICAL-Final | 3/7/2023 | Approved | STEPHANIE SWANSON |
| Final | 3/7/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 3/7/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 3/7/2023 | Approved | STEPHANIE SWANSON |
| Final | 3/10/2023 | Partial Approval | ASHLEY THOMPSON |
| Gas Test | 3/10/2023 | Approved | ASHLEY THOMPSON |
| Final | 3/20/2023 | Conditional Approval | ASHLEY THOMPSON |
| Service/Power Release | 3/20/2023 | Approved | ASHLEY THOMPSON |