8057 S KENTWOOD AVE 90045

Certificate Information: 8057 S KENTWOOD AVE 90045

Application / Permit
21014-30000-05189
Plan Check / Job No.
B21WL04544
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Remodel, Ground Floor and 2-Story Addition to an (E) 1-Story S.F.D
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
CofO Issued on 4/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/19/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 DAVID CASTILLO
Corrections Issued 11/3/2021 DAVID CASTILLO
Quality Review Completed 11/17/2021 TARIK SAOUD
Building Plans Picked Up 12/10/2021 APPLICANT
Applicant returned to address corrections 3/4/2022 DAVID CASTILLO
Plan Check Approved 3/25/2022 DAVID CASTILLO
Issued 4/13/2022 APPLICANT
CofO in Progress 3/9/2023 ANDREW BEELI
CofO in Progress 3/9/2023 JOHN MATTILLO
Permit Finaled 4/3/2023 BRUCE TODD
CofO Issued 4/3/2023 BRUCE TODD
Permit Finaled 4/3/2023 BRUCE TODD

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/2/2021 DINAH GARIN
Permit Cleared 12/10/2021 ANTHONY MAINEZ
Sewer availability Cleared 12/14/2021 ANTHONY MAINEZ
Trees in Parkway Cleared 12/14/2021 ADALBERTO VERA
Grading Pre-Inspection Cleared 12/16/2021 SERGIO VALENZUELA
Low Impact Development Cleared 1/27/2022 ANDRES COVARRUBIAS
Roof/Waste drainage to street Cleared 2/10/2022 TRACY TATE

Contact Information

Architect Noteware,, Brian Arthur; Lic. No.: C21514 845 20TH STREET, #106      SANTA MONICA, CA 90403
Contractor Owner-Builder       ,

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 5/20/2022 Conditional Approval MARIAN PODPORA
Deputy Drilled-In Anchors 5/23/2022 Conditional Approval JOHN MATTILLO
Excavation/Setback/Form/Re-Bar 5/26/2022 Conditional Approval MARIAN PODPORA
BUILDING-Rough-Frame 6/10/2022 Conditional Approval MARIAN PODPORA
Footing/Foundation/Slab 6/10/2022 Conditional Approval MARIAN PODPORA
Underground Mechanical 6/10/2022 Partial Approval MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 6/17/2022 Conditional Approval MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 6/22/2022 Partial Approval MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 6/30/2022 Corrections Issued JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 8/24/2022 Corrections Issued JOHN MATTILLO
PLUMBING-Rough 8/24/2022 Approved JOHN MATTILLO
Floor/Roof Diaphrgm/Shear Wall 8/30/2022 Corrections Issued MARIAN PODPORA
ELECTRICAL-Rough 9/14/2022 Not Ready for Inspection MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 9/14/2022 Conditional Approval MARIAN PODPORA
HVAC-Rough 9/14/2022 Not Ready for Inspection MARIAN PODPORA
ELECTRICAL-Rough 9/20/2022 Partial Approval MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 9/20/2022 Partial Approval MARIAN PODPORA
HVAC-Rough 9/20/2022 Corrections Issued MARIAN PODPORA
BUILDING-Rough-Frame 9/28/2022 Corrections Issued MARIAN PODPORA
Green Building Rough 9/28/2022 Corrections Issued MARIAN PODPORA
HVAC-Rough 9/28/2022 Not Ready for Inspection MARIAN PODPORA
Underground Mechanical 9/30/2022 Partial Approval MARIAN PODPORA
HVAC-Rough 10/4/2022 Partial Approval MARIAN PODPORA
Underground Mechanical 10/4/2022 Partial Approval MARIAN PODPORA
BUILDING-Rough-Frame 10/12/2022 Partial Approval MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Partial Approval MARIAN PODPORA
Green Building Rough 10/12/2022 Approved MARIAN PODPORA
Shower Pan 10/12/2022 Approved MARIAN PODPORA
Wood Frame 10/12/2022 Partial Approval MARIAN PODPORA
Interior/Exterior Lathing 10/21/2022 Partial Approval MARIAN PODPORA
Floor/Roof Diaphrgm/Shear Wall 10/31/2022 Approved RYAN BARNES
Insulation 10/31/2022 Approved RYAN BARNES
Interior/Exterior Lathing 10/31/2022 Conditional Approval RYAN BARNES
Wood Frame 10/31/2022 Approved RYAN BARNES
Drywall Nailing 11/4/2022 Approved MARIAN PODPORA
Interior/Exterior Lathing 11/4/2022 Approved MARIAN PODPORA
ELECTRICAL-Rough 11/14/2022 Partial Approval MARIAN PODPORA
Interior/Exterior Lathing 11/14/2022 Approved MARIAN PODPORA
BUILDING-Rough-Frame 12/6/2022 Approved MARIAN PODPORA
Underground Mechanical 1/17/2023 Corrections Issued JOHN MATTILLO
PLUMBING-Final 2/3/2023 Conditional Approval RYAN BARNES
HVAC-Final 2/7/2023 Approved ANDREW BEELI
PLUMBING-Final 2/7/2023 Approved ANDREW BEELI
Service/Power Release 2/7/2023 Approved ANDREW BEELI
ELECTRICAL-Final 2/16/2023 Corrections Issued ANDREW BEELI
Final 2/16/2023 Not Ready for Inspection ANDREW BEELI
Footing/Foundation/Slab 2/16/2023 Approved ANDREW BEELI
Green Building Final 2/16/2023 Approved ANDREW BEELI
SGSOV-Seismic Gas S/O Valve 2/16/2023 SGSOV Approved ANDREW BEELI
Smoke Detectors 2/16/2023 Not Ready for Inspection ANDREW BEELI
ELECTRICAL-Final 2/21/2023 Approved ANDREW BEELI
Final 2/21/2023 Partial Approval ANDREW BEELI
Gas Test 2/21/2023 Approved ANDREW BEELI
Smoke Detectors 2/21/2023 Approved ANDREW BEELI
Final 3/9/2023 OK to Issue CofO ANDREW BEELI