8057 S KENTWOOD AVE 90045
Certificate Information: 8057 S KENTWOOD AVE 90045
- Application / Permit
- 21014-30000-05189
- Plan Check / Job No.
- B21WL04544
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Remodel, Ground Floor and 2-Story Addition to an (E) 1-Story S.F.D
- Permit Issued
- Issued on 4/13/2022
- Issuing Office
- Current Status
- CofO Issued on 4/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/19/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | DAVID CASTILLO |
| Corrections Issued | 11/3/2021 | DAVID CASTILLO |
| Quality Review Completed | 11/17/2021 | TARIK SAOUD |
| Building Plans Picked Up | 12/10/2021 | APPLICANT |
| Applicant returned to address corrections | 3/4/2022 | DAVID CASTILLO |
| Plan Check Approved | 3/25/2022 | DAVID CASTILLO |
| Issued | 4/13/2022 | APPLICANT |
| CofO in Progress | 3/9/2023 | ANDREW BEELI |
| CofO in Progress | 3/9/2023 | JOHN MATTILLO |
| Permit Finaled | 4/3/2023 | BRUCE TODD |
| CofO Issued | 4/3/2023 | BRUCE TODD |
| Permit Finaled | 4/3/2023 | BRUCE TODD |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2021 | DINAH GARIN |
| Permit | Cleared | 12/10/2021 | ANTHONY MAINEZ |
| Sewer availability | Cleared | 12/14/2021 | ANTHONY MAINEZ |
| Trees in Parkway | Cleared | 12/14/2021 | ADALBERTO VERA |
| Grading Pre-Inspection | Cleared | 12/16/2021 | SERGIO VALENZUELA |
| Low Impact Development | Cleared | 1/27/2022 | ANDRES COVARRUBIAS |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | TRACY TATE |
Contact Information
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| ROBERT GARTH, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN MATTILLO, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PEDRO RIVERA, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| EUSEBIO GUZMAN, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL REECE, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
| ANDREW BEELI, (213) 978-4498 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 5/20/2022 | Conditional Approval | MARIAN PODPORA |
| Deputy Drilled-In Anchors | 5/23/2022 | Conditional Approval | JOHN MATTILLO |
| Excavation/Setback/Form/Re-Bar | 5/26/2022 | Conditional Approval | MARIAN PODPORA |
| BUILDING-Rough-Frame | 6/10/2022 | Conditional Approval | MARIAN PODPORA |
| Footing/Foundation/Slab | 6/10/2022 | Conditional Approval | MARIAN PODPORA |
| Underground Mechanical | 6/10/2022 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 6/17/2022 | Conditional Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 6/30/2022 | Corrections Issued | JOHN MATTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Corrections Issued | JOHN MATTILLO |
| PLUMBING-Rough | 8/24/2022 | Approved | JOHN MATTILLO |
| Floor/Roof Diaphrgm/Shear Wall | 8/30/2022 | Corrections Issued | MARIAN PODPORA |
| ELECTRICAL-Rough | 9/14/2022 | Not Ready for Inspection | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 9/14/2022 | Conditional Approval | MARIAN PODPORA |
| HVAC-Rough | 9/14/2022 | Not Ready for Inspection | MARIAN PODPORA |
| ELECTRICAL-Rough | 9/20/2022 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Partial Approval | MARIAN PODPORA |
| HVAC-Rough | 9/20/2022 | Corrections Issued | MARIAN PODPORA |
| BUILDING-Rough-Frame | 9/28/2022 | Corrections Issued | MARIAN PODPORA |
| Green Building Rough | 9/28/2022 | Corrections Issued | MARIAN PODPORA |
| HVAC-Rough | 9/28/2022 | Not Ready for Inspection | MARIAN PODPORA |
| Underground Mechanical | 9/30/2022 | Partial Approval | MARIAN PODPORA |
| HVAC-Rough | 10/4/2022 | Partial Approval | MARIAN PODPORA |
| Underground Mechanical | 10/4/2022 | Partial Approval | MARIAN PODPORA |
| BUILDING-Rough-Frame | 10/12/2022 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | MARIAN PODPORA |
| Green Building Rough | 10/12/2022 | Approved | MARIAN PODPORA |
| Shower Pan | 10/12/2022 | Approved | MARIAN PODPORA |
| Wood Frame | 10/12/2022 | Partial Approval | MARIAN PODPORA |
| Interior/Exterior Lathing | 10/21/2022 | Partial Approval | MARIAN PODPORA |
| Floor/Roof Diaphrgm/Shear Wall | 10/31/2022 | Approved | RYAN BARNES |
| Insulation | 10/31/2022 | Approved | RYAN BARNES |
| Interior/Exterior Lathing | 10/31/2022 | Conditional Approval | RYAN BARNES |
| Wood Frame | 10/31/2022 | Approved | RYAN BARNES |
| Drywall Nailing | 11/4/2022 | Approved | MARIAN PODPORA |
| Interior/Exterior Lathing | 11/4/2022 | Approved | MARIAN PODPORA |
| ELECTRICAL-Rough | 11/14/2022 | Partial Approval | MARIAN PODPORA |
| Interior/Exterior Lathing | 11/14/2022 | Approved | MARIAN PODPORA |
| BUILDING-Rough-Frame | 12/6/2022 | Approved | MARIAN PODPORA |
| Underground Mechanical | 1/17/2023 | Corrections Issued | JOHN MATTILLO |
| PLUMBING-Final | 2/3/2023 | Conditional Approval | RYAN BARNES |
| HVAC-Final | 2/7/2023 | Approved | ANDREW BEELI |
| PLUMBING-Final | 2/7/2023 | Approved | ANDREW BEELI |
| Service/Power Release | 2/7/2023 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 2/16/2023 | Corrections Issued | ANDREW BEELI |
| Final | 2/16/2023 | Not Ready for Inspection | ANDREW BEELI |
| Footing/Foundation/Slab | 2/16/2023 | Approved | ANDREW BEELI |
| Green Building Final | 2/16/2023 | Approved | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 2/16/2023 | SGSOV Approved | ANDREW BEELI |
| Smoke Detectors | 2/16/2023 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Final | 2/21/2023 | Approved | ANDREW BEELI |
| Final | 2/21/2023 | Partial Approval | ANDREW BEELI |
| Gas Test | 2/21/2023 | Approved | ANDREW BEELI |
| Smoke Detectors | 2/21/2023 | Approved | ANDREW BEELI |
| Final | 3/9/2023 | OK to Issue CofO | ANDREW BEELI |