448 N ROCKINGHAM AVE 90049

Certificate Information: 448 N ROCKINGHAM AVE 90049

Application / Permit
21014-30000-05188
Plan Check / Job No.
B21WL04539
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Addition, Remodel, and Structural Alteration to an (E) 2-Story S.F.D (N) Patio Cover, Re-Roof, and (N) Windows and Doors
Permit Issued
Issued on 3/1/2023
Issuing Office
West Los Angeles
Current Status
Issued on 3/1/2023
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 10/20/2021 APPLICANT
Assigned to Plan Check Engineer 11/10/2021 DAVID CASTILLO
Corrections Issued 11/18/2021 DAVID CASTILLO
Quality Review Completed 11/29/2021 TARIK SAOUD
Applicant returned to address corrections 8/29/2022 DAVID CASTILLO
Building Plans Picked Up 12/23/2022 APPLICANT
Applicant returned to address corrections 1/20/2023 DAVID CASTILLO
Plan Check Approved 2/27/2023 DAVID CASTILLO
Issued 3/1/2023 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/12/2023 ANTHONY MAINEZ
Sewer availability Cleared 1/12/2023 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 2/3/2023 ANTHONY MAINEZ
Grading Pre-Inspection Cleared 2/3/2023 KIRK LINKLATER

Contact Information

Contractor Momo Design Group Inc; Lic. No.: 1037903-B 30 EDELMAN      IRVINE, CA 92618
Engineer Monjezi,, Daryoosh; Lic. No.: C42625 PO BOX 39      LAKE FOREST, CA 92609
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/25/2023 No Access for Inspection KEVIN SARGSYAN
Footing/Foundation/Slab 9/25/2023 No Access for Inspection KEVIN SARGSYAN
Pre-Inspection 9/25/2023 No Access for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/27/2023 Corrections Issued KEVIN SARGSYAN
Footing/Foundation/Slab 11/27/2023 Not Ready for Inspection KEVIN SARGSYAN
Pre-Inspection 11/27/2023 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/28/2023 Not Ready for Inspection KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 11/30/2023 Corrections Issued KEVIN SARGSYAN
Excavation/Setback/Form/Re-Bar 12/4/2023 Conditional Approval KEVIN SARGSYAN
Footing/Foundation/Slab 3/10/2025 Corrections Issued HERBERT GIRON
PLUMBING-Rough 5/1/2025 Corrections Issued KEVIN SARGSYAN
BUILDING-Rough-Frame 5/5/2025 Partial Approval MEL KHACHATOURIAN
Green Building Rough 5/5/2025 Not Ready for Inspection MEL KHACHATOURIAN
PLUMBING-Rough 5/5/2025 Partial Approval MEL KHACHATOURIAN
BUILDING-Rough-Frame 5/7/2025 Partial Approval ARAM AVEDISIAN
Insulation 5/7/2025 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 5/20/2025 Corrections Issued KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 5/23/2025 Partial Approval KEVIN SARGSYAN