1110 N BUNDY DR 90049
Certificate Information: 1110 N BUNDY DR 90049
- Application / Permit
- 21014-30000-05134
- Plan Check / Job No.
- B21WL04493
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- remodeling & addition to (e) 2-story house
- Permit Issued
- Issued on 3/3/2022
- Issuing Office
- Current Status
- CofO Issued on 6/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | KHUONG TRUONG |
| Corrections Issued | 10/23/2021 | KHUONG TRUONG |
| Quality Review Completed | 11/4/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 1/27/2022 | KHUONG TRUONG |
| Applicant returned to address corrections | 2/9/2022 | KHUONG TRUONG |
| Plan Check Approved | 2/11/2022 | KHUONG TRUONG |
| Issued | 3/3/2022 | APPLICANT |
| Building Plans Picked Up | 3/7/2022 | APPLICANT |
| CofO in Progress | 6/9/2023 | CARLOS MATAMOROS |
| Permit Finaled | 6/13/2023 | DANIEL ORRANTE |
| CofO Issued | 6/13/2023 | DANIEL ORRANTE |
| Permit Finaled | 6/13/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| ZA Case | Cleared | 11/24/2021 | LAUREN PADICK |
| Eng Process Fee Ord 176,300 | Cleared | 11/29/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 11/29/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 11/29/2021 | HISASHI KOBAYAKAWA |
| Permit | Cleared | 12/1/2021 | HISASHI KOBAYAKAWA |
| Grading Pre-Inspection | Cleared | 1/27/2022 | KHUONG TRUONG |
| Trees in Parkway | Cleared | 2/3/2022 | ADALBERTO VERA |
| Watercourse | Cleared | 2/10/2022 | MAHELET GEBEYHU |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | De, Leon, Cynthia Aguilar; Lic. No.: C31604 | 8061 SAN MATEO CIR BUENA PARK, CA 90620 |
| Engineer | Sayah,, Daniel H; Lic. No.: C67905 | 15233 VENTURA BLVD STE 1130 SHERMAN OAKS, CA 91403 |
Inspector Information
| EVAN COOPER, (310) 914-3861 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 4/21/2022 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 4/22/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Excavation/Setback/Form/Re-Bar | 4/25/2022 | Approved | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 4/25/2022 | Approved | CHRISTOPHER WILSON |
| Deputy Steel/Welding | 5/2/2022 | Approved | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/22/2022 | Partial Approval | CARLOS MATAMOROS |
| FLOOD-Proofing Certificate | 6/22/2022 | Approved | CARLOS MATAMOROS |
| Floor/Roof Diaphrgm/Shear Wall | 6/22/2022 | Approved | CARLOS MATAMOROS |
| Green Building Rough | 6/22/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Steel/Welding | 7/20/2022 | Conditional Approval | MICHAEL PELHAM |
| PLUMBING-Rough | 9/1/2022 | Partial Approval | CARLOS MATAMOROS |
| HVAC-Rough | 9/2/2022 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 9/9/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 9/9/2022 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 9/9/2022 | Approved | CARLOS MATAMOROS |
| Deputy Wood Construction | 9/12/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 9/13/2022 | Approved | CARLOS MATAMOROS |
| Shower Pan | 9/13/2022 | Approved | CARLOS MATAMOROS |
| Interior/Exterior Lathing | 10/21/2022 | Approved | CARLOS MATAMOROS |
| PLUMBING-Rough | 10/21/2022 | Approved | CARLOS MATAMOROS |
| Drywall Nailing | 11/7/2022 | Partial Approval | CARLOS MATAMOROS |
| Drywall Nailing | 11/15/2022 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 3/23/2023 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 3/30/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Final | 3/30/2023 | Approved | CARLOS MATAMOROS |
| PLUMBING-Final | 3/30/2023 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Final | 4/4/2023 | Approved | CARLOS MATAMOROS |
| Gas Test | 4/4/2023 | Approved | CARLOS MATAMOROS |
| Service/Power Release | 4/4/2023 | Approved | CARLOS MATAMOROS |
| BUILDING-Rough-Frame | 4/14/2023 | Approved | CARLOS MATAMOROS |
| Final | 4/14/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 4/14/2023 | Approved | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 4/14/2023 | SGSOV Approved | CARLOS MATAMOROS |
| Smoke Detectors | 4/14/2023 | Approved | CARLOS MATAMOROS |
| Final | 5/20/2023 | Corrections Issued | MICHAEL PELHAM |
| Final | 6/9/2023 | OK to Issue CofO | CARLOS MATAMOROS |