854 N LAS LOMAS AVE 90272

Certificate Information: 854 N LAS LOMAS AVE 90272

Application / Permit
21014-30000-05131
Plan Check / Job No.
B21WL04479
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
Ground floor addition to an existing 2-story S.F.D
Permit Issued
Issued on 8/22/2022
Issuing Office
Valley
Current Status
CofO Issued on 2/20/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/11/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 FELIPE HERNANDEZ
Corrections Issued 10/29/2021 FELIPE HERNANDEZ
Quality Review Completed 11/8/2021 TARIK SAOUD
Applicant returned to address corrections 3/1/2022 FELIPE HERNANDEZ
Applicant returned to address corrections 4/29/2022 FELIPE HERNANDEZ
Plan Check Approved 7/21/2022 FELIPE HERNANDEZ
Building Plans Picked Up 7/21/2022 APPLICANT
Issued 8/22/2022 APPLICANT
CofO in Progress 2/16/2024 EVAN COOPER
Permit Finaled 2/20/2024 DANIEL ORRANTE
CofO Issued 2/20/2024 DANIEL ORRANTE
Permit Finaled 2/20/2024 DANIEL ORRANTE

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/28/2022 STEVEN JIN
Roof/Waste drainage to street Cleared 1/28/2022 STEVEN JIN
Coastal Zone Cleared 2/9/2022 RICHARD REASER
GPI Written Notices Cleared 7/21/2022 FELIPE HERNANDEZ
Grading Pre-Inspection Cleared 7/21/2022 FELIPE HERNANDEZ

Contact Information

Contractor Arnold'S Remodeling; Lic. No.: 929036-B 8146 LONGRIDGE AVENUE      NORTH HOLLYWOOD, CA 91605
Engineer Almalla,, Dean; Lic. No.: C58024 15053 VENTURA BLVD STE 205      SHERMAN OAKS, CA 91403
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311

Inspector Information

DANIEL VERA, (213) 577-9924 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Piling/Pier/Caisson 9/27/2022 Corrections Issued BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 9/30/2022 Not Ready for Inspection BRENDAN LOONEY
Piling/Pier/Caisson 9/30/2022 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 10/21/2022 Approved ANDREW NAVE
PLUMBING-Rough 10/21/2022 Partial Approval ANDREW NAVE
Piling/Pier/Caisson 10/21/2022 Approved ANDREW NAVE
PLUMBING-Rough 11/15/2022 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 11/21/2022 Partial Approval BRENDAN LOONEY
ELECTRICAL-Rough 11/21/2022 Approved BRENDAN LOONEY
Green Building Rough 11/21/2022 Not Ready for Inspection BRENDAN LOONEY
HVAC-Rough 11/21/2022 Approved BRENDAN LOONEY
PLUMBING-Rough 11/21/2022 Not Ready for Inspection BRENDAN LOONEY
Floor/Roof Diaphrgm/Shear Wall 11/23/2022 Corrections Issued BRENDAN LOONEY
Insulation 11/23/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 11/23/2022 Corrections Issued BRENDAN LOONEY
ELECTRICAL-Rough 11/30/2022 Approved BRENDAN LOONEY
PLUMBING-Rough 11/30/2022 Approved BRENDAN LOONEY
Insulation 12/15/2022 Corrections Issued BRENDAN LOONEY
Interior/Exterior Lathing 12/15/2022 Partial Approval BRENDAN LOONEY
Shower Pan 12/23/2022 Approved KENNETH NAGLE
Drywall Nailing 12/29/2022 Approved BRENDAN LOONEY
Green Building Rough 12/29/2022 Approved BRENDAN LOONEY
Interior/Exterior Lathing 1/4/2023 Partial Approval CLAYTON GRAHAM
BUILDING-Rough-Frame 8/22/2023 Approved EVAN COOPER
Final 8/22/2023 Corrections Issued EVAN COOPER
Green Building Final 8/22/2023 Approved EVAN COOPER
SGSOV-Seismic Gas S/O Valve 8/22/2023 SGSOV Approved EVAN COOPER
Smoke Detectors 8/22/2023 Approved EVAN COOPER
PLUMBING-Rough 1/12/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 2/15/2024 Approved EVAN COOPER
Final 2/15/2024 OK to Issue CofO EVAN COOPER
HVAC-Final 2/15/2024 Approved EVAN COOPER
PLUMBING-Final 2/15/2024 Approved EVAN COOPER