854 N LAS LOMAS AVE 90272
Certificate Information: 854 N LAS LOMAS AVE 90272
- Application / Permit
- 21014-30000-05131
- Plan Check / Job No.
- B21WL04479
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Ground floor addition to an existing 2-story S.F.D
- Permit Issued
- Issued on 8/22/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/20/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/11/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | FELIPE HERNANDEZ |
| Corrections Issued | 10/29/2021 | FELIPE HERNANDEZ |
| Quality Review Completed | 11/8/2021 | TARIK SAOUD |
| Applicant returned to address corrections | 3/1/2022 | FELIPE HERNANDEZ |
| Applicant returned to address corrections | 4/29/2022 | FELIPE HERNANDEZ |
| Plan Check Approved | 7/21/2022 | FELIPE HERNANDEZ |
| Building Plans Picked Up | 7/21/2022 | APPLICANT |
| Issued | 8/22/2022 | APPLICANT |
| CofO in Progress | 2/16/2024 | EVAN COOPER |
| Permit Finaled | 2/20/2024 | DANIEL ORRANTE |
| CofO Issued | 2/20/2024 | DANIEL ORRANTE |
| Permit Finaled | 2/20/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2022 | STEVEN JIN |
| Roof/Waste drainage to street | Cleared | 1/28/2022 | STEVEN JIN |
| Coastal Zone | Cleared | 2/9/2022 | RICHARD REASER |
| GPI Written Notices | Cleared | 7/21/2022 | FELIPE HERNANDEZ |
| Grading Pre-Inspection | Cleared | 7/21/2022 | FELIPE HERNANDEZ |
Contact Information
| Contractor | Arnold'S Remodeling; Lic. No.: 929036-B | 8146 LONGRIDGE AVENUE NORTH HOLLYWOOD, CA 91605 |
| Engineer | Almalla,, Dean; Lic. No.: C58024 | 15053 VENTURA BLVD STE 205 SHERMAN OAKS, CA 91403 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 9/27/2022 | Corrections Issued | BRENDAN LOONEY |
| Excavation/Setback/Form/Re-Bar | 9/30/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Piling/Pier/Caisson | 9/30/2022 | Corrections Issued | BRENDAN LOONEY |
| Footing/Foundation/Slab | 10/21/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 10/21/2022 | Partial Approval | ANDREW NAVE |
| Piling/Pier/Caisson | 10/21/2022 | Approved | ANDREW NAVE |
| PLUMBING-Rough | 11/15/2022 | Partial Approval | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/21/2022 | Partial Approval | BRENDAN LOONEY |
| ELECTRICAL-Rough | 11/21/2022 | Approved | BRENDAN LOONEY |
| Green Building Rough | 11/21/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| HVAC-Rough | 11/21/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 11/21/2022 | Not Ready for Inspection | BRENDAN LOONEY |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Corrections Issued | BRENDAN LOONEY |
| Insulation | 11/23/2022 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Rough | 11/23/2022 | Corrections Issued | BRENDAN LOONEY |
| ELECTRICAL-Rough | 11/30/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 11/30/2022 | Approved | BRENDAN LOONEY |
| Insulation | 12/15/2022 | Corrections Issued | BRENDAN LOONEY |
| Interior/Exterior Lathing | 12/15/2022 | Partial Approval | BRENDAN LOONEY |
| Shower Pan | 12/23/2022 | Approved | KENNETH NAGLE |
| Drywall Nailing | 12/29/2022 | Approved | BRENDAN LOONEY |
| Green Building Rough | 12/29/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 1/4/2023 | Partial Approval | CLAYTON GRAHAM |
| BUILDING-Rough-Frame | 8/22/2023 | Approved | EVAN COOPER |
| Final | 8/22/2023 | Corrections Issued | EVAN COOPER |
| Green Building Final | 8/22/2023 | Approved | EVAN COOPER |
| SGSOV-Seismic Gas S/O Valve | 8/22/2023 | SGSOV Approved | EVAN COOPER |
| Smoke Detectors | 8/22/2023 | Approved | EVAN COOPER |
| PLUMBING-Rough | 1/12/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 2/15/2024 | Approved | EVAN COOPER |
| Final | 2/15/2024 | OK to Issue CofO | EVAN COOPER |
| HVAC-Final | 2/15/2024 | Approved | EVAN COOPER |
| PLUMBING-Final | 2/15/2024 | Approved | EVAN COOPER |